Charges for embedded generators - Eskom 21 July 2010
Charges for embedded generators - Eskom 21 July 2010
• Loads pay published and approved charges for the use of the network
• Eskom will allow wheeling BUT the wheeling arrangement is subject to the
generator receiving its approvals to generate and trade
• Generators that wish to wheel energy face challenges related to the use-of-
system charges.
• There is urgent need to address these issues and propose a framework for
use of system charges
• The proposed framework together with the Eskom wheeling policy aims to
reduce barriers to entry and risk for non-Eskom generators
• In particular for generators that wish to wheel energy
Transactions with generators
• The generator will contract with the network Useof
Use ofsystem
system The proposed
provider to provide network services. The chargesfor
charges for framework with deals
network provider will raise charges for these Generators
Generators the generator
services. use of system
charges
• The generator will contract with the entity PPA
PPA
purchasing the energy through a PPA and between
this may be with Eskom, a third party or for between
generator
generator
own generation. andbuyer
buyer
and
• If the energy is sold to a third party, the
electricity bill must be adjusted for the Useofofsystem
system
wheeled energy through a supplementary Use
contract. The customer will pay the chargesfor
charges for
standard tariffs associated with the cost of Loads
Loads
delivering the energy.
• Generators are liable for charges for the use of the network
• Loads are liable for charges for the use of the network
• The 2 are NOT linked.
• Generators, whether they sell energy to Eskom or wheel energy to
third parties will pay equitable use-of-system charges
• Loads that receive wheeled energy from a non-Eskom generator
or energy from Eskom will pay the equitable use of system
charges
• A wheeling transaction is a financial adjustment for the energy not
supplied by Eskom.
• The service provided with regard to the use of the network is
independent from who owns the energy
• Any use-of-system benefit or cost associated with a generator’s
location accrues to that generator and not to the purchaser of the
energy.
Allocation of network charges between loads
and generators
Generator
R/kVA network charge Generators will pay
equitably for the network
usage
Generator A
Load R/kVA network charge
Meter
100 kWh Sum of all load and Load R/kVA
generator network network charge
charges
Meter
= Distribution
revenue requirement Load A
• What needs to be resolved is how to make the situation fair, transparent and
predictable.
• Level the playing field for generators selling energy to Eskom and generators
selling energy to third parties without resorting to special pricing arrangements.
• Based on the research and inputs from stakeholders, the following are
considered potential options regarding network charges (all would require
NERSA framework and approval):
Options considered/recommended
Option Comments
1. A network charges framework” based on date of • Will require known increases
generator connection. • Subsidies if generator does not export.
• Justify on the basis of reduction of losses and the benefit to SA Inc. but
not necessarily cost reflective.
2. Network charges based on the cost-reflective • Lower than current HV network charges but much higher for MV.
urban use-of-system costs as calculated for loads • Simple to apply, but will require publication
• Justifiable
3. As (1) or (2) but only raised or HV and not raised • Will be significantly lower than current network charges for HV supplies.
for MV and lower • Justifiable as MV connected generators reduce capacity on networks
and losses.
4. As (1), but network charges are zero for first block • Simple to apply and predictable
• Would require cross-subsides and no incentive to generate energy.
• Not justifiable
5. As for (2) but network charges rebated on energy • Includes a locational signal
produced using standard tariff loss factors. • For generators with high load factors the network charge could be fully
rebated.
• Generators located in the Cape will receive higher rebates
• Justified on the basis of reduction of losses and incentivising generator
production.
6. As (2) but base network charges on maintenance • Would be subject to average price increase.
and operation cost • This should be an average value
7. Ignore the benefit of losses • Simple to apply and predictable
• Not cost reflective.
8. Charge cost of losses or provide a negative charge • Complex to apply and not predictable.
if losses reduced • Requires different charges/benefits per generator
• Applicable for certain period.
• Should only be applicable if cost-reflective charges are raised.
9. Evaluate how connection charges are raised • Will require a change in policy and the Code
10. For co-generators the use-of-system charges • Based on international precedent.
based on the higher of import or export. charge • Load and generator should not pay twice for the same network capacity.
Proposed framework for Generator use of
system charges (GUoS)
• The use-of-system charges will comprise,
• network charges,
• network charge rebate,
• reliability services charges (same as criteria for loads) and
• service and administration charges (same as criteria for loads).
• The network charge will comprise
• A HV R/kVA tariff network charge (>66kV < 132 KV) using the average cost-reflective distribution
network costs as currently calculated determined for loads, based on the maximum export capacity.
• This charge will increase at a given indexed value.
• The HV network charges are rebated
• Based on energy produced based on the standard tariff loss factors, per transmission zone and
voltage at the base WEPS/Megaflex energy rates (the rate excluding losses and reliability services),
• Not rebated beyond extinction.
• For medium voltage (<66 KV – mainly 11 and 22 kV) connected generators, no network charges to be
raised
• The rebate scheme to be revaluated in the future, but it is proposed that all generators that connect in the
next 5 years will remain on the rebate scheme until termination.
Network charge rebate
• The rebate is based on the reduction of (technical) losses to Eskom
• The generator’s network charge is reduced by a c/kWh rebate based on the amount of
energy produced by the generator.
• Justified by assumed reduction of cost of losses on the Distribution network.
• Cost of losses is costs calculated as c/kWh energy rates at standard tariff loss factors
• The rebate incentivises generators:
• That have higher load factors
• That are located in areas with high loss factors
• While the rebate approach provides a signal for the losses benefit - it is not cost
reflective, therefore
• The rebate should be never be beyond extinction.
• The rebate should not be applied to the service, administration and reliability service
charges.
Network charge rebate
= {Delivered energyt x (distribution loss factorV x transmission loss factorZ-1) x Pt}
Where:
V = at the relevant voltage level
Z= transmission zone and
t = the appropriate peak, standard or off peak time period and
Pt= Megaflex energy price excluding losses and reliability services for each PSO time period.
Cost reflective network charges
Voltage ≥132kV
≤66kV &
Transmission Zone 1
MEC (MW) 300
Load factor % 60%
Based on the above formula the rebate (c/kWh) is then determined as follows:
Table 2 – Example: rebate per peak standard and off-peak period
Peak Standard Off Peak
PSO ratio 17% 42% 42%
Losses c/kWh
High demand season [Jun - Aug] 7.45 1.93 1.02
Low demand season [Sep - May] 2.07 1.26 0.88
Based on peak,
Based on peak,
standard and off-peak
standard and off-peak
generation profile
generation profile