Study Unit 1- Cost Behaviour
Study Unit 1- Cost Behaviour
Product cost?
Variable cost??
Fixed cost??
Costs are classified as fixed of variable
based on cost behavioural paterns
Cost behaviour has to do with the way in
cost predictions
Variable costs:
costs
◦ Total variable costs change in relation to the
activity level
◦ Variable cost per unit stays constant within the
relevant range
Step fixed costs:
costs
◦ A range of increases in fixed costs over relative
short ranges of production volumes within the
relevant range
◦ Increases in jumps
1 TRUCK – 2 ton maize
N$ 5 000 – 1 TRUCK's rent
1 to 8 ton maize – relevant range
Rent
2 ton maize – N$5 000
3 – 4 ton maize – N$10 000
5-6 ton maize – N$15 000
It changes in STEPS
Fixed costs:
costs
◦ Total fixed cost stays constant within the
relevant range irrespective of the change in
activity level
◦ Fixed cost per unit changes if the activity level
changes
Mixed costs (semi-variable costs):
Costs with a fixed and variable
component, eg electricity, telephone.
The relevant range
Identifying costs as fixed or variable is
only valid within a specific range, thus the
range is where the total fixed costs and
variable cost per unit do not change.
Mixed cost consists of a fixed and
variable component
Can be plotted on a graph
Can also be expressed as a function
Graph: Draw fixed cost line first
200
180
160
140
Cost (Rand)
120
100
Fixed cost
80
R75.00
60
40
20
0
0 20 40 60 80
Graph: Draw variable cost line
200
180
160
140
Cost (Rand)
120
100
80
Variable
60
cost
40 R2.00/minut
20 e
0
0 20 40 60 80
Graph: Graphs combined
200
180
160
140
Cost (Rand)
120
100
Fixed cost
80
R75.00
60
Variable
40 cost
20 R2.00/minut
0 e
0 20 40 60 80
Mixed cost consists of a fixed and
variable component
Graph: 200
180
Total mixed
160
cost
140
Cost (Rand)
120
100
Fixed cost
80
R75.00
60
40 Variable
20 cost
R2.00/minut
0
e
0 20 40 60 80
Function: y = a + bX
where y = Total mixed cost
a = Total fixed cost
b = Variable cost per cost driver
X = Activity level (Cost driver)
Thus for our example:
y = R75.00 + (R2/min x X)
And for 50 minutes
y = R75.00 + (R2/min x 50 min)
y = R175.00
Four methods
• High-low method
• Scattergraph method
• Least squares regression method
• Multiple regression analysis
Based on linear relationship between total
mixed cost and the activity level
Use only two observations – highest and
= R0.75/machine hour
Now that the variable cost per machine hour
is known, the total fixed cost can be
calculated by means of the cost function:
Y = a + bX
Substitute any of the two points in the
function:
R7 375 = a + (R0.75/mh x 4 500mh)
a = R7 375 – R3 375
= R4 000
Cost function: Y = R4 000 + R0.75X(mh)
A range of observations are plotted on a
graph, and then a regression line is drawn.
The regression line represents the average
element
The slope of the line represents the
variable cost
8000
7000
Total cost (Rand)
6000
5000
4000
3000
2000
1000
0
0 1000 2000 3000 4000 5000
Activity level (Machine hours)
8000
7000
Total cost (Rand)
6000
5000
4000
3000 R4 000
2000 Y-intercept
represents
1000
the fixed cost
0
0 1000 2000 3000 4000 5000
Activity level (Machine hours)
The regression line intercepts the y-axis at
R4 000. Thus the fixed cost is R 4 000.
The slope (b) can now be calculated by
Y = R4 000 + R0.75/mh
Statistical method that takes all points into
account.
Easy with calculator or computer (Excel)
Formulas:
A. ΣXY = aΣX + bΣX²
B. ΣY = na + bΣX
Formulas:
A. b = n(ΣXY) – (ΣX)(ΣY)
n(ΣX²) – (ΣX)²
B. a = (ΣY) – b (ΣX)
n
X = Activity level
Y = total mixed cost for the activity
level
A = total fixed cost
B = variable cost per cost driver
N = the number of observations
Σ = sigma – means the sum of
Month Activity level Total XY X²
(machine electricity
hours) (X) cost (Y)
January 3 500 R6 625 23 187 12 250
500 000
February 2 800 R6 100 17 080 7 840 000
000
March 3 400 R6 550 22 270 11 560
000 000
April 4 200 R7 150 30 030 17 640
000 000
May 3 700 R6 775 25 067 13 690
500 000
June 3 000 R6 250 18 750 9 000 000
000
July 2 500 R5 875 14 687 6 250 000
500
August 2 200 R5 650 12 430 4 840 000
b = n(ΣXY) – (ΣX)(ΣY)
n(ΣX²) – (ΣX)²
= 64 260 000
85 680 000
= 0.75
a = (ΣY) – b (ΣX)
n
= 48 000
12
= 4 000