Porject Final Closure Report EX 03
Porject Final Closure Report EX 03
EX 03
DC 3
Closure Report
STTelemedia, Ambattur
ABOUT PROJECT
MAA 20 EX 03 is a Fit out for Tier III Data
center 4.7 MW extension Project
Build area : 54,650 Sqft
Location : Ambattur, Chennai
Project Timeline : 11 months (Apr 2021 – Feb 2022)
JLL’S SCOPE OF WORKS
DESIGN MANAGEMENT
CLOSE-OUT MANAGEMENT
• Design Coordination with all consultants
• Punch List De-snagging
• Limited to Technical Pre-Qualification
• Facility Commissioning
• Assist Contract Documentation Preparation
• As-Built Documentation
• Financial Close-out
5
6
JLL and STT Team
• Mr.
• Mr. • • Mr. Bala
• Mr. • Mr. • • •• Mr. • Mr. •
Mohanr
• Mr.
Mohan
Ajay • Mr.
Mr.
Nathan • Mr.
Mr. • Mr.
Mr.
Bala • Mr.
Mr. •Dhaksha
Mr.
Mr.
Jeffery
oop sadhasiv
Muthus Uday
Praveen •yogenda
Manikan
Mr. Vijay Vasigara
Narendr Mathew Prabhak
Mubara
Kathirav
Subrama
Krishnan Nirmal
Manath Nithin
Sabarish Karthick Jahangir
Sainath namoort
Jegan
na
Felix
Sivakum am
elvam shankar
GV rdan n
an Prasanth karan
anAli
niyam unai hy
Moorthy
ar
Manager
Manager
Director
Electrical
Electrical
Manager
Manager
Manager
-Manager
Manager
ELV Manager
Manager
ELV Manager
Construction
Construction
HSE Manager
Lead
HVAC
HVAC
HVAC
Manager
Manager
Planning
Project
MEP-
MEP-
MEP-
Project
Quality
Project
MEP-
T&C
T&C
Civil
Civil
HSE
HSE
HSE
HSE
MEP
ELV
Project Organization Chart
Mr. Mohan
Subramanian
Project Director
Mr. Jayachandran
Mr.
Mr. Bala Mr. Muthuselvam Mr. Praveen GV Mr. Mubarak Ali
Dhakshanamoorthy
EHS Manager- STT EHS Manager- STT EHS Manager- STT EHS Manager- STT HSE Manager- STT
Mr. Koteeswaran Mr. Sadam Hussain Mr. Rajesh Mr. Prasath Mr. Mahesh Mr. Pankaj
HSE Lead - Crescon HSE Officer - Siemens HSE Lead -8JCI HSE officer - S&W HSE Officer - Chubb HSE OffiCer - Kokban
Mr. Nathan
RESCUE TEAM EVACUATION TEAM FIRST AID TEAM FIRE FIGHTING TEAM HEAD COUNT TEAM
Respective Site
Mr. S Karthick Mr. Manibalan Mr. Karnan Mr. Pushpalingam
Incharges
9
Stake Holders & Contractors
10
• M/s. • M/s. • M/s.
M/s.
• M/s. • M/s.
• M/s.
M/s.
Sterling • M/s.
Johnson • M/s.
M/s. • M/s. • M/s.
Sieme
STTelem Siemen • M/s.
