Financial Progress
Actual: 3.23%
Schedule : 28.07%
Site Activities as todate
13.12.2019
1. Piling works at culvert 8 (LHS & RHS)
2. Backfilling works culvert 4 & 5
3. Culvert:-
• Culvert 2 – 50% Completed - LHS
• Culvert 3 – 45% Completed - LHS
• Culvert 4 – 48% Completed - LHS
• Culvert 5 – Completed – Except Stone Pitching
• Culvert 6 – Completed
• Culvert 7 – Completed
4. Ground Treatment at CH2+115 to CH2+215 – In Progress
5. Site Clearance From CH4+550 to CH5+550 – In Progress