QUALITY MANAGEMENT PLAN
1. TABLE OF CONTENTS
1. Table of Contents.................................................................................................................. 1
2. Acronyms .............................................................................................................................. 2
3. Introduction ........................................................................................................................... 3
4. Approval, Distribution, Review and Audit ........................................................................... 4
4.1 Approval.............................................................................................................................................4
4.2 Distribution of complete project quality management plan................................................................4
4.3 Monitoring and review........................................................................................................................5
4.4 Inspection and Audit ..........................................................................................................................5
4.5 Record of Inspections, Audits and Reviews ......................................................................................7
4.6 QMR – Site Inspection Reporting Sheet............................................................................................8
5. QMP Objectives and Description of the Project.................................................................. 9
5.1 QMP Objectives.................................................................................................................................9
5.2 Description of the Project...................................................................................................................9
6. Organisation and Responsibilities..................................................................................... 10
6.1 Project specific Quality Management Organization Chart...............................................................10
6.2 Quality Control responsibilities (UNOPS) ........................................................................................11
6.3 Quality Control Responsibilities (UNOPS and Contractor)..............................................................12
6.4 Schedule of Key Activities ...............................................................................................................13
7. Commitment and Competency........................................................................................... 14
7.1 Leadership and Commitement.........................................................................................................14
7.2 Competency Awareness & Training ................................................................................................14
8. Control of work processes ................................................................................................. 15
8.1 Control of Works Plan Phasing........................................................................................................15
8.2 Inspection and Testing.....................................................................................................................15
8.2.1 Storage of Materials.................................................................................................................16
8.3 Submittals ........................................................................................................................................17
8.3.1 Shop Drawings.........................................................................................................................17
8.3.2 Material Submittal Schedule ....................................................................................................17
8.3.3 Process, Review and Acceptance ...........................................................................................18
8.3.4 Storage ....................................................................................................................................18
8.4 Construction Nonconformities/Deficiencies .....................................................................................18
8.4.1 Non-conformance/Deficiency Identification and Notification ...................................................18
8.4.2 Non-conformance and Non-conformance Report (NCR) ........................................................18
8.4.3 Preventive Actions ...................................................................................................................18
8.5 Documentation control.....................................................................................................................19
8.5.1 Drawings records.....................................................................................................................19
8.5.2 Final Reporting.........................................................................................................................19
8.5.3 Defect Notification Period ........................................................................................................19
9. Appendixes.......................................................................................................................... 21
9.1 Appendix 1 - Material Approval request ..........................................................................................21
9.2 Appendix 2 - Non-Conformance Report ..........................................................................................22
9.3 Appendix 3 - Non-Conformance Register........................................................................................24
9.4 Appendix 4 - Defects Register.........................................................................................................25
9.5 Appendix 5 - Defect Notification ......................................................................................................26
9.6 Appendix 6 - Material Storage Checklist .........................................................................................27
9.7 Appendix 7 – Quality Policy.............................................................................................................28
SOUTH SUDAN OPERATIONS CENTRE
2
QUALITY MANAGEMENT PLAN
2. ACRONYMS
 UNOPS-United Nations Office for Project Services
 QMS-Quality Management System
 QMP-Quality Management Plan
 PCM-Project Centre Manager
 PM-Project Manager
 DPM-Deputy Project Manager/Senior Engineer
 PE-Project Engineer
 QMR-Quality Management Representative
 SQMR-Senior Quality Management Representative
 QR-Quality Representative
 WP-Work Processes
 ITP-Inspection and Test Plan
 WIP-Work Inspection Procedures
 CL-Checklist
 NCR-Non Conformance Report
SOUTH SUDAN OPERATIONS CENTRE
3
QUALITY MANAGEMENT PLAN
3. INTRODUCTION
United Nations Office for Project Services (UNOPS) will perform the central role in managing
Quality issues during the construction phase of the project. Our Site Management will ensure that
the works are carried out to a high standard in compliance with client requirements, current
legislation and guidance. This will be achieved by application of our Quality Control Management
System. This information is available to all site personnel.
This Quality Management Plan forms one part of the overall Quality Management System that has
been developed for EU -ZEAT –BEAD- Feeder roads contract. It provides a guide for personnel
involved in the construction of this project on how the quality requirements of the specifications are
addressed. It has been developed from the information detailed within the ‘Contract Specification,
Beneficiary Requirements and Agreement information’1
.
