Resource Allocation I
Resource Allocation I
A Managerial Approach
Resource Allocation
Slope =( crash cost - normal cost)/ (crash time normal time) That is, the cost per day of crashing a project. Negative slope indicates that as the time required for a project task is decreased, the cost is increased.
Exercise 1
Given the following network, determine the first activity to be crashed by the following priority rules: a. Shortest task first b. Minimum slack first c. Most critical followers d. Most successors A4
1
D5
2
C7 B3
3
Shortest task is B B, C, or D have zero slack. Critical path is B-C-D. A has slack of 6 days. B has the most critical followers. B has the most successors, 2. Critical Time is 15 days.
Exercise 2
Using the previous network and the additional information below, find: The crash cost per day. Which activities should be crashed to meet a project deadline of 13 days at minimum cost. Assume partial crashing is allowed.
Activity
Normal cost
A
B C
3
1 4
$500
325 550
4
3 7
$300
250 400
250
150
B
C D
2
3 2
75
150 100
37.5
50 50
Task B is on the critical path and has the lowest crash cost per day. Hence crashing task B will imply additional crash cost of $75 only. Crashing B by 2 days reduces the duration to 13 days without making any other new tasks critical.
c 3
e
Normal time,cost
Activity
Crash time,cost $
Partial crashing
a
b c
3, 60
6, 80 2, 90
3, $60
7, 30 5, 50
No
Yes No
d
e
5, 50
2, 100
6, 30
4, 40
No
Yes
d 6
4 12 5 c e 4 b 7 3 8 Since the critical path is a-c-e, we initially need consider only these 3 activities:
a: cannot be crashed c: can cut 3days at an extra cost of $ 40 but only results in project completion by day 11, due to b. to reach 10 days, cut b by 1 day, total extra cost $90. e: can cut e by 2 days for an extra cost of $60 & results in project completion by day 10.