ESR FEB 2022.....
ESR FEB 2022.....
ANTICIPATED EOT
NO. ANTICIPATED EOT - DESCRIPTIONS NO OF DAYS
1 EIW 30
Based on WP BL05
Plan 100.00%
Actual
67.20%
Ahead/Delay(+/-) = -32.80%
Financial Work Progress
FEBRUARY
JANUARY
DECEMBER 2021 2022
2022
Month Based on
Based on Based on
Revised
Revised Revised
WP BL05
WP BL04 WP BL05
TOTAL RM 16,172,962.33
Progress as of
25th February 2022
Based on WP BL05
Plan : 100.00%
Actual : 67.20%
Ahead/Delay(+/-) : -32.38%
WORK BREAKDOWN
STRUCTURES (WBS)
WORK BREAKDOWN STRUCTURES
3+450 0%
1+850 0
Tier 1 0% 100% 100% Tier 1 0% 100% 100%
Ground Treatment Works
2+115 to 2+415 to
Chainage 2+215 CH3+415 3+510 to 4+565 4+615 to 5+765 6+040to 6+325 6+380 to 6+660
Excavation (300mm ) 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0%
Filling sand (300mm) 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0%
Installation of Bamboo 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0%
Installation of Geotextile 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0%
Surcharge Filling works (earth fill) 100% 100% 100% 100% 80% 95% 80% 90% 50% 50% 0% 0%
31 6+749.338 75 0 0 0% 0% 0% 0%
6 - 6.754 km (LHS) 0%
DRAINAGE WORKS
RHS & LHS
Toe Drain Interceptor Drain Roadside Drain Bench/ Berm Drain Cascading Slope Drain
CH
RHS
% Workdone % Workdone % Workdone % Workdone % Workdone
5 - 6 km (RHS) 100%
6 - 6.754 km (RHS) 0%
RESOURCES PROGRESS
- MANPOWER SUMMARY
- MACHINERIES SUMMARY
- MATERIALS ON SITE
Manpower Summary
Feb
No. Material on site Jan 2022 2022/NO- Cumulative
CURRENT
1 90 0 7340
150 x 150mm R.C Precast Pile
2 0 0 630
250 x 250mm R.C Precast Pile
3 5 0 475
1500 mm Dia . Pipe Culvert (m)
4 0 0 75
900 mm Dia . Pipe Culvert
5 600mm Dia Spun Piles 0 0 96
CLOSE
MONITORING
REPORT
ACHIEVEMENT FOR THE MONTH OF FEBRUARY 2022
TOTAL ACHIEVEMEN
No ACTIVITIES PLAN (%) PLAN (RM) WORKDONE (%) WORDONE (RM) MACHINERIES
AMOUNT T
1 Piling for Civil Works
i 1500mm Dia Pipe -Culvert 17 -outlet side 22,500.00 70% 9,000.00 ACHIEVED 70.00% 9,000.00 PILING RIG -1
PILING RIG -1
iii Retainig Wall A 40,000.00 10% 4,000.00 NOT ACHIEVED 0.00% -
EXCAVATOR -1
6 Bridge Works
i Prestressed Concrete Girder Fabrication of Type 30 I-Beam
194,000.00 50% 97,000.00 NOT ACHIEVED 0.00%
876,300.00 4.708% 426,899.70 0.740% 119,400.00
ACHIEVEMENT :4/8
MILESTONE FOR THE MONTH OF MARCH 2022
MARCH 2022 MILESTONE
2 Retaining Wall
i Retaining Wall A 100% 32,000.00 PILING RIG -1
ii Retaining Wall B 40% 16,000.00 EXCAVATOR- 1
4 Geotechnical Works
a Ground Treatment Works
i Excavate and Filling Granular Material CH6+350 to CH6+500 50% 35,158.14
EXCAVATOR -3
DUMPTRUCK -4
ii Geotextile & Timber Mattress -CH6+350 to CH6+500 50% 46,240.50
4 Bridge Works
a Single Span - Bridge Over Sg. Annau
i Prestressed Concrete Girder
a Fabrication of Type 30 I-Beam -100% 20% 38,800.00
2 Retaining Wall
ii Retaining Wall B 80% 16,000.00 PILING RIG -1
EXCAVATOR 1
2 Piling (Bridge Works) -Provisional
PILING RIG -1
a 600mm Dia Spun Pile -Piling Works at Bridge Over Sg. Annau 80% 57,750.00
EXCAVATOR -1
4 Geotechnical Works
a Ground Treatment Works
i Excavate and Filling Granular Material CH6+350 to CH6+500 100% 35,158.14
EXCAVATOR -3
DUMPTRUCK -4
ii Geotextile & Timber Mattress -CH6+350 to CH6+500 100% 46,240.50
5 Bridge Works
a Single Span - Bridge Over Sg. Annau
i Abutment A1 50% 21,887.00
b Prestressed Concrete Girder
i Fabrication of Type 30 I-Beam -100% 60% 77,600.00
2 Retaining Wall
ii Retaining Wall B 80% 6,000.00 PILING RIG -1
EXCAVATOR 1
2 Piling (Bridge Works) -Provisional
PILING RIG -1
a 600mm Dia Spun Pile -Piling Works at Bridge Over Sg. Annau 80% 13,860.00
EXCAVATOR -1
4 Geotechnical Works
a Ground Treatment Works
i Excavate and Filling Granular Material CH6+500 to CH6+700 100% 56,253.01
EXCAVATOR -3
DUMPTRUCK -4
ii Geotextile & Timber Mattress - CH6+500 to CH6+700 100% 73,984.80
5 Bridge Works
a Single Span - Bridge Over Sg. Annau
i Abutment A1 100% 21,887.00
b Prestressed Concrete Girder
i Fabrication of Type 30 I-Beam -100% 100% 77,600.00
445000
Total Cumulative Manhour Up to Current Month
1 FEBRUARY 31 19 61.30%
2022
PROGRESS PHOTOGRAPH
Embankment Filling Works in Progress
Embankment Filling Works in Progress