1
Legal Documentation provided prior to work commencing.
SOUTH SUDAN OPERATIONS CENTRE
4
QUALITY MANAGEMENT PLAN
4. APPROVAL, DISTRIBUTION, REVIEW AND AUDIT
Project Name: EU- ZEAT-BEAD-Feeder Roads Project.
Project Number: 088050
4.1 APPROVAL
Date Signature
Approved by Donor*
Approved by Project Centre Manager*
Approved by Project Manager*
Reviewed by the Deputy PM*
Reviewed by the Project engineer*
[Insert other positions that are relevant to
Project/Office]
* These signatures are required for the first issue only. Thereafter the Project Manager can
approve changes which shall be recorded in the review section of the Plan.
4.2 DISTRIBUTION OF COMPLETE PROJECT QUALITY MANAGEMENT PLAN
No Name Role Location
1 GIRLANDO PAOLO EUROPEAN UNION( EU) JUBA
2 Richard Shroeder Senior Quality Management
Representative/ Project
Manager
JUBA
3 Solomon Kuliche Quality Management
Representative/ Deputy PM
JUBA
4 IBRAHIM KAMAU Quality Representative/
Project engineer
GREATER BAHR EL-
GHAZAL STATE
5 [Insert contractors
representative]
[Insert Contractor] GREATER BAHR EL-
GHAZAL STATE
* Copy of front page with authorized signature only to be emailed.
Copy 1 is the Master QMP and is the only controlled copy containing records of all reviews and
amendments.
SOUTH SUDAN OPERATIONS CENTRE
5
QUALITY MANAGEMENT PLAN
4.3 MONITORING AND REVIEW
The Project Manager shall ensure that the Project Quality Management Plan is reviewed monthly
to ensure that:
 The objectives and requirements of the Project Quality Management Plan are still valid,
and are being met.
 Forthcoming activities are reviewed and any necessary amendments to the Project Quality
Management Plan are put in place before the relevant work begins
 QMP processes shall be reviewed to ensure continuing suitability and effectiveness.
The Project Manager is accountable for the development and implementation of the Quality Plan
and delegates the responsibility for the development and implementation of this plan to the Quality
Management Representative (QMR). The Quality Management Plan is issued with the authority of
the Project Manager. All changes to the Quality Management Plan will be reviewed and authorised
by the Project Manager.
Everybody who works for UNOPS, whether as an employee or contractor, has a responsibility to
fulfil UNOPS’s quality policy and objectives, and is expected to work towards achieving these
organizational objectives.
Finally the schedule in this section, which is maintained only in the Master Copy of the Project
Quality Management Plan, shall be completed to confirm that the review has taken place.
On a weekly basis QMP performance and production matters shall be reviewed. Problems
encountered in compliance with or achievement of the processes for direct work shall be recorded,
e.g. in meeting minutes, Non-conformance Report, etc. Requirements for the coming week shall
also be considered to include improvements gained from the review, and noted to staff for action.
Project Engineers are responsible for ongoing monitoring of QMP matters.
The site based Quality Management Representative is:
IBRAHIM KAMAU
The site based Quality Management Representative (QMR) is responsible for monitoring quality
matters and shall also conduct a phase based inspection. The information obtained from these
inspections will be used by the ‘QMR (Deputy PM) to produce the monthly quality report. This
monthly report will be issued to the SQMR (Project Manager)’2
.
4.4 INSPECTION AND AUDIT
The DPM will conduct checks in accordance with Project Manager QMP Tours to confirm that
processes are being carried out effectively. A record of these checks shall be noted in this
section.
Inspections will be carried out on a regular basis by QMR with a written report being submitted to
PM (SQMR) for review and action.
UNOPS personnel responsible for Quality Control for this project are:
Quality Management Representative: IBRAHIM KAMAU
2
[Explain roles and responsibilities for your specific project].
SOUTH SUDAN OPERATIONS CENTRE
6
QUALITY MANAGEMENT PLAN
A UNOPS personnel responsible for Auditing Quality Management System for this project is:
Project Manager, Richard Shroeder.
UNOPS personnel responsible for Senior Auditing Quality Management System for this project is:
Project Centre Manager/Programme Manager.
Formal planned audits of the System shall be carried out by the UNOPS Senior Manager and
reports shall be submitted to Project Manager. These audits shall include assessments of the
Organisation Management System operating on this contract. Additional Supply Chain and site
audits shall be conducted upon request.
