DFCCIL Introduction to bridgesVKT
DFCCIL Introduction to bridgesVKT
Vishvas Kumar
Sr Professor/Bridge-II
IRICEN
1
Introduction to bridges:
Basic Concepts & Classification
• Will be covered
• Classification 15
• LWR on Bridges
• Basic concept of Rail Structure Interaction 15
• IRPWM Provision for LWR on Bridges
30
Over IR network,
• About 23.4 per cent are over 100 year old
Arch
Through Type Semi -Through Type Under Slung Type Through Type Semi -Through Type Under Slung Type
MAIN PARTS OF THE BRIDGES
1) Superstructure
– Track Structure
– Girder
– Bearing
2) Substructure
– Bed Block
– Training & Protective Works
– Pier/Abutment/Wing Wall
– Foundations
Monolithic Bridge like Pipe Culvert, Box Culvert
and Arch act like one unit.
5
FOUNDATIONS
1. Open Foundation
2. Pile Foundation
3. Well Foundations
SUB STRUCTURE
1. Masonry
2. Concrete
3. RCC
4. Steel
CLASSIFICATION OF
BRIDGES
9
1. ACCORDING TO SPAN OR OPENING
1) Minor Bridge
2) Major Bridge
3) Important Bridges –
10
2. ACCORDING TO FUNCTION
6) Aquaduct
• - Canal or Nallah over Track
12
Road Over Bridge
Foot Over Bridge
3. ACCORDING TO MATERIAL OF
CONSTRUCTION OF SUPER STRUCTURE
17
RUB NH
5. ACCORDING TO STRUCTURAL
CHARACTERISTICS OF SUPER STRUCTURE
1) Simply supported
2) Continuous
3) Balanced Cantilever
4) Cable Stayed
5) Suspension
7) Rigid Frame.
19
Arch Bridge
20
ELEMENTS OF AN ARCH BRIDGE
ELEMENTS OF AN ARCH BRIDGE
Bowstring Bridge
24
25
Cable Stayed Bridge
26
27
28
Suspension Bridge
29
Suspension Bridge
30
Suspension Bridge:
Forces
31
32
RIGID FRAME
33
6. ACCORDING TO LEVEL OF
FLOOR SYSTEMS 1) Deck Type – (Track Structure on
Top Flange or Chord)
34
SEMI THROUGH TRUSS
35
THROUGH SEMI THROUGH
BRIDGE BRIDGE
DECK TYPE
BRIDGE
36
38
PLATE GIRDER
39
PLATE GIRDER
ELEVATION
40
PLATE GIRDER
CROSS SECTION
MAIN GIRDER
BEARING
BED BLOCK
41
Plate Girder Bridge
42
Plate Girder Bridge
43
COMPOSITE GIRDER
Open Web Girder Bridges
Through Girder
Under
Slung
45
Open Web Girder
• Mostly open web type girders are used for track
bridges over valleys and large rivers on account of
economy in cost.
• This is achieved by using smaller sections than plate
girders and also fixing rail level as per site conditions
resulting less earth work .
• Open web girder on which track structure is provided
on the bottom of girder is called as through type girder.
• Open web girder on which track structure is provided
on the top of the Girder is called Underslung type
Girder.
• Presently steel used is conforming to IS: 2062 Grade
‘B0’ for rolled sections. 46
Through Girder Bridge
47
Under slung Girder Bridge
Open web girder on which track structure is provided on the top of the Girder
is called Underslung type Girder.
Latest drawing No. RDSO/B-17141 to 17155 is issued by RDSO for 25 tonne
axel loading welded type. 48
Under slung Girder Bridge
49
BOGIBEEL BRIDGE
50
Through girder bridge
51
PSC BOX GIRDER
53
PSC I GIRDER
55
RCC BOX
SEGMENT
56
RCC SLAB BRIDGE
57
MOVEABLE BRIDGES :
• Swing Bridge
• Bascule Bridge
• Lifting Bridge
58
Bascule Bridges
Video
59
Video
60
Swing Bridges
61
Lifting bridges
Video
62
7. ACCORDING TO TYPE OF SERVICE
1) Permanent
2) Temporary
– Restricted Head Girder (RH Girder)
– Calender-Hamilton Bridge
– Pontoon Bridge
63
TEMPORATY BRIDGES
Type of girder Span
1. Rail Cluster 3660mm (12’)
2 RH Girder a) 1800mm
(Plate girder type, b) 7200mm (24’)
duplicate girders) c) 9680mm(31’-9”)
d) 13200mm (44”)
e) 16400mm (53’-6”)
f) 26480mm (87”)
3. Calendar Hamilton a) 24400mm (80’)
Girder(open web b) 30500mm (100’)
through type) c) 45700mm (150’)
d) 61000mm (200’)
4. Standard Span a) 12200mm (40’)
(Plate girders) b) 18300mm (60’)
c) 24400mm (80’)
64
RH Girders – Salient Features
• Single Leaf girders
• Sleepers provided on top.
• Welded girders, welded intermediate
stiffeners
• Bracing/ cross frames with turned bolts
• Designed for 0.6 million cycles of loading as
per SBC
66
Pontoon Bridges
67
8. ACCORDING TO METHOD OF CONNECTION
(STEEL GIRDER)
1) Riveted
2) Welded
3) Bolted
68
9. ACCORDING TO LEVEL OF DECKING
WITH REFERENCE TO HFL
69
10. ACCORDING TO RAILWAY
GAUGE
1) Broad Gauge (BG – 1676 MM)
2) Metre Gauge (MG – 1000 MM)
3) Narrow Gauge (NG – 762 MM)
70
11. ACCORDING TO LOADING
Broad Gauge
– DFC
– 25 T
– MBG – 1987 (Modified Broad Gauge)
– RBG – 1975 (Revised Broad Gauge)
– BGML (Main Line)
– BGBL (Branch Line)
71
LWR Track over Bridges
72
LWR Track over Bridges
73
What Causes Relative movement between rail and bridge
deck?
