Section I-1
Section I-1
Safety
Accident
Causes
Management IEC61508
Technical
Requirements
Safety Life
Cycle
Competence
of Persons
Certification
CFSE Exam Preparation: Section I-1
Identify
The safety lifecycle
approach, as
described in ISA
Verify Assess 84.01, IEC 61511,
and IEC 61508 is a
closed loop process.
Design
4
CFSE Exam Preparation: Section I-1
Terms
E/E/PE: Electrical / Electronic /
Programmable Electronic
PES: Programmable Electronic System
SRS: Safety Related System
RR: Risk Reduction (Facility)
EUC: Equipment Under Control
SF: Safety Function
SIL: Safety Integrity Level
FSM: Management of Functional Safety
SLC: Safety LifeCycle
CFSE Exam Preparation: Section I-1
Terms
Equipment under Control
The equipment, machinery, apparatus, or plant used
for manufacturing, process, transport, medical, or
other activities. The EUC control system is separate
and distinct from the EUC.
Safety Requirements Specification
Contains:
1. The Safety Functions that have to be carried out
by the safety related systems, and
2. The Safety Integrity Levels for the various Safety
functions.
CFSE Exam Preparation: Section I-1
Terms
Random Failures
A failure occurring at a random time, which results
from one or more of the possible degradation
mechanisms.
Systematic Failures
A failure related in a deterministic way to a certain
cause, which can only be eliminated by a modification
of the design or of the manufacturing process,
operational procedures, documentation,
or other relevant factors.
CFSE Exam Preparation: Section I-1
E/E/PES
Sensors Hardware &
Embedded Software Final
Elements
CFSE Exam Preparation: Section I-1
Terms
Safety Instrumented Function (SIF)
What to measure (sense)
What to do (actuate)
When to do (event logic)
How fast from measure to react (timing)
Loop 1
Logic
Solver
Loop 2
Loop 3
CFSE Exam Preparation: Section I-1
Terms
Safety Function - Example
Restrict fuel intake to reduce high speed
Supply coolant to reduce extreme temperature
Open value to relief excessive pressure
Direct 5 tons of escaping liquid to the waste
handling
Issue fire alarm and unlock fire water pumps
Dispatch emergency response team within
3 minutes
CFSE Exam Preparation: Section I-1
Overall Safety
4
Requirements
Safety Requirements
5
Allocation
maintenance, Covered by
S84.01
SIS Installation, Periodic
No SIS Functional Tests
Commissioning
Required?
and Pre-startup
Yes Acceptance Test Modify, SIS
Define Target Decommission? Decommissioning
SIL Decommission
Modify
ANALYSIS REALISATION OPERATION
CFSE Exam Preparation: Section I-1
Sub-
Operation and Maintenance
Sub-clause 15 OPERATION Sub-
clause
clause
Clause 5 Decommissioning 7, 12.7
6.2 Modification
Sub-clause 15.4 Sub-clause 16
13
CFSE Exam Preparation: Section I-1
“ANALYSIS” 2
Overall Scope
Definition
Phase 3
Hazard & Risk
Analysis
(End User/Contractor/
Overall Safety
Consultant) 4
Requirements
Safety Requirements
5
Allocation
Overall Installation
12
& Commissioning
Overall Safety
13
Validation
Architectural / Detail Design
SIL Verification - Fault Trees / Markov Models
Operation and Maintenance Planning
Validation Test Planning
Installation and Commissioning
Validation Testing
CFSE Exam Preparation: Section I-1
16 Decommissioning
Operation
Risk-based Maintenance
Periodic Inspection and Testing
Modification Process and Retrofit
Decommissioning
CFSE Exam Preparation: Section I-1
PART 2 PART 3
PART 6
Realisation phase for Realisation phase for
E/E/PE safety-related safety-related
systems software Guidelines for the
application of part 2 and 3 PART 7
PART 1 Overview of techniques
and measures
Installation and commissioning and safety validation of
E/E/PE safety-related systems
PART 1
Operation and maintenance, modification and retrofit,
decommissioning or disposal of Technical
E/E/PE safety-related systems
requirements
CFSE Exam Preparation: Section I-1 e
Safety Lifecycle
excellence in dependable automation
ida .com
Conceptual
Process Design Process Information
Event History
Identify
Potential Risks Potential Hazards
e ida.com
Layers of Protection excellence in dependable automation
PROBE Tool
Detail
e ida.com
FETCH Tool
Analyze Potential excellence in dependable automation
Safety
Database
Tolerable Risk Select Target Target SILs
Guidelines Develop non- SIL
SIS Layers e ida.com
excellence in dependable automation
DOCUMENT Template
Lifecycle
No
SIS Functional Description of each Safety
Requirements
Required? Exit
Allocation
Instrumented Function, Target SIL,
Safety
Yes Mitigated Hazards, Process parameters,
Logic, Bypass/Maintenance
Develop Safety requirements, Response time, etc
Specification
Select Relays, Fail-Safe Solid State, PLC, Safety
Technology PLC, Sensors, Final Elements
18 Modify Modify,
Decommission?
SIS
Decommissioning
Port Chambers, New
Zealand
Sarnia , Canada
CFSE Exam Preparation: Section I-1
19
CFSE Exam Preparation: Section I-1
SIL Selection
• Objective
– Specify the required risk reduction, or
Allocation of difference between existing and tolerable
Safety Functions risk levels – in terms of SIL
to Safety • Tasks
Instrumented
– Compare process risk against tolerable
Systems or Other
risk
Means of Risk
Reduction – Use decision guidelines to select required
risk reduction
Subclause 9 – Document selection process
20
CFSE Exam Preparation: Section I-1
Safety Requirements
Specification
• Objective
– Specify all requirements of SIS
Safety
Requirements
needed for detailed engineering and
Specification for process safety information purposes
the Safety • Tasks
Instrumented
System – Identify and describe safety functions
– Document SIL
Subclause 10
– Document action taken – Logic,
Cause and Effect Diagram, etc.
21
CFSE Exam Preparation: Section I-1
Conceptual /
Detailed Design
• Objective
– Select and configure equipment
Design and used in the SIS (including
Engineering of programming)
Safety
Instrumented • Tasks
System – Specify system technology and
architecture
Subclauses 11,
– Specify field instrumentation
12
– Configuration / Programming
– Select vendors, review bids
22
CFSE Exam Preparation: Section I-1
• Objective
– Install equipment, after acceptance
Installation,
Commissioning
testing, and prepare for operation
• Tasks
Subclauses 13
and 14 – Factory Acceptance Testing Field
and control room equipment
installation
– Confirm equipment operation
– Instrumentation Calibration
23
CFSE Exam Preparation: Section I-1
Safety Review
Validation
• Objectives
– Verify that the SIS is designed,
Validation installed, and operating according the
the Safety Requirements
Subclauses 13 • Tasks
– Verify operation of field instruments
– Validate logic and operation
– Verify SIL of installed equipment
– Produce OSHA and EPA required
documentation – Certifications if req.
24
CFSE Exam Preparation: Section I-1
Operation and
Maintenance
• Objective
– Operate and maintain the SIS so that
Operation and the specified SIL is maintained
Maintenance • Tasks
Subclause 15 – Establish procedures for operating
and maintaining the SIS
– Perform periodic function test on an
interval that allows the specified SIL
to be achieved with the installed
equipment
25
CFSE Exam Preparation: Section I-1
Modification and
Decommissioning
• Objective
– Ensure changes to the system are
Modification and safe and appropriately reviewed
Decommissioning
• Tasks
Subclauses 15.4 – Establish procedures for change
and 16
management
– Review safety functions prior to
taking an SIS out of service
26
CFSE Exam Preparation: Section I-1
Exercises
Safety Lifecycle
1. Explain, in general, how hazards that require a SIF for risk
reduction are identified.
28
CFSE Exam Preparation: Section I-1
Exercises (Key)
Safety Lifecycle
Explain the difference between conceptual design and detailed
design for SIS.
Conceptual design involves selecting the technology (e.g., PLC
vs. Relay) and architecture (1oo2 vs. 2oo3). Detailed design
involves selecting specific components (make and model) and
wiring and/or programming the physical equipment.
Provide an example of when decommissioning a safety
instrumented system could be hazardous.
If a single SIS contains a preponderance of SIF from a unit that
is being decommissioned, but also contains 1 or 2 SIF from a
unit that will remain in service. If the SIS were completely
decommissioned with the process unit, the SIF for other process
units would no longer exist, causing a hazard.
29
CFSE Exam Preparation: Section I-1
Exercises (Key)
Safety Lifecycle
Explain, in general, how hazards that require a SIF for risk
reduction are identified.
Some functions are identified by experience, these are existing
functions which should be marked on P&ID. Others are found
by systematic creative brainstorming exercises called Process
Hazards Analyses. (PHA)
How many safety integrity levels are defined in IEC 61511 or
ISA 84.01(select one of your choice)? What are the associated
probability of failure on demand ranges?
IEC 61511 has four levels, 1,2,3 and 4. ISA S84 has three levels,
1,2, and 3. The PFD ranges are as follows:
SIL1 – 0.10.01 SIL2 – 0.01 0.001
SIL3 – 0.001 0.0001 SIL4 – 0.0001 0.00001
30