SPPTChap012
SPPTChap012
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.
Chapter 12: Learning Objectives
You should be able to:
LO 12.1 Describe the conditions under which MRP is most
appropriate
LO 12.2 Describe the inputs, outputs, and nature of MRP
processing
LO 12.3 Explain how requirements in a master production schedule
are translated into material requirements for lower-level
items
LO 12.4 Discuss the benefits and requirements of MRP
LO 12.5 Describe some of the difficulties users have encountered
with MRP
LO 12.6 Describe MRP II and its benefits
LO 12.7 Explain how an MRP system is useful in capacity
requirements planning
LO 12.8 Describe ERP, what it provides, and its hidden costs
12-2
Dependent vs Independent Demand
LO 12-3
12.1
MRP
Material requirements planning
(MRP):
A computer-based information system that
translates master schedule requirements for
end items into time-phased requirements for
subassemblies, components, and raw
materials.
The MRP is designed to answer three
questions:
1. What is needed?
2. How much is needed?
3. When is it needed?
LO 12-4
12.2
Overview of MRP
LO 12-5
12.2
MRP Outputs: Primary
Primary Outputs
Planned orders
A schedule indicating the amount and timing of
future orders
Order releases
Authorizing the execution of planned orders
Changes
Revisions of the dates or quantities, or the
cancellation of orders
LO 12-6
12.2
MRP: Development
The MRP is based on the product structure tree
diagram
Requirements are determined level by level,
beginning with the end item and working down
the tree
The timing and quantity of each “parent” becomes the
basis for determining the timing and quantity of the
“children” items directly below it.
The “children” items then become the “parent” items for
the next level, and so on
LO 12-7
12.3
Example MRP
Shutter
Wood
Frames
sections
(2)
(4)
LO 12-8
12.3
Example MRP
LO 12-9
12.3
MRP Benefits
Enables managers to easily
determine the quantities of each component for a given order
size
To know when to release orders for each component
To be alerted when items need attention
Additional benefits
Low levels of in-process inventories
The ability to track material requirements
The ability to evaluate capacity requirements
A means of allocating production time
The ability to easily determine inventory usage via
backflushing
Exploding an end item’s BOM to determine the quantities of the
components that were used to make the item
LO 12-10
12.4
MRP Difficulties
Consequence of Inaccurate Data
Missing parts
Ordering incorrect numbers of items
Inability to stay on schedule
Other problems
Assumptions of constant lead times
Products being produced differently from the
BOM
Failure to alter a BOM when customizing a
product
Inaccurate forecasts
LO 12-11
12.5
MRP II
Manufacturing resources planning (MRP II)
Expanded approach to production resource planning,
involving other areas of the firm in the planning process
and enabling capacity requirements planning
Most MRP II systems have the capability of performing
simulation to answer a variety of “what if” questions so they
can gain a better appreciation of available options and their
consequences
LO 12-12
12.6
Capacity Requirements Planning
Capacity requirements planning (CRP)
The process of determining short-range capacity
requirements.
Inputs to capacity requirement planning
Planned-order releases for the MRP
Current shop loading
Routing information
Job time
Key outputs
Load reports for each work center
LO 12-13
12.7
Enterprise Resource Planning
Enterprise resource planning (ERP)
ERP was the next step in an evolution that began with
MRP and evolved into MRPII
ERP, like MRP II, typically has an MRP core
LO 12-14
12.8