1. The thermal expansion of the deck only, in the case of CWR, or the
thermal expansion of the deck and of the rail, whenever a rail
expansion device is present.
2. Horizontal braking and acceleration forces
3. Rotation of the deck as a result of the deck bending under vertical
traffic loads
4. Deformation of the concrete structure due to creep and shrinkage
5. Longitudinal displacement of the supports under the influence of the
thermal gradient
6. Deformation of the structure due to the vertical temperature
gradient
Note- In most cases, 1st three are of major importance for bridge design
74
Rail-structure Interaction takes place due to:
1. Thermal movement of Bridge Deck/Rail
2. Tractive Effort/Braking Force
3. Deck Bending (End rotations)
NOTE
First phenomenon is gradual while remaining two are rapid
Interaction effect due to thermal movement of Rail will take
place only if SEJ is present on bridge or within 100 m of
approaches
Long term phenomenon like deformation of deck under
creep/shrinkage are considered to be dissipated during various
track maintenance operations hence not considered while
carrying out RSI studies
76
Interaction due to temp variation
RAIL
DECK
𝑓 𝐾𝑁 / 𝑚
A B
L
TENSION Forces in
Rail
COMPRESSION
78
Variation of Additional
Rail Stress
Force in Rail due to thermal movement of deck
TENSIO
N
Support reaction
COMPRESSIO
N 79
Additional Stresses in LWR due to deck movement
RSI due to Longitudinal force (Braking Force)
Direction of
Vehicl traffic
e
Approach RAIL Approach
Reaction Reaction
Deck
Fixed Reaction Movabl
Bridge Deck e
Pier
81
Interaction Due to Longitudinal Force
(TE/BF)
• The tractive force cause tension in front and compression in
rear of the Locomotive.
• The braking force cause compression in front and tension in
rear of the train.
• Sharing of longitudinal loads between approaches and bridge
substructure depends upon the relative stiffness of track and
bridge in longitudinal direction.
• Stiffer part will attract more load.
• The fixity of rail at approaches will increase the rail stress and
reduce the load at bearing.
82
Shortening RSI due to Deck
of deck top
Bending Lifting of edge
L TOP
L TOP’
L NA
L NA'
L BOT
L BOT'
84
LWR on Bridges
• 330 Bridges with Ballasted Deck and Ballast Less Track (BLT) (with bearing):
• Detailed calculations shall be done by the Design office of Chief Bridge Engineer/CAO(C) to
ascertain the effect of LWR on such bridges and its effect on the Sub-structure of the bridge
as per Para 2.8.1.2 of “Bridge Rules”.
• The LWR/CWR may be permitted on a case-to-case basis based on the above calculations.
• In case detailed calculations are not done, LWR on ballasted deck bridges (with bearings)
may be permitted as per Para 331 below for bridges with un-ballasted deck.
• The LWR/CWR on BLT Bridges may only be permitted, if found satisfactory on the basis of
above calculations. Chief Bridge Engineer/CAO(C) may further permit use of special
arrangements to control RSI effects as stipulated in the RDSO report no. BS-114
85
LWR on Bridges
• 331 Bridges with Un-Ballasted Deck:
• LWR/CWR shall be continued over such bridges with overall length as specified in sub-Para(1)
to (3) below:
(1) Bridges provided with rail-free fastenings
(single span not exceeding 30.5 metre and having sliding bearings on both ends)
Overall length of the bridge should not exceed the maximum as provided in Table-1with following
stipulations:
a) Rail-free fastenings shall be provided throughout the length of the bridge between
abutments.
(b) SEJ of the LWR should be located such that
– bridge does not fall in the breathing length of the LWR.
– The approach track upto 50 m on both sides shall be well anchored by providing PRC sleepers with elastic rail clips
with adequate toe load so as to arrest creep.
(c) The ballast section of approach track upto 50 metre shall be heaped upto the foot of the rail
on the shoulders and kept in well-compacted and consolidated condition during the86
months of extreme summer and winter.
LWR on Bridges
• 331 Bridges with Un-Ballasted Deck:
• (2) Bridges provided with rail-free fastenings and partly box-anchored
(with single span not exceeding 30.5 metre and having sliding bearings at both ends)
• Overall length of the bridge should not exceed the maximum as provided in Table-1 with
following stipulations:
(a) On each span, 4 central sleepers shall be box-anchored with fair ‘V’ or similar type creep
anchors and the remaining sleepers shall be provided with rail-freefastenings. For fair ‘V’ type
anchors, typical drawing Nos. RDSO/T-1045 for 60 Kg rail section and RDSO/T-10327 for 52 Kg rail section may
be referred.
(b) The track structure in the approaches shall be laid and maintained to the standards as stated in
(1) (b) & (c) above.
(c) The girders shall be centralized with reference to the location strips on the bearing, before
laying LWR/CWR.
(d) The sliding bearings shall be inspected during the months of March and October
each year and cleared of all foreign Materials. Lubrication of the bearings shall be 87
done once in two years.
LWR on Bridges
• 331 Bridges with Un-Ballasted Deck:
• (2) Bridges provided with rail-free fastenings and partly box-anchored
88
LWR on Bridges
89
90
LWR on Bridges
• (6) Bridges on which LWR/CWR is not permitted/provided as per above
shall be isolated by a minimum length of 30 metre of well anchored PSC sleeper track
on either side.
91
Thanks 92