Part 2-AtoE
Part 2-AtoE
Auditing
Part II Planning the Engagement
A Establish Engagement Objectives and Scope
B Conduct Engagement Risk Assessment
C Prepare Engagement Procedures and Work
Program
D Determine Staff and Resources for the
Engagement
E Construct an Audit Staff Schedule for Effective
Use of Time
Engagement Audit Process
Engagement planning (e.g. interviews with the audit client, walk through
the processes/systems, research into risks etc.)
Creation of the audit program (including audit objectives and tests)
Fieldwork (e.g. interviews, observations, analyses etc.)
Internal audit manager review
Draft report
Client review and discussions
Final report
Engagement Planning
- Performance Standard 2200
Examples:
• Acts and regulations
• Policies and procedures; Standards or guidelines
• Client management roles and responsibilities
• Industry best practice
• Guidance provided by recognized bodies of experts
Part II Planning the Engagement
A Establish Engagement Objectives and Scope
B Conduct Engagement Risk Assessment
C Prepare Engagement Procedures and Work
Program
D Determine Staff and Resources for the
Engagement
E Construct an Audit Staff Schedule for Effective
Use of Time
Risk-based approach
During the audit, the actual time spent performing the engagement should be
tracked against the budget time, significant overrun may be documented as a
lesson learned for future planning purposes.
Documents that may demonstrate conformance with Standard 2230 may include
–
Approved engagement work program
Internal auditing activity’s planning notes
Timesheets or tracking documentation used to monitor budgeted hours
against actual hours
A post-audit client survey on the quality of internal audit resources and
timeliness of the audit report.
Part II Planning the Engagement
A Establish Engagement Objectives and Scope
B Conduct Engagement Risk Assessment
C Prepare Engagement Procedures and Work
Program
D Determine Staff and Resources for the
Engagement
E Construct an Audit Staff Schedule for Effective
Use of Time
Construct an Audit Staff Schedule
for Effective Use of Time 1/3
A staff schedule is an important tool for managing the
activity’s resources efficiently.
Gantt chart, a project scheduling technique can be used
for audit staff scheduling.
Gantt chart divides each project into sequential activities with
estimated start and completion times.
It helps plan tasks that need to be completed; and provides a
basis for scheduling when tasks will be executed.
It also provides a quick look of the project status and
progress, allows for the assessment of key resources against
the plan, and also allows for the assessment of the project’s
performance against the plan.
Construct an Audit Staff Schedule
for Effective Use of Time 2/3
Example:
Notes:
1) Each task has three time estimates: the optimistic time estimate (O), the most likely or normal
time estimate (M), and the pessimistic time estimate (P).
2) The expected time (TE) is estimated using the beta probability distribution for the time
estimates, using the formula (O + 4M + P) ÷ 6.
Construct an Audit Staff Schedule
for Effective Use of Time 3/3
A Gantt The Gantt chart also shows the task milestones and the task
relationships between predecessor and successor tasks.
References
The IIA’s CIA Learning System, 2: Internal Audit Practice
Wiley CIAexcel Exam Review 2018, Part 2: Internal Audit Practice.
The IPPF’s Implementation Guidance – 2017
Gleim Part 2 CIA Review 2020 Edition
https://na.theiia.org/standards-guidance/mandatory-guidance/Pages/Standards-
Glossary.aspx
https://linfordco.com/blog/audit-procedures-testing/
https://en.wikipedia.org/wiki/Gantt_chart
ASQ Green Belt Handbook
Q & A