Schnei
HBL
Microso
and
Crescon s
Vertiv SGB
Jones
Datson Chubb
Trane • Stulz
Kokban
edia
ns s India Chola
der IDAI
ft Pvt
Wilson
India
India Control
India Lang
India
India India India
India
India Pvt Ltd MSRS
India
Ltd
India
Pvt
PvtLtd
Ltd India
Pvt Ltd Lasalle
Pvt
PvtLtd
Ltd Pvt Ltd Pvt Ltd
Pvt Ltd
PvtLtd
Ltd Pvt Ltd
Pvt Ltd Pvt
Consultant
Consultant
Contractor
Transformer
2250Kva
750Kva
User
750Kva
Provider
and
Security
Chiller
General
Panel
Control
sytems
CRAH
Client/
Access
Access
Contol
Battery
EPMS
Lease
PDU
UPS
PMC
T&C
HSE
DG
Fire
End
HT
UPS
Logisitics Plan - External
Cable
ACCESS 02 Collection
Pit
N
Routing
DG Worker
Rest Area screening
Dinning LOADING
Septic
Area POINT
tank
DOCKYARD
ACCESS 01
S a fe A
Hazardous
AMBULANCE
PARKING OHD Store
ssemb
Material
Store Septic
ly
Toilet tank
Diesel Emergency walk way
MAIN ENTR
& EXIT
Store
Scrap
Debris
SECURITY
FIRST AID
N
3
Emergency exit/
Vehicle
Access 01 movement area
Pedestrian
access
Access 02
Road Cross
Vehicle U turn
Emergency walk way
No Entry No Entry
Emergency
Assembly Point
12
Logisitics Plan - Ground Floor
Access 4
Costuction
access
DG Corridor
Access 4 GF,
Construction
D CAT
D CAT
Access to DG
MV Panel Room A, B
room
Access 5
Holding Room
CAT
D
Transformer Room
13
Logisitics Plan - First Floor
Access 4
Access 5 1F to
freight lift and
fire staircase
Constuction
access
Access 4,
Access 5
Construction
staff
D CAT
ANR
MMR
Access 3 Access
14
6
Logisitics Plan - Third Floor
Access 4
Access 5 2F to
freight lift and
emergency
staircase
D CAT
IDF
Pedestrian
Pathway
Access 5
Access 4 2F,
Construction
15
Emergency Plan - Third Floor
Access 04
N
H-2
BATTERY H-2
ROOM ELEC ROOM Access no 4,5
DC HALL 02 Emergency Exits
NOT IN OUR SCOPE
H-2 H-2
BATTERY ELEC ROOM
ROOM Access
Access 05
Sanitizer Point
Drinking Water
Point
16
Emergency Plan - Fourth Floor
Access 01
N
H-2
BATTERY H-2
ROOM ELEC ROOM Access no 4,5
DC HALL 02 Emergency Exits
H-2 H-2
BATTERY
ROOM
ELEC ROOM Construction
Access
Access 02
Sanitizer Point
Fire Point
Drinking Water
Point
17
5M- Site
Management
1. Man
2. Machine
3. Material
4. Methodology
5. Management of
Work Permit system
5M- Site
Management
1. Man
2. Machine
3. Material
4. Methodology
5. Management of
Work Permit system
5M- Site
Management
1. Man
2. Machine
3. Material
4. Methodology
5. Management of
Work Permit system
5M- Site
Management
1. Man
2. Machine
3. Material
4. Methodology
5. Management of
Work Permit system
5M- Site
Management
1. Man
2. Machine
3. Material
4. Methodology
5. Management of
Work Permit system
HSE Dcouments for Pre Submission
PTW
In addition to the permit daily tool box talks
proof(Job specific) and PPE checklist is attached
while raising the permit.
Key Metrics
HSE STATISTICS Cumulative Man-hours
TB
Induction Trainings No of Trained
T 832766
779030
May 12 40 1 21
693278
June 60 155 6 55
Septembe
182 167 14 232
r
275880
Cumulative Monthly
January 169 102 13 229
February 69 69 7 156
Audit
Key Metrics
5
4 4 4
HSE STATISTICS
17 0
May June 0
July 0
August September October NovemberDecember January
15
12
TBT
285
5
4
2
a0y e0
n ly s0t be
r er be
r
be
r ry r0y
M Ju Ju gu tob ua rua 185 188
Au em Oc em ce
m a n
eb 182
pt ov De
J F 169
Se N
130 129
60
12
May June July August September October NovemberDecember January
• Fatal
0
• Major Incident
Key Metrics
0 HSE Trainings
• Minor Incident
0 15
16
HSE STATISTICS
0 • First Aid 11
10 10
8
•Induction
1 Near Misses
4
• Unsafe
167 act and
1311
155
Conditions
140
2
136 March April May June July 0
August September October November
127
100 102
81
40
299
1622
1503
1313
191
1105
120 150
133
120
120
717
109
78 104
630
88
87
52 86
446
75
31 74
375
62
62
52
50
179
34
30
27
27
26
26
21
60
5 16
15
14
2 14
14
ril ay st r er er r ry ry
10
10
ne ly be be
p M Ju Ju gu ob ob ua ua
5
5
A t t r
2
u m m n
A te Oc Oc ce J a eb
March Apr i l May June Jul y Aug ust Se pte m be r O c tobe r Nove m be r S ep De F
Non- Compliances
Lagging Indicator on HRA Non-Compliances
Open/ Close Status Observation Categories
Grand Total
196 158 134
196
122 97 78 158
97
78
Grand Total 422 422
68 65 62
74
58
38 34 33
Hot Work 28 31
25
Barrice and Signages
17% 16% Electrical 5 5s
Hazardous Material es
s
g es ace ical ent nts tion ct
k l t
or eria igh pin ilur
g e n g
tio iftin dlin
g E
PP men gen
t e
10% gr a p tr m e a j e W t e e a a i
n S ec ron m v b in L an
Work at Height
E
nd d S
i g ed El ip xca g O Hot a tH ke lF ge Hy
a fin nvi Equ E i n u s M rk a use ura llum a lH a na nd
25% Housekeeping ss e a Conn E l l o o Ho ced
I u M a
20% ce nd Fa rd W an te lfar
e
Ac arri
c
l sa a za Pro M a s
o H n d e
12% Unsafe Act Unsafe Conditions B To la
W W
ria
e
at
Raised Closed M
Milestones
Project Milestones based on the key highlights of the MAA 20
EX 03
RT - PCR Tests done site wide and Vaccination drive conducted to achive All worker and staff temperature monitoring, disinfection for vehicles,
double Vaccination for worker and staff. social distancing marking done at entrance and partitions made in office
setup.
