For Technical Meeting

The project involves the construction of a new road from Tatau to Kuala Tatau in the Bintulu Division, with a contract sum of RM 28,121,329.52 and a duration of 24 months. As of December 13, 2019, the physical progress is at 5.86%, significantly behind schedule, while financial progress is at 3.23%. Various site activities are ongoing, including piling and backfilling works, with several culverts at different stages of completion.

Uploaded by

Premier Toh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
5 views7 pages

For Technical Meeting

The project involves the construction of a new road from Tatau to Kuala Tatau in the Bintulu Division, with a contract sum of RM 28,121,329.52 and a duration of 24 months. As of December 13, 2019, the physical progress is at 5.86%, significantly behind schedule, while financial progress is at 3.23%. Various site activities are ongoing, including piling and backfilling works, with several culverts at different stages of completion.

Uploaded by

Premier Toh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 7

PROJEK KERAJAAN SARAWAK

MEMBINA JALAN BARU TATAU KE KUALA TATAU, BINTULU DIVISION


Project Brief
Project Title MEMBINA JALAN BARU TATAU KE KUALA TATAU, BINTULU DIVISION
Contract No. PWD/HO/B009/2019
Contract Sum RM 28,121,329.52
Superintending Officer Regional Manager, Northern Regional Office, Jabatan Kerja Raya Sarawak.
Client Jabatan Kerja Raya
Consultant United Consultants
Contractor Kemena Holding Sdn Bhd
Construction Period 24 months
Site Possession Date 27 February 2019
Completion Date 26 February 2021
Defects Liability Period 12 months
Physical Progress & Financial
Progress
Physical Progress
Actual: 5.86%
Schedule : 27.62%
Delay : -21.72%

Financial Progress
Actual: 3.23%
Schedule : 28.07%
Site Activities as todate
13.12.2019
1. Piling works at culvert 8 (LHS & RHS)
2. Backfilling works culvert 4 & 5
3. Culvert:-
• Culvert 2 – 50% Completed - LHS
• Culvert 3 – 45% Completed - LHS
• Culvert 4 – 48% Completed - LHS
• Culvert 5 – Completed – Except Stone Pitching
• Culvert 6 – Completed
• Culvert 7 – Completed
4. Ground Treatment at CH2+115 to CH2+215 – In Progress
5. Site Clearance From CH4+550 to CH5+550 – In Progress