Preservation Management PPT
Preservation Management PPT
Implement Plan
维护保养计划
May
2023
Contents
1. Purpose
Inspection at Worksite
• Preservation Manager
• Preservation Engineer
• Yard Preservation Coordinator
• Yard Preservation Supervisor
• Yard Preservation Workforce Team
Organization Chart
Preservation Manager
Preservation
Engineer
Yard Preservation
Coordinator
Yard Preservation
Workforce Team
Responsibilities
Preservation Manager carries out the following activities:
• Manage and oversee the Preservation activities (including preparation & implementation
of tool, prior to Construction and CSU phases) 。
• Monitor and verify (with Preservation Coordinators & Engineers) that Preservation
database is available, consistent and ready for implementation at yard, take counter-
measures if necessary.
• Report on weekly and monthly basis to his management of the Preservation
management.
• Coordinate regular audit and corrective actions.
• Issue a weekly report, monitor work progress schedules and make the necessary
modifications in order to achieve deadlines and committed budget.
• Conduct on weekly basis Yard patrol related to preservation (including HSSE topics).
• Establish and ensure effective communication between all parties on the subject of the
preservation.
• Ensure the interface with the different parties involved in the preservation.
• Evaluate, allocate and assign preservation resources.
• Coordinate procurement of all preservative consumables required for all preservation
phases.
Responsibilities
Preservation Engineer carries out the following activities:
• Protective covers, plugs and coatings shall be renewed if not intact or missing.
• Rust preventative coatings applied on exterior machined and threaded surfaces.
• If vapor phase inhibitors or desiccants are used to protect the interiors of mechanical
equipment, vessels or machinery, the seals shall be examined when the equipment is
received.
• Nitrogen pressure on pressure equipment with Nitrogen filling.
• vapor seals shall be protected until the equipment is serviced for installation or pre-
commissioning.
• Special care shall be taken regarding the storage condition (temperature/Humidity of storage
requirements, location).
• Special attention must be paid for stainless steel (austenitic and martensitic) equipment that
can be exposed to salt water or salt spray or blowing salty-sand during storage at yard.
• Equipment stored outdoors will be positioned off the ground and above ground water pooling.
Preservation Implementation During Fabrication
Pipeline Preservation methods
• Closed Pipeline Preservation
• Opened Carbon Steel Pipeline
• Opened Stainless Pipeline
1 Closed Pipeline Nitrogen Nitrogen content Filled nitrogen and remain micro-positive
99.9% pressure (0.5~1.0 bar).
2 Opened Carbon Steel VPCI337 Cortec Spraying anti-rust agent VPCI-337 inside of
Pipeline pipeline and sealed with pipe Cap.
3 Opened Stainless Silicon 500g/Bag Placed desiccant bags at the bottom of end
Pipeline desiccant of the pipeline and sealed with pipe cap.
Preservation Implementation During Fabrication
Diagrammatic Drawing Of Nitrogen Preservation
Preservation Implementation During Fabrication
VPCI-337w anti-rust agent work flow
Preservation Implementation During Fabrication
Silicon desiccant and test paper
Preservation Implementation During Fabrication
Static Equipment Preservation
Static equipment includes non-rotary or non-mobile equipment without drive, such as tanks,
pressure vessels, atmospheric pressure vessels, drums, columns, heat exchanger, heaters,
filters.
4 Temperature Control Sensor Plastic bags, with drying Wrapped for delicate
Temperature Control Unit agent inside material
F&G Beacon
F&G Sounder
IECEX SPEAKER 25W WITH
1 INDIVIDUAL JUNCTION BOX VPCI126 Wrapped
Multipoint Temperature Transmitter
Actuator of instrument Valve
Multicore IECEX PAGA junction box
11 Soft plastic film Clear color 0.26x1.0MX30M Roll For external protection of Screen 、 indicator light etc.
12 Packing Tape Packing Tape Roll - Rubber Adhesive, Roll For external protection of Equipment and Instrument.
50mm x 33m
13 Polyethylene pipe end cap low temperature and low density Piece Preservation for pipe end.
14 Pack Stainless steel belt 16mm Stainless steel belt and Clamp Piece Preservation for seal of pipe end.
14 Plywood Plate Water resistant 5~10mm Sheet Preservation for flange face.
15 Denso Tape TM Roll Seal material
Cold wrap anticorrosive sealing tape
16 Preservation Label Self-adhesive waterproof anti-corrosion Piece Preservation mark
mate, 240mmX140mm
16 Dehumidifier If required