Lecture 1 Mining Part One
Lecture 1 Mining Part One
Instructors:
Dr Ombeni John Mdee
Eng. Emanuel Mdika
University of Dodoma
College of Earth Sciences and Engineering
Department of Mining and Mineral Processing
Engineering
Chapter One: Introduction
• Mine Planning involves the correct selection
and coordinated operation of all subsystems,
e.g., mine production capacity, equipment
selection, budgeting and scheduling.
• Mine Design refers to the engineering design of
subsystems in the mine structure, eg, drilling,
blasting, haulage, transportation of workforce
and supplies, electric power, water, ventilation,
pumping, fill systems, ground support and
reinforcement, stope and pillar dimensions.
Process of Mine Planning and Design
More Details: For underground, refers Mine Development and Underground Mine Courses
For Surface Mining, refers Surface Mining course
• As such your design needs to focus on
» Operational Efficiency (trucking and digging,
andmaybe drilling)
» Cost Minimization / Value Maximization (less
waste, more ore).
» Schedule flexibility (is it practical to schedule
and maintain productivity)
» Safety (don’t build hazards and risks into the
design!)
Design for Ultimate Pit Limit
PIT DESIGN PARAMETERS
• Before starting a pit design, you will need to know the
general expected pit design parameters by material
type and/or geotechnical domain, specifically the
following:
• » Safety Berm width and placement intervals (if
requested or required)
• » Batter angle (bench face angle)
• » Bench Height
• » Inter-ramp angle (IRA) limits
• » Overall slope angle (OSA) limits
• » Ramp width
• » Ramp gradient
• » Switchback width and gradient
• » Minimum Radius for Curves
• » Truck Stopping Distances (Loaded & Unloaded – at
• maximum allowable or achievable speeds)
• » Drainage planning needs, including drainage gradients
• for benches and berms
• » Minimum mining width – pit bottom, bench ends, stage
• cut-back widths
• » Preferred effective bench mining width.
• » Safety Features required (e.g. safety ramp run-offs; etc.)
• » Geotechnical zones to avoid for ramp placement.
Some things to think about up-front and to think
about
through-out the design process:
• Generally, design will start from bottom and work its way up.
• » Sometimes you may have to do some of design from top
down and work out how to join the two designs. This will
almost certainly happen where you have a preferred pit exit
point for a ramp.
• » Look at previous designs to see what previous designers
have come up with
• » Think about where ramp should exit bottom to access
• areas higher up with minimal waste stripping.
• » Where should ramp(s) exit at top of pit?
• » Should I have multiple ramps for productivity and safety
• (but at what extra stripping cost)?
• » Can I backfill an area with waste to avoid haulage to a
surface dump?
• » Can I use backfill to access an area?
• » Slice pit optimisation shells to have as a guide
contour for each bench
• » Similarly, be able to have a block model slice of ore
– colour coded for value or grade – for each bench
• » Slice significant geology wireframes (shears, faults,
dykes) by bench for use in design process.
• » Potentially may want to design a “good-bye” cut at
bottom (an excavation “trench” of ore by a backhoe
excavator without an access ramp, dug retreating
from the excavation with trucks backed up to
excavator).
• » Design pit and ramp to minimize loaded truck travel
time and minimize trucking costs from a maintenance
perspective as well as an operating perspective (and
accept that this is a compromise for unloaded truck
return hauls).
• Can I place a ramp in an area/wall that will be long
life and used for multiple stages/cut-backs (e.g.
the footwall of a stratiform deposit) for which it
will then be worthwhile building good quality
roads (e.g. good road base and sub-base)?
• » Some ramps may be temporary (e.g. providing
access for drill rigs and blast trucks or access to
pumps and infrastructure – not just for haulage)
• » Think about scheduling implications if cutting off
access to an area with a later stage design (first
area must be completely mined before being cut-
off, which may result in scheduling problems).
Width and Height of Open Pit
Powder Factor
Assignment Three
• Design drilling and blasting parameters for the
typical mine. Taking into consideration you
have been in the industry three times, i.e.,
PT1, PT2 and PT3.
• Prepare a report for the Blast Design and
Simulation using Blasting software, i.e.,
SHOTPlus
Chapter Four
CYCLE TIME MODEL
The cycle time for a haul unit can be expressed as (
Suboleski, 1975):
where:
LCT = cycle time of a haul unit, min
STL = spot time at the loader, min
LT = load time of the haul unit, min
TL = travel time (loaded), min
STD = spot time at the dump, min
DT = dump time, min
TE = travel time (empty), min
AD = average delay on the haul cycle,
min (wait at dump, wait at the loader, or slow down on the
haul road).
Also;
• TCP = capacity of the haul unit, short tons and
LR = loading rate of the loader, st/min
where:
HD = haul distance from the loader to the dump, ft
SL = speed of a loaded haul unit, ft/min.
SE = speed of an empty haul unit, ft/min.
• If there is no delay at the dump or the haul
road, the number of haul units required to keep
the loading unit busy is given by:
where
h = superelevation, ft
a = the rail gage, ft
v = velocity, ft/sec
g = acceleration due to gravity, ft/sec2
R = radius of the curve, ft.
Cycle Time of a Train:
The cycle time is the sum of the loading, travel loaded, dump,
travel empty times, and delay time per trip.
loading time, 7 cars = 35.00 min
@ 5 min/car
travel loaded time:
1,000 ft @ 5 mph =
2.27 min
26,640 ft @ 10 mph
= 30.27 min
6,000 ft @ 25 mph =
2.73 min
2,000 ft @ 5 mph = = 39.82 min
4.55 min
dumping time @ 1 = 7.00 min
min per car
travel empty time:
2,000 ft @ 5 mph =
4.55 min
6,000 ft @ 35 mph =
1.95 min
26,640 ft @ 20 mph
= 15.14 min
1,000 ft @ 5 mph = = 23.91 min
2.27 min
delay time per trip = 5.00 min
cycle time per trip = 110.73 min
Haul Truck Cost Estimation
• Crossfall is the difference in elevation between the crest (crown) and the
road edge. It is a widely used technique that effectively drains water from
road surfaces and is to be incorporated in all road designs.
• Crossfall helps protect the road pavement from damage by water by reducing
pooling of water, mud and potholing. If water is allowed to accumulate on
the running surface, deterioration of the sub-base due to water saturation
may occur. If the sub-base becomes exposed, tyre damage may also occur
•
• The rate of crossfall depends on a number of factors including the road
gradient, the road surface and the expected weather conditions. From an
operator’s point of view, a level driving surface is most preferred because this
requires the least steering effort.
• However, to allow adequate drainage, crossfall must be applied and so the
rate must accommodate both a rapid removal of surface water and
steerability.
Super elevation
• Super elevation is a technique employed at Mine XYZ to assist
vehicles in manoeuvring safely around corners.
• Super elevation is the banking of the road surface at curves. It
allows the vehicle taking the corner to counteract centrifugal
forces towards the outside of the curve, by directing the
vehicle weight towards the centre of radius of the curve.
• The amount of super elevation on a corner is directly related
to the radius of the corner and the desired vehicle speed
through the corner.
• The following table is a guide for providing the super elevation
necessary to reduce lateral forces. 5% should be regarded as
the maximum super elevation.
• Curves super elevated between 5% and 10% should be used
with caution. Curves super elevated over 10% should not be
used.
• Super elevation is a particularly important design consideration
for switchbacks on pit ramps at Mine XYZ. On such corners,
which typically have a small turn radius, superelevation is
extremely important.
• On switchbacks that have the centre of the curve located on the
up-side of the ramp, a well-chosen superelevation rate prevents
material being spilled from laden trucks and also improves the
vehicular control.
Rule of Thumb
• A 10% gradient is a typical safe haul road gradient in
open pit mines for rigid body haul trucks
• The running surface of a two lane haul road should be
3.5 ties the width of the largest truck operating on
that road.
• A single lane road should be twice the width of the
largest truck.
• The height of the windrow on the side of a haul road
should be at least one-half the tire diameter of the
largest truck using the road.
Light vehicle roads
• Light vehicle roads may be permanent or
temporary. They can be access roads around the
perimeter of the pit and roads that give access to
remote or rarely used areas of the pit or mine
site. The basic criteria for light vehicle roads are:
• typically long term roads but can be short term
• used by light vehicles and service vehicles only
• access remote areas of the mine
• low frequency traffic
Assignment Four
• GPSSH Application