FIDIC Contracts - 13 Dec 2011
FIDIC Contracts - 13 Dec 2011
FIDIC Contracts
Construction Contract Law Dr Sam Laryea Murdoch & Hughes (2008) Construction contracts: law and management; London, Spon. Chapter 9
www.reading.ac.uk
FIDIC contracts
Key questions
1. 2. What is a FIDIC conditions of contract? What will make the initiators of a construction project decide to use a FIDIC conditions of contract and what form of contract will they use? What factors will the choice depend on? 3. What are the basic contents of a FIDIC contract book? 4. Who are the main parties in a FIDIC contract and what are their roles and responsibilities? 5. How many different FIDIC contract books are there and what are the key differences between them? 6. How are FIDIC contracts used in practice? 7. How are disputes resolved?
Engineer employed in the contract acts as clients agent and representative / contract administrator New editions are organised around extent of design and responsibilities assumed by employer and contractor / procurement strategy rather than nature of construction works
For the provision of electrical and mechanical plant, and for the design and execution of building or engineering works. The Contractor designs and produces, in accordance with the Employers Requirements, plant and/or other works; which may include any combination of civil, mechanical, electrical and/or construction works.
The general conditions (clauses 1 to 20), except clauses 5 & 12, are principally the same as red book.
Contractor carries out all engineering, procurement, construction, ready for operation at the turn of a key Contractor carries majority of risks, so Employer pays more Small number of tenderers with negotiation Lump Sum Contract Price (adjustments in limited specified cases)
Designer
Supervisor / contract administrator Issuing instructions
Payment
The final contract price will reflect adjustments to the accepted contract amount (sum in letter of acceptance) Re-measurement /lump sum
Payments are normally determined by measurement and applying the rates and prices from the bill of quantities Payment could also be on a lump sum basis
Retention money (parties have to agree, no fixed percentage) Delay damages (parties have to specify the percentage for LAD) Value engineering (Clause 13.2 of Red Book)
Incentivizes the contractor to suggest changes which can benefit the employer. Contractor shares 50% of any financial benefit from their suggestions.
Dispute Resolution
Dispute resolution steps
Engineer consults with parties to reach agreement If agreement cannot be reached the engineer must make a fair determination taking due regard of all relevant facts. Note: It is unwise for engineer to make unfair determination against contractor If engineers determination is not agreed by either parties the dispute will be referred to a Dispute Adjudication Board (DAB) or Dispute Review Board (DRB) If the decision of the dispute board is not accepted by any of the parties then resolution through an international arbitration (ICC rules)
Dispute resolution
FIDIC procedures - contract conditions
Cl.20.2 Disputes shall be adjudicated by DAB Cl.20.2 Appointment of DAB Cl.20.3 Failure to agree DAB nomination Cl.20.4 Obtaining a Decision Cl.20.7 Enforcement
Risk management
All contracts contain risks for both Contracting Authorities/ Employers and Contractors There is no riskfree contract FIDIC attempts to rationalise and allocate responsibilities for main risks A key requirement is for the Contract Parties to fully understand the FIDIC General and Particular Conditions of Contract that set out their Responsibilities and Risks within a Project Every risk given to the other party has its cost, no Party assumes a risk for free.
Further reading
Rights and responsibilities of parties in a FIDIC contract
Substantiation of costs
Substantiation of value Presentation of claims for loss and expense and claims for EOT Risk allocation, responsibility and insurance Negotiation and settlement Dispute resolution procedures