MM.DD.20XX
Equipment/ Workplace Signage
More Convenient
Signages, hazard markings, barricades done in work location to Lift Operator, emergency contact details displayed freight lift.
denote hazardous environment and to avoid unauthorized entry. Electrical equipments provided with LEW stickers.
MM.DD.20XX
Posters and signages
More Convenient
COVID Awareness signages palced at entry, Mandatory, warning signages Awareness signages placed inside floor, fire points with signages and
placed inside floor. markings displayed.
Less Convenient
MM.DD.20XX ADD A FOOTER
Vehicle movement and
pedestrian access
More Convenient
Pedestrian access and crossing demarcation done with hard barricade Pedestrian and vehicle access segregation at site entry, Minimum space
and signages. All vehicle provided with flagman during marching of 1.5m width provided for pedestrain access throughout the site.
Less Convenient
MM.DD.20XX ADD A FOOTER
Emergency Prepardness
Ambulance ispection done on daily basis, Ambulance driver and first aider Site wide Emergency Mock drill conducted periodically
made available for 24x7 service, Green lights provided at exit points
Less Convenient
MM.DD.20XX ADD A FOOTER
Welfare Facilities
More Convenient
Touch free drinking water points maintined at multiple locations. Dining area maintained with social distancing markings and first aider
Restrooms and hand wash stationed maintained. room maintained.
MM.DD.20XX
Work Permit/ Tool Box/ Trainings
More Convenient
Competitor 2
Logo
Work permit system training conduted for all engineers and safrty Job specfic trainings and third party trainings organized for worker and
executives, daily tool box meeting conduted by the respective engineer in staff, competent and trained rescures made available on site.
assisstance with safety executives.
MM.DD.20XX
Man Screening
More Convenient
Daily temperature monitoring done during entry and exit, Security cabin Class room training session organized for workers and sample equipments
provided with CCTV monitoring system, all workers entering the site used inside the site on displayed and are trained before entry for site
provided with job specific induction and marked on their passports. usage. Only worker above 18 allowed inside the site.
Less Convenient
MM.DD.20XX
Plant and Equipment
Less Convenient
MM.DD.20XX ADD A FOOTER
Electrical Equipment's
B license competent electrician will inspect all electrcial equipment and ELCB trip checks done on site and the time taken for the trip is recorded,
LEW sticker is provided after inspection, Earth resistance value checked at DG inspection done by licensed electrician
earth pits periodically.
Lifting Operation’s
More Convenient
Pre Job meeting conducted with all stake holders and the plan debriefed, Pre job meeting conduted for the worker before lifting activity. Pre lift
lifting activity done by competent lifting crew with zero load done to identify the seating location and SWL of the crane
Less Convenient
MM.DD.20XX
Hazardous Goods and Substances
Hazarodus material store under isolated room and conditions with MSDS Worker entering the enrgized room provided with shoe cover job specific
and COSHH displayed along with fire protection system. PPE’s and ventillation with ducts.
MM.DD.20XX
Hot Work
Hot work booths and welding screens used during welding and cutting Welding and cutting operation provided with booth signage and barricade,
operations worker provided with job specific PEE and fire watcher.
