ESR APRIL 2022
ESR APRIL 2022
ANTICIPATED EOT
NO. ANTICIPATED EOT - DESCRIPTIONS NO OF DAYS
Actual Cumulative
67.20% 67.70% 72.16%
Ahead/ Behind -32.80% -32.30% -27.82%
Based on WP BL05
Plan 100.00%
Actual
72.16%
Ahead/Delay(+/-) = -27.82%
Financial Work Progress
APRIL 2022
FEBRUARY 2022 MARCH 2022
Month Based on
Based on Revised Based on Revised Revised
WP BL05 WP BL05 WP BL05
TOTAL RM 16,172,962.33
Progress as of
25th APRIL 2022
Based on WP BL05
Plan : 100.00%
Actual : 79.24%
Ahead/Delay(+/-) : -27.04%
WORK BREAKDOWN
STRUCTURES (WBS)
WORK BREAKDOWN STRUCTURES
WTG %
Description (SUMMARY =
No. (SUMMARY OF TENDER) Plan EOT Var EOT Plan EOT Var EOT
OF TENDER) Actual Actual (WTG/100*CURR RM
LATEST LATEST LATEST LATEST
ENT MONTH Var
EOT LATEST)
PILING FOR CIVIL
1 10.92% 100% 98.50% -1.50% 100% 98.80% -1.20% 0.13% 44,260.10
WORKS
PILING FOR BRIDGE
2 1.35% 100% 0.00% -100% 100% 0.00% -100% 1.35% 364,857.70
WORKS
4,638,144.4
3 CIVIL WORKS 78.03% 100% 78.00% -22.00% 100% 80% -20.00% 15.61%
5
1,388,328.0
4 BRIDGE 5.14% 100% 0.00% -100.00% 100% 1% -99% 5.0%
8
BRIDGE
5 1.15% 100% 0.00% -100.00% 100% 0.00% -100.00% 1.15% 311,112.29
EMBANKMENT WALL
6 ENVIRONMENTAL 1.56% 100% 55.00% 45.00% 100% 60.00% 40.00% 0.64% 231,165.02
7 TRAFFIC 1.85% 100% 55.00% 45.00% 100% 60.00% 40.00% 0.74% 225,090.00
6,922,956.8
Total Overall Progress 100.00% 100% 67.70% -32.30% 100% 72.16% -27.82% -27.82%
4
3+450 0%
1+850 0
Tier 1 0% 100% 100% Tier 1 0% 100% 100%
Ground Treatment Works
Chainage 2+115 to 2+215 2+415 to CH3+415 3+510 to 4+565 4+615 to 5+765 6+040to 6+325 6+380 to 6+660
Previous Current Previous Current Previous Current Previous Current Previous Current Previous Current
Excavation (300mm ) 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0%
Filling sand (300mm) 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 0%
Installation of Bamboo 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0%
Installation of Geotextile 100% 100% 100% 100% 100% 100% 100% 100% 0% 0% 0% 0%
Earth filling works 100% 100% 100% 100% 95% 98% 90% 98% 50% 90% 20% 50%
31 6+749.338 75 0 0 0% 0% 0% 0%
CH1+024 100%
10 26 26 0 100% 0% 100%
CH1+047
12 33 33 0 100% 0% 100% 100%
CH1+715
13 18 18 0 100% 0% 100% 100%
SURFACE DRAINAGE WORKS
RHS & LHS
Bench/ Berm Cascading Slope
CH Toe Drain Interceptor Drain Roadside Drain Drain Drain
LHS
Workdone % Workdone % Workdone % Workdone % Workdone
0 -1 km (LHS) 100% 100% 0% 100% 100%
100% 100% 100%
1 - 2 km (LHS) 100% 100%
6 - 6.754 km (LHS) 0%
DRAINAGE WORKS
RHS & LHS
Toe Drain Interceptor Drain Roadside Drain Bench/ Berm Drain Cascading Slope Drain
CH
RHS
% Workdone % Workdone % Workdone % Workdone % Workdone
5 - 6 km (RHS) 100%
6 - 6.754 km (RHS) 0%
RESOURCES PROGRESS
- MANPOWER SUMMARY
- MACHINERIES SUMMARY
- MATERIALS ON SITE
Manpower Summary
7 1 1 working 1 1 working
Backhoe Loader
Total 35 35 35 35
1 25 0 7365
150 x 150mm R.C Precast Pile
2 30 0 660
250 x 250mm R.C Precast Pile
3 8 0 483
1500 mm Dia . Pipe Culvert (m)
4 20 0 85
900 mm Dia . Pipe Culvert
5 600mm Dia Spun Piles 64 0 96
CLOSE
MONITORING
REPORT
MILESTONE FOR THE MONTH OF APRIL 2022
ACHIEVEMENT : 5/8
MILESTONE FOR THE MONTH OF MAY 2022
MAY 2022 MILESTONE
4 Geotechnical Works
a Ground Treatment Works
i Excavate and Filling Granular Material CH6+350 to CH6+500 100% EXCAVATOR -3
DUMPTRUCK -4
5 Bridge Works
b Prestressed Concrete Girder
i Fabrication of Type 30 I-Beam -100% - STEELWORK 100%
MILESTONE FOR THE MONTH OF JUNE 2022
MILESTONE FOR THE MONTH OF JULY 2022
MILESTONE FOR JULY 2022
4 Geotechnical Works
a Ground Treatment Works
EXCAVATOR -3
i Surcahrge filling works 20%
DUMPTRUCK -4
5 Bridge Works
a Single Span - Bridge Over Sg. Annau
i Abutment A 100%
TOTAL 0.74%
ISSUES ARISING & STATUS
Issues Arising & Status