Progress Review Report (1)

The Dubai Police Training Center project is currently at 13.92% progress, significantly behind the planned 28.26%. Key issues include groundwater table challenges and discrepancies in drawings, which may further delay construction. Immediate next steps involve addressing these issues, revising the schedule, and closely monitoring progress.

Uploaded by

Najmul Hussain
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
4 views

Progress Review Report (1)

The Dubai Police Training Center project is currently at 13.92% progress, significantly behind the planned 28.26%. Key issues include groundwater table challenges and discrepancies in drawings, which may further delay construction. Immediate next steps involve addressing these issues, revising the schedule, and closely monitoring progress.

Uploaded by

Najmul Hussain
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Dubai Police Training Center,

Hatta Project Phase 2


Project #: 1790
Project Overview
Report Period: 23-Dec-2024 to 28-Dec-2024 (Week #014)

1/2/2025 Dubai Police Engineering Consultant Office 1


1. Progress Overview
Overall Progress
• Current Status:
• Overall progress at 13.92% vs. planned 28.26%
• Key activities: Excavation, backfilling, anti-termite treatment,
shuttering, casting, curing, waterproofing.
• Workforce: 80 personnel
• Equipment: Pickups, buses, excavators, dump trucks, and other machinery
Planned progress % Achieved progress % Variance %

2. Financial
• Advance payment invoice submitted and payment received.
3. Quality & Safety
• No non-conformance reports.
• No safety incidents reported.

1/2/2025 Dubai Police Engineering Consultant Office 2


4. Key Issues
• Groundwater table issues: Impacting excavation and potentially delaying construction.
• Drawing discrepancies: Between structural and architectural drawings.
5. Look-Ahead
• Focus on waterproofing, dewatering, excavation, and rebar/steel reinforcement
delivery.
6. Schedule Variance (Key Activities) Physical Progress
External Works
• Significant delays observed in:
Boundary Chain Link Fence
• Completion of Substructure - Main Block (-111 days)
External Under Ground Holding Tank
• Completion of Superstructure - Main Block (-29 days)
• Completion of Security Blocks (-41 days) Security Rooms

• Completion of MEP Works - Main Block (-64 days) Training Center

• Completion of Grand Stand (-68 days) Grand Stand

• Completion of Finishes Works - Main Block (-74 days) Residential Building

-100.00% -50.00% 0.00% 50.00% 100.00% 150.00%

Planned Progress Achieved Progress Variance

1/2/2025 Dubai Police Engineering Consultant Office 3


7. Next Steps
•Urgent: Address groundwater table issues and resolve drawing discrepancies.
•Mitigation: Develop and implement a revised schedule to recover delays.
•Close Monitoring: Continuously monitor progress and proactively address any
potential issues.

*** Report Ends ***