MM.DD.20XX
Work at Height
More Convenient
Competitor 1
Logo
Catch nets were installed for DG stack erection, trained rescue team made Platform scaffold erected inside the electrical rooms replacing mobile
available at site, vertigo tests done. WAH inside energized rooms with FRP scaffold to eleminating fall from height hazard.
ladders
Less Convenient
MM.DD.20XX
Confined Space
More Convenient
Click icon to add picture
Competitor 4
Logo
Confined space permit raised while working inside Shafts, external Each time before entry inti the confined space oxygen levels, illumination
ventillation systema provided for the shaft during worker occupancy levels checked
Competitor 5
Logo Competitor 6
Logo
Less Convenient
MM.DD.20XX
Civil Works
Material storage with proper barricade and signages, end caps provided Job specific PPE’s provided for braking and painting operations, hazard
for protruding rods, barricades privided for open spaces markings and signages placed to avoid unauthorized entry
MM.DD.20XX
Ground Disturbances
Access egress made clear and provided with barricade and signages to Sheet piling aand nets were placed to avoid soil slide from the sheets,
avoid slip trip and fall near excavated zones. entry restricted for unauthorised persons
MM.DD.20XX
Review Meetings
More Convenient
Weekly afety review meeting conducted with all vendors representatives, Committee meeting organized and conducted monthly for all contractors,
key highlights and look ahead discussed. on site review meeting conducted for all vendors.
Less Convenient
MM.DD.20XX
Motivational Programs
More Convenient
Each month all vendors conduct motivationall program for worker and staff Rewards and refreshments provided at the end of every motivational
program
MM.DD.20XX
Safety Campaign
More Convenient
Weekly saefty campins conduted by the vendor to create awareness Awareness on Reporting near miss safety campaign was conducted to
among worker and staff, Job specific campaigns conducted. encourage workers to come forward and report unseen nearmisses.
Less Convenient
MM.DD.20XX
Leadership Visit’s
More Convenient
Microsoft and its represtative site visits done during milestone Leadership site visit fro STT and GC along with other condtractors done on
achivements, MS representative weekly site visits and audits done. site monthly. Mr. Sumit Mukeeja conducted a audit on site.
Less Convenient
MM.DD.20XX
MS Representative Audits
Competitor 4
Logo
Medical facility, WAH, Electrical audit, emergency evacuation audited by Lifting audit and site inspections done by MS representative.
MS representative.
MM.DD.20XX
Sub-con evaluation
More Convenient
Vendor evaluation done on Monthly basis for each vendor on the five Review Meeting after the evaluation conduted for audit closure aling
acpects designed by microsoft with project and safety teams.
Competitor 3
Competitor 5
Logo
Logo
Less Convenient
MM.DD.20XX ADD A FOOTER
Training and Inspection
Competitor 2
Logo
External inspections and pre job lift checked outside the site, Third party Internal and third party trainings organized for workers and staff.
inspections and trainings conducted.
Competitor 3
Competitor 5
Logo Competitor 6
Logo
Logo
Vendor evaluation done on
MM.DD.20XX Monthly basis for each vendor on
ADD A FOOTER
the five acpects designed by
Energization Protocol
Energized are deep cleaning done LOTO provided on isolated equipments, Placards, SLD Energization flow along with emergency contact diplsyed on
rubber mats laid and signages dispalyed. site for all electrical energized panles, rubber glover used for working on
electrical equipments, exclusion zone makring and barricade provided
MM.DD.20XX
Load Test
External load banks placed under barricade to avoid unauthorized entry Load bank testing inside the floor is provided with barricade and
into the location and to avoid hot air vent exposure. signages to avoid unauthorized person from tampering the process.
MM.DD.20XX
Energization/ IST
IST meeting Organized by STT along with all vendors and consultants. All room access controlled with single point access, PQM testing done with
briefing done by IDAI Team. thermal guns used for temperaure monitoring. barricade and signages.
Arc flash suits are made available.
MM.DD.20XX
Post IST
More Convenient
Post IST images of DC Hall, electrical room, PAHU gallery and battery room Post IST team appreciation meeting and celebration.
Less Convenient
MM.DD.20XX
Deep Cleaning
WAH access provided for deep cleaning inside DC hall bove ceiling works, Walk ways above tile provided for standing and lifeline installed for
access egress provided wit illumination and signages. worker movement.
MM.DD.20XX
Team Refreshment Programs
Team outing planned to provide a break from the works, to regain focus Worker refreshment programs conducted on site to concentrate on
and team work. Staffs were awarded with gifts and cash prize. physical and mental welbeing of workers in form of excercises and Yoga.
MM.DD.20XX
SUMMARY
MAA 20 EX 03
4.7MW was handed over and was available for service from the month
of Feb 2022 without any harm, property damage and LTI in a safe
manner on time. A cumulative manhours of 8,32,766 Lakhs was
achieved during the course of the project.