Audits carried out on the Project by external/client bodies shall be recorded in this section. Any
reports issued by these parties to the site shall be copied to the QMP Department.
SOUTH SUDAN OPERATIONS CENTRE
7
QUALITY MANAGEMENT PLAN
4.5 RECORD OF INSPECTIONS, AUDITS AND REVIEWS
Date Q SQMR Detail of Review Action Taken Signed
Q=Quality; QMR=Quality Management Representative;
*Include a copy of the tour report following this page.
SOUTH SUDAN OPERATIONS CENTRE
8
QUALITY MANAGEMENT PLAN
4.6 QMR – SITE INSPECTION REPORTING SHEET
Manager: Richard Shoreder Date:
Location: Greater Bahr el-Ghazal, South Sudan Project Eng.: IBRAHIM KAMAU
Recommendations for Good Performance
Item Good Practice Identified By Whom
Issues
Raised/Reviewed/Discussed
Comments/Actions Priority
Date to be
Done By
Responsibility
Action
By
Closed Out
Name Signature
SOUTH SUDAN OPERATIONS CENTRE
9
QUALITY MANAGEMENT PLAN
5. QMP OBJECTIVES AND DESCRIPTION OF THE PROJECT
5.1 QMP OBJECTIVES
This Project Quality Management Plan is specific to this project.
The objective for this project is to carry out our work which will ensure that all conditions, activities
and tasks, affecting Quality are planned, organized, executed, and controlled in accordance with the
requirements of UNOPS statutory legislation and our clients European Union (EU).
5.2 DESCRIPTION OF THE PROJECT
Some of the worst social indicators are found in South Sudan. At least 80 per cent of the population
is income-poor. More than one third of the population is food insecure. The country’s economy is
constrained by the sheer absence of roads and by the fact that any existing roads are of very poor
quality. South Sudan’s fragmented transport infrastructure network has impeded agricultural
producers in remote areas from effectively connecting to market centres.
The South Sudan Development Plan (SSDP) sets out national priorities to achieve inclusive and
sustainable development. A component of the SSDP’s Economic Development pillar is the
achievement of rural transformation to improve livelihoods and expand employment opportunities.
As identified in the SSDP, a key ingredient for rural transformation is the extension, upgrading and
maintenance of feeder roads. Sustainable feeder roads can improve livelihoods, reduce poverty and
improve security.
In this regard and in full consultation with the Government the EU proposed to support the Greater
Bahr el Ghazal (GBG) Zone in its effort to achieve agricultural development and the Zonal Effort for
Agricultural Transformation: Bahr el Ghazal Effort for Agricultural Development (ZEAT-BEAD, or ZB)
program was created. One of the components of this program is to build roads to increase
marketing volumes and increase access to productive areas.
In this connection, the EU and UNOPS have signed a contribution agreement for the
implementation of the action entitled ZEAT BEAD “Feeder Road Construction in support of Trade
and Market development in South Sudan” in line with the strategic objective of the EU’s programme
and others complimentary existing and envisaged programmes and assessed needs of
stakeholders. The key activities in this action also include Capacity Building within the State
Ministries of Physical Infrastructure and local contractors; community engagement and labour
intensive support activities.
The action will focus on the construction and maintenance of approximately 120 km of feeder roads
in Greater Bahr el Ghazal (Northern & Western Bahr el Ghazal, Warrap and Lakes State) States
incorporating the implementation of a maintenance and capacity building program. The objective is
to improve rural livelihoods by providing sustainable access to agricultural markets using
appropriately engineered infrastructure approaches. As part of the implementation process UNOPS
will undertake a feasibility study and a social and environmental impact assessment for the priority
routes proposed by the respective States Ministry of Physical Infrastructure and Ministries of
Agriculture. This process will allow for appropriate road section selection for construction along the
SOUTH SUDAN OPERATIONS CENTRE
10
QUALITY MANAGEMENT PLAN
priority routes that will fit with the planned project length of roads and be relevant to the
ZEAT BEAD and/or SORUDEV feeder road programs by linking agricultural areas to markets.
6. ORGANISATION AND RESPONSIBILITIES
6.1 PROJECT SPECIFIC QUALITY MANAGEMENT ORGANIZATION CHART
Organogram 1: UNOPS is responsible for managing Project’s Quality
Infrastructure Project Manager
Richard Schroeder
SMQR
Deputy PM
Solomon Kuliche
QMR
Project Engineer(s) IBRAHIM
KAMAU
QR
Contractor’s Representative
[Insert Name]
QR
SOUTH SUDAN OPERATIONS CENTRE
11
QUALITY MANAGEMENT PLAN
6.2 QUALITY CONTROL RESPONSIBILITIES (UNOPS)
Richard Schroeder
Senior Quality Management Representative
Solomon Kulicher
Quality Management Representative
IBRAHIM KAMAU
Quality Representatives
Area of Designated Responsibility Area of Designated Responsibility Area of Designated Responsibility
 Reviewing and authorizing the project Quality
Management Plan (QMP) and other project plans
 Assigning quality responsibilities to all project
personnel
 Ensuring all project personnel are suitably trained, and
possess the necessary skills, to undertake their
designated quality responsibilities
 Ensuring the provision of appropriate training in quality
for all project personnel
 Continually monitoring of quality performance to
ensure compatibility and continued effectiveness with
the UNOPS’s policy, objectives and other
requirements
 Allocating resources to ensure the project quality
objectives are achieved
 Participating in the review of the quality system and
other relevant quality meetings and programs
 Liaising with the Client on Quality issues.
 Preparing Quality Management Plan
 Ensuring procedures in the Quality Management Plan
are followed
 Ensuring the project QMP is correctly implemented to
meet the requirements of the project
 Allocating project staff to perform inspection duties
Preparation of work Method Statements (MS), Work
Procedures and Checklists (WIP and CL) and
Inspection & Test Plans (ITP’s)
 Reviewing prepared ITP’s, WIP’s and CL’s.
 Reviewing inspection reports and ensuring any actions
required are initiated
 Implement, verify and review the project’s preventive
and corrective action effectiveness
 Ensuring and verifying that agreed rectification works
and corrective action is taken when required for non-
conforming work
 Ensuring construction targets and programs are met
 Attending meetings called to discuss quality issues
 Identifying and reporting any quality management
system issues
 Auditing and assessment of contractor (report to
SQMR).
 Assisting in preparation of QMP
 Preparing Work Inspection Procedures and Checklists
(WIP and CL) and Inspection & Test Plans (ITP’s)
 Performing verifications and quality inspections as
requested
 Monitoring the implementation of
manufacture/construction activities
 Identifying and reporting material and/or workmanship
non-conformity and notifying the SQMR and QMR of the
suspected non-conformity
 Rejecting defective workmanship and materials
 Assisting with the maintenance of the project program
 Performing verifications and quality inspections as
requested by the SQMR and QMR
 Completing a diary on a project daily report
 Technical and logistic support to the SQMR and QMR
 Supervision of construction activities
 Identifying and reporting material deficiency and issuing
to contractor Defect Notification Report
 And every activity listed under 8.3 which is not included
above .
Designated Signature: Designated Signature: Designated Signature:
SOUTH SUDAN OPERATIONS CENTRE
12
QUALITY MANAGEMENT PLAN
6.3 QUALITY CONTROL RESPONSIBILITIES (UNOPS AND CONTRACTOR)
Richard Schroeder Senior Quality
Management Representative
IBRAHIM KAMAU
Quality Representatives
[insert Contractor's PM name]
Quality Management Representative
[Insert Contractor's PEs Name]
Quality Representatives
[insert contact number] [insert contact number] [insert contact number] [insert contact number]
Area of Designated Responsibility Area of Designated Responsibility Area of Designated Responsibility Area of Designated Responsibility
 Reviewing and authorizing the project
Quality Management Plan (QMP) and
other project plans
 Ensuring all project personnel are
suitably trained, and possess the
necessary skills, to undertake their
designated quality responsibilities
 Reviewing Contractor’s Quality Control
reports, tests and inspection results
 Participating in the review of the quality
system and other relevant quality
meetings and programs
 Liaising with the Client on Quality
issues.
 Ensuring procedures in the Quality
Management Plan are followed
 Conducting independent inspection to
verify quality of the works
 Reviewing inspection reports and
ensuring any actions required are
initiated
 Implement, verify and review the
project’s preventive and corrective
action effectiveness
 Reviewing and verifying that agreed
rectification works and corrective action
is taken when required for non-
conforming work
 Ensuring construction targets and
programs are met
 Attending meetings called to discuss
quality issues
 Ensuring that all QMP issues have been
identified and reported
 Ensuring that required documentation is
submitted
 Auditing and assessment of contractor
(report to SQMR).
 Preparing Quality Management Plan
 Assigning quality responsibilities to all
project personnel
 Ensuring procedures in the Quality
Management Plan are followed
 Ensuring the project QMP is correctly
implemented to meet the requirements of
the project
 Ensuring the provision of appropriate
training in quality for all project personnel
 Continually monitoring of quality
performance to ensure compatibility and
continued effectiveness with the UNOPS’s
policy, objectives and other requirements
 Allocating resources to ensure the project
quality objectives are achieved
 Identifying and reporting any quality
management system issues
 Implement, verify and review the project’s
preventive and corrective action
effectiveness
 Ensuring and verifying that agreed
rectification works and corrective action is
taken when required for non-conforming
work.
 Assisting in preparation of QMP
 Preparing Work Inspection Procedures
and Checklists (WIP and CL) and
Inspection & Test Plans (ITP’s)
 Performing verifications and quality
inspections as requested
 Monitoring the implementation of
manufacture/construction activities
 Identifying and reporting material and/or
workmanship non-conformity and
notifying QMR
 Rejecting defective workmanship and
materials
 Assisting with the maintenance of the
project program
 Performing verifications and quality
inspections as requested by QMR
 Completing a diary on a project daily
report
 Technical and logistic support to QMR
 Supervision of construction activities
 Identifying and reporting any quality
management system issues
 And every activity listed under point 8.3
which is not included above.
Designated Signature: Designated Signature: Designated Signature: Designated Signature:
SOUTH SUDAN OPERATIONS CENTRE
13
QUALITY MANAGEMENT PLAN
6.4 SCHEDULE OF KEY ACTIVITIES
No. Work Activity Inspection and Test Plan Work Procedure
Date
required
Action by:
Reviewed
by:
01 Mobilization Complete/impartial
Take inspection and record all items in
question before commencement
02 Camp site layout As specs,
Before set out obtain land approval from
local authority.
02
Setting/Survey
work
Chain ages set,
Survey team with survey equipment
Request to survey( RTS) and approval to
proceed issued by Client Engineer
03 Bush clearance Within specs ,stamps, roots are removed
Obtain letter of commencement from PM
and local authority
04 Trees cutting
Tree falling within working area ,No and
options of pruning branches only
Letter from forestry and fishery
05 Embankment
Layers, compaction, materials and
moisture contents
Request for testing ( RFT) form filled and
signed
06 Sub base layers
Compaction ,material and moisture
contents
07
Gravel wearing
course
Borrow pit and compaction test/inspection Request for testing
08 Road Furniture’s
Sign posts ,KM stone, Alienators’ ,safety
installation
09 Drainage works De-silting ,invert level, position and size
SOUTH SUDAN OPERATIONS CENTRE
14
QUALITY MANAGEMENT PLAN
7. COMMITMENT AND COMPETENCY
7.1 LEADERSHIP AND COMMITEMENT
It is UNOPS’s intent that its managers and supervisors at all levels, by means of their actions and
behaviour, provide visible and pro-active commitment to Quality Management.
Demonstrated proactive and visible leadership and commitment to Quality on this Project shall
include carrying out activities such as:
 Setting clear quality objectives
 Project Management conducting site visits
 Senior management participating in audits
 Involving the workforce in addressing quality issues
 Encouraging open communication on quality issues
 Encouraging an environment of continual improvement
 Adhering to the Standards set by UNOPS Management System
 The recognition and reward of outstanding contributions to quality performance
7.2 COMPETENCY AWARENESS & TRAINING
The competency needs of all personnel performing activities which affect the quality of
manufacture/construction shall be identified by UNOPS SQMR and QMR. Personnel performing
specified assigned tasks shall be appropriately qualified on the basis of training, skills and/or
experience, which will be confirmed by UNOPS and /or the Contractors Project Management team
as required.
The QMR shall be responsible for ensuring site personnel hold current and relevant qualifications
for the work they are required to perform and maintain training records. Records of training and
competencies (written confirmation by Contractors PM) will be kept and maintained in relevant
project files.
Training needs for project personnel shall be identified giving consideration to: the knowledge and
skills required from the position to fulfil the realization of the requirements within UNOPS
Management System.
SOUTH SUDAN OPERATIONS CENTRE
15
QUALITY MANAGEMENT PLAN
8. CONTROL OF WORK PROCESSES
Effective Quality Control requires a serious and concerted effort on the part of the supervisory and
inspection personnel. Tools for the accomplishment of effective Quality Control are as follow:
 Before start of construction, the UNOPS SQMR/QMR shall conduct a mutual understanding
meeting with the contractor and discuss the contractor’s quality management system
 Construction Works will commence only after mutual understanding between UNOPS and
Contractor has been achieved.
8.1 CONTROL OF WORKS PLAN PHASING
Control of Work Processes will comprise the following 3 phases:
 Preparatory phase meetings: WP meeting will be held before each definable feature of
work to ensure that the documentation is complete, materials are on hand, and the people
who are to perform the work understand what they need to know about the feature of work.
Both the actual contract specifications and those referenced in the contract specifications
shall be in the contractor’s library and available to the control of WP inspections.
 Initial Inspections: Control of WP inspections shall be conducted in a timely manner at the
beginning of a definable feature of work. A check of the preliminary work will determine
whether or not the Contractor, through his craftsmen involved, thoroughly understand and is
capable of accomplishing the work as specified.
 Follow-up Inspections: follow- up inspections also conducted by UNOPS and contractor’s
quality management personnel, occur daily when work is in progress and are for the purpose
of assuring that the controls established in the earlier phases of inspection continue to
provide work which conforms to the contract requirements. 3
8.2 INSPECTION AND TESTING
The status of the constructed works will be identified by the progressive completion of Inspection
and testing documentation which are Inspection & Test Plans, Work Inspection Procedures and
Checklists.
UNOPS team and contractors shall be responsible for the quality of the works. Checklists will be
signed for each operation (earth work, concrete work, metal work, roofing work, finishes work,
landscape work, etc. including mechanical, electrical and hydraulic works) to verify that works have
been completed in accordance with requirements.
Independent inspections shall be carried out to verify that the self-certification process is being
operated correctly. Requirements for independent inspections shall be identified on Inspection &
3
In all projects, there is work that is ‘cut and cover’, work that cannot be inspected “after the fact”. This includes concrete where the size,
number and location of reinforcing steel cannot be readily determined after the concrete is placed. Most of the underground utilities
cannot be inspected after covering. Work of this nature shall be closely controlled and monitored. A disadvantage with the system arises
from the fact that Contractor’s personnel, are unlikely to readily take actions which will result in delay and expense to the contractor for
the ask of quality. for example, if concrete is to be placed with a maximum slump of 6cm, it is unlikely that a load with 10cm or 12cm
slump will be rejected. If roofing bituminous material is overheated, it is unlikely that it will be rejected. The deficiencies occasioned by
these conditions may become latent defects revealed long after any possible contractor liability can be enforced.
SOUTH SUDAN OPERATIONS CENTRE
16
QUALITY MANAGEMENT PLAN
Test Plan, Check-lists.
Independent inspections can be completed by appointed persons within the Project team. Non-
conformances, defects or outstanding works shall be recorded as specific in UNOPS Procedures.
Where an independent inspection is completed with all matters correct, this inspection can be
recorded as “right first time” and used as a performance indicator.
Inspections and Test Plans define the inspection and testing requirements of the project including:
 Activity Description
 Inspection or Item Description
 Acceptance Criteria
 Inspection Frequency
 Inspection Test/Procedure
 Hold Point Identification
 Responsibility for carrying the inspection.
UNOPS QMR will monitor the preparation of ITP’s4
:
 Watch for omissions
 Watch for discrepancies between plans and specifications
 Check plans and specifications against requirements of which problems occurred on similar
jobs
 Compare elevations, grades and details shown on plans as exiting, with those at the actual
site
 Report all errors, omissions, discrepancies, and deficiencies to the SQMR.
*Always keep a posted and marked up set of plans and specifications convenient for ready reference.
*Make sure that construction contractor has this same information.
8.2.1 Storage of Materials
UNOPS QR shall5
:
 ensure/produce site organisation and management plan (location of material storage)
 ensure that adequate space is available for the contractor’s operations and storage areas
 ensure that approval has been obtained for temporary sheds, buildings, etc. which the
contractor proposes to install
 ensure that materials and equipment’s are properly stored and protected
 ensure that safety requirements, especially in the storage of flammable or explosive
materials, are adhered to
 ensure temporary structures are secured against wind damage
 ensure the necessary heating and ventilating systems are provided.
4
See: Point 6.2 Quality Control Responsibilities.
5
Appendix 7.
SOUTH SUDAN OPERATIONS CENTRE
17
QUALITY MANAGEMENT PLAN
8.3 SUBMITTALS
This section describes the procedures for submittals.
8.3.1 Shop Drawings
The QR shall:
 administer, control, and process submittals from the construction contractor(s)6
 review all contractor submittals, and related supporting documents, to ensure compliance
with project specifications and drawings
 prepare submittal register for plans, and specifications
 Check submittal register for inclusion of all shop drawings required including layouts of
equipment, equipment rooms, etc.
 ensure that all data is registered and submitted to the QMR
 ensure that the submittal register is periodically updated
 make continual checks of the submittal register to avoid untimely and omitted submittals so
as to avoid delay of constructions
 compare the shop drawings to the contract requirements and report apparent differences to
the QMR and SQMR
 ensure each detail on the shop drawings is clearly understood by the constructions contract
requirements
 ensure that the contractor makes note on his submittal of items which deviate from contract
requirements
 check materials being installed against the approved shop drawing (if the contractor installs
unapproved material, inform him in writing that the material, if not subsequently approved,
will be removed at his expense).
*The submittals disposition will be noted on the submittal, which will be signed, dated and recorded.
If required, the QR will return the submittal to the contractor for revision, incorporating the
comments. The contractor shall resubmit it for review and verification for compliance. Submittals
will be logged and copies will be retained in the project files. Results shall be recorded and available
for review. [see conditions of contract]
8.3.2 Material Submittal Schedule
The construction contractor will prepare and submit a submittal schedule to the QR, which will then
be provided to UNOPS project manager, the schedule should be linked to the Contractor’s
approved programme of works. The schedule will be initially submitted within [see conditions of
contract] after the award of the contract and updated on a monthly basis. The QMR shall work with
the contractor to prioritize and sequence submittals so that the most critical submittals are received
and processed first (preparation of submittal schedule). The submittal schedule will become the
baseline against which receipt of all required submittals will be compared. The approved submittal
schedule will be forwarded to the UNOPS PM for resource availability planning.
7
6
See: 8.3.3 Process Review and Acceptance.
7
Appendix 1.
SOUTH SUDAN OPERATIONS CENTRE
18
QUALITY MANAGEMENT PLAN
8.3.3 Process, Review and Acceptance
Submittals will be managed as follows:
[Fill this section according to contractor’s capacity and Project Construction Contract conditions; for
further detailed information see example provided together with this template]
8.3.4 Storage
The QMR will maintain all submittal files via a combination of a secure document filing and storage
system. All submittal records will be provided to the UNOPS PM as part of the project closeout
documentation.
8.4 CONSTRUCTION NONCONFORMITIES/DEFICIENCIES
This section provides procedures for tracking construction nonconformities/deficiencies from
identification through acceptable corrective action. It defines the controls and related responsibilities
and authorities for dealing with noncompliant products or services.
8.4.1 Non-conformance/Deficiency Identification and Notification
Non-conformance/deficiency occurs when a material, performed work, or installation does not meet
the plans and/or specifications for the project. Any item of work found to be deficient will be
identified by the inspector on the Non-conformance Report as described in this section.
8.4.2 Non-conformance and Non-conformance Report (NCR)8
Non-conformances are major deviations from the project specifications and the contract requirement
and/or accepted standard of quality, which shall be formally documented for corrective action by
UNOPS project staff or the third party testing group. Failure by a contractor to correct a minor
deficiency after having been put on notice will also result in a non-conformance if it is not corrected
within time frame stated in the Condition of Contract. Non-conformances shall be formally
documented on the example Non Conformance Report form. The Non-conformance report shall be
distributed to the contractor and UNOPS SQMR and QMR.
The Non-Conformance Report (NCR) is a formal notification to the contractor that work does not
meet the plans or the specifications for the project. Any item of work found to be deficient- out of
conformance with the construction drawings and/or specifications - will be identified by the inspector
on the non-conformance report as described in this section. Non-conformance reports will be
included on the non-conformance register9
and tracked through verification that the non-
conformance has been corrected.
8.4.3 Preventive Actions
Preventive actions are to be taken to eliminate the cause of a potential non-conformity. For
example, defects that appear on the surface of concrete during construction or within a relatively
short time after completion are usually caused by poor quality materials, improper mix design, lack
8
Appendix 2
9
Appendix3
SOUTH SUDAN OPERATIONS CENTRE
19
QUALITY MANAGEMENT PLAN
of proper placing and curing procedures, or poor workmanship. UNOPS shall take preventive
actions as necessary to eliminate the causes of potential deficiencies so as to prevent their
occurrence.
8.5 DOCUMENTATION CONTROL
Quality Documentation developed specifically for the project shall be controlled on site by the QR.
8.5.1 Drawings records
 The contractor’s record drawings shall be reviewed monthly by UNOPS
 Project and design office staff to ensure that they are correct
 Ensure that as soon as a change or addition is made in construction it is noted on the record
drawing
 See that the following items are considered in the changes for Record
 Drawings:
· [Insert List of Drawings Specific for the Project]
 Draft final record drawings will be prepared and submitted by Contractor to UNOPS SQMR
for review in order to prepare final drawings record (As built) based on UNOPS PM
Comments. [See: Conditions of Contract for Works]
8.5.2 Final Reporting
The following quality related documents will be generated during implementation of the Project and
will be submitted to the Quality Control file that will be handed over to the end user on project
completion.
Work Completion Report:
 Record (as-built) drawings
 Operation and maintenance manuals; and
Results of the Start-up and Testing Plan and the Commissioning Plan implemented for each major
piece of equipment or system before system turnover, in accordance with Technical Specification
Contractor Quality Program Requirements.
8.5.3 Defect Notification Period
Defect Notification Period means the period for notifying defects in the Works (as the case may be)
under the clause 1)"Defects Notification Period and Final Completion", as stated in the “Minor
Works Contract”; 2-3)“Defect Liability”, as stated in the “Measured Price Construction Contract” and
“Lump Sum Construction Contract”, which is calculated from the date on which the Works is
completed as certified under the clause 1) "Substantial Completion and Taking Over", within “Minor
Works Contract”; 2-3)”Employer’s Taking Over” within “Measured Price Construction Contract” and
“Lump Sum Construction Contract”.
When material, performed work or installation is found to be deficient, the QR will assure deficiency
correction is implemented. The QR shall ensure that the defected material, work or installation is
identified and controlled to prevent unintended use or delivery.
SOUTH SUDAN OPERATIONS CENTRE
20
QUALITY MANAGEMENT PLAN
UNOPS will instruct contractor to implement corrective actions to remedy work that is not in
accordance with the drawings and specifications. The corrective actions will include removal and
replacement of deficient work using methods approved by the UNOPS Project Manager. Removal
shall be done in a manner that does not disturb operation of the product; otherwise, the disturbed
material shall also be removed and replaced. Replacement shall be done in accordance with the
corresponding technical specifications. Replacement will be subjected to the same scope of Quality
Control inspection and testing as the original work. If the replacement work is not in accordance with
the drawings and specifications, the replacement work will be removed, replaced, re inspected, and
re-tested. All activities undertaken with regards to defects shall be recorded in Defects Register.10
Any item of work found to be deficient will be identified by the PE and issued by Contractor on the
Defect Notification
11
as described in this section.
FINALLY
It is essential that work is carried out in line with the contract requirements and the UNOPS
systems. Therefore please follow instructions and if work appears to be carried out incorrectly,
please inform your supervisor before you go too far and it is covered up. If in doubt please ask!
10
Appendix 4.
11
Appendix 5.
SOUTH SUDAN OPERATIONS CENTRE
21
QUALITY MANAGEMENT PLAN
9. APPENDIXES
9.1 APPENDIX 1 - MATERIAL APPROVAL REQUEST
Project: EU-ZEAT BEAD Feeder Roads, Greater Bahr el-
Ghazal ,RSS
Request No:
Contractor: Date:
Item Submitted:
Discipline : Civil Building Mechanical Electrical
Description:
Supplier/Manufacture, including model number:
BOQ Ref.: Specification Ref.:
Attachments:
Data Sheet Catalogue Sample
For Contractor
Discipline Engineer Name: Signature:
Project Manager Name: Signature:
For UNOPS
Received Date: Received Time:
Received By: Signature:
UNOPS Action:
Approved Not Approved
Approved As Noted Others: ...................................................
Remarks: ........................................................................................................................................................
Action by: Signature: Date:
For UNOPS Project Manager Use:
........................................................................................................................................................................
Project Manager Name: Signature: Date:
Contractor Receive
Received Date: Received Time:
Received By: Signature:
SOUTH SUDAN OPERATIONS CENTