Urs - Propak - 20190613 - JW 02
Urs - Propak - 20190613 - JW 02
User Basis of
Requirements Design
Functional
Requirement URS
Basic
Requirements
FDS TOR
Technical
Specification Design Purchasing
Documents Documents
Black
Black && Clean
Clean Utility
Utility
Systems
Systems M&E
M&E
HVAC,
HVAC, Clean
Clean Room
Room
Control
Control Systems
Systems
Process
Process Equipment
Equipment
Integrated Logistics
Maintenance &
Maintenance
System Warehousing
System
Project Phasing
Conceptual phase Design phase Execution phase Validation phase
Feasibility
Study
Procurement
Handover Validation
Support
Effective Start up
Annex
Connecting Pharmaceutical Knowledge ispe.org
Key of success
Right approach : Effective URS!
Right decision on Contractor/suppliers selection
No negotiation on quality of work
Technical support from network, consultants and suppliers
Apply GMP principle/concept to construction project since beginning
e.g. supplier audit, qualification proof record, personnel training and
QA on construction
Team character: Target oriented, Flexibility and prompt action and
Friendship atmosphere
“มาตรฐานวิธีการที่ดีในการผลิตยา เป็น
แนวทางปฏิบัติในการผลิตยา ซึ่งเป็นส่วน
หนึ่งของระบบการประกันคุณภาพยา เพื่อให้มี
ความเชื่อมั่นว่า ยาที่ผลิตมีคุณภาพ
ประสิทธิภาพ และความ ปลอดภัย ตรงตามคุณภาพ
มาตรฐานที่กำหนดและสม่ำเสมอในทุกๆรุ่น
ประกาศกระทรวงสาธารณสุข เรื่อง “การกำหนดราย
ละเอียดเกี่ยวกับหลักเกณฑ์และวิธีการในการผลิต
ที่มีการผลิต”
ยาแผนปัจจุบันตามกฎหมายว่าด้วยยา
World Healthพ.ศ. 2559”
มาตรฐานวิธีการที่ดีในการ
Organization
ผลิตยา PIC/S GMP
Connecting Pharmaceutical Knowledge ispe.org 8
GMP Goals
GMP Funct Focus on GMP Goals
User Basis of
Requirements Design
Functional
Requirement URS
Basic
Requirements
FDS TOR
Technical
Specification Design Purchasing
Documents Documents
An important and difficult step of designing systems are determining what the owner actually
wants it to do. This is because often the owner is not able to communicate the entirety of their
needs and wants, and the information they provide may also be incomplete, inaccurate and self-
conflicting.
The responsibility of completely understanding what the owner wants then falls on the providers
of the product.
Once the required information is completely gathered, it is documented in a URS, which is meant
to spell out exactly what the function must do and becomes part of the contractual agreement.
An owner cannot demand features not in the URS without renegotiating and a designer cannot
claim the system is ready if it does not meet an item of the URS.
(การตรวจรับรองและการตรวจสอบความถูกต้อง)
3.1 Qualification activities should consider all stages from initial development of the user
requirements specification through to the end of use of the equipment, facility, utility or system.
The main stages and some suggested criteria (although this depends on individual project
circumstances and may be different) which could be included in each stage are indicated below:
3.2 The specification for equipment, facilities, utilities or systems should be defined in a URS
and/or a functional specification. The essential elements of quality need to be built in at this stage
and any GMP risks mitigated to an acceptable level. The URS should be a point of reference
throughout the validation life cycle
PIC/S GMP GUIDE PE 009- 14, Annex 11 (computerized system), p 88, PROJECT PHASE
PIC/S PI 011-3, 2007, PIC/S Guidance: Good practices for computerized systems in regulated GxP environment
Owner (w vendor) PQ
Vendor OQ =
OC+OQ
Vendor IQ = IC+IQ
Build
Manufacture/Fabricate
JETT Equipment
p ro
va Develop Risk Assessment Docs
l
Detail with User
Acquisition Model Review/Approval Detailed Design Detail Doc Develop Detailed Design Docs
Traceability
Version 006 • Finalize Risk Assessment Ap Traceable to the Functional Specification
p ro
v al
Revision
Review Supplier Commiss. Docs Develop Test Documents
Test Docs
Develop Additional Commissioning Documents FAT - SAT - Commissioning Tests
(if required) Ap
pro
val
By owner user
46
E Cleanroom URS Given by Owner
L
A MP (GMP Impact Requirements at Minimum)
E X
URS FDS DDS
Cleanroom air
cleanliness grade C
(WHO-GMP, ISO 14644
series)
HEPA 99.97% (H13) (Camfil or
AAF)
Air change > 20 4 rooms @ 6x10x3 m3
47
E Cleanroom URS Completed by Supplier
L
A MP GXP Requirements Traceability Matrix (RTM)
E X
URS FDS DDS
Cleanroom air Facilitate cleanability Materials – floor, wall, ceiling,
cleanliness grade C (GMP aspect) piping (PW, CD)
(WHO-GMP, ISO 14644
series) – continued Mat’ls: epoxy, sandwich panel,
SS316L, SS304
Smooth surface, coved corner
JETT Equipment
p ro
va Develop Risk Assessment Docs
l
Detail with User
Acquisition Model Review/Approval Detailed Design Detail Doc Develop Detailed Design Docs
Traceability
Version 006 • Finalize Risk Assessment Ap Traceable to the Functional Specification
p ro
v al
Revision
Review Supplier Commiss. Docs Develop Test Documents
Test Docs
Develop Additional Commissioning Documents FAT - SAT - Commissioning Tests
(if required) Ap
pro
val
JETT Mission: Improve communications between Users and Suppliers to more effectively
meet the “validation” requirements of the pharmaceutical industry.
JETT’s URS Templates
Connecting www.jettconsortium.com
PharmaceuticalKnowledge ispe.org 59
ISPE GAMP Guide Part 1: User Responsibilities
PS System
URS
EXAMPLE 2
EXAMPLE 1
* It describes the Validation Master Plan which is the “big picture” validation activities and is
typically approved by management and QA. System Specific Validation Plan is a Validation
Plan developed for the Suppliers that defines their responsibilities for specification and testing
so that what they do can be utilized as part of the overall validation plan. You will not find the
term (System Specific) used widely in GAMP. Its alluded to in the explanations of how
documents and specifications should flow and therefore we’ve started using that term more
commonly.
* According to GAMP, each Supplier should be formally audited to ensure the quality of the
services or equipment they supply. The audit should be done prior to seeking
equipment/services from the Supplier.
* The User is responsible for defining “WHAT” the equipment is suppose to do. It may be
written by a third party but should be approved by the User.
* The Users are responsible for Supplier education.
n t
h i
a l
t ic
a c
P r
NB: When more than one (potential) supplier is involved: more than 1 DQ may be required
Selecting the right supplier - the Users are responsible for “Supplier education”
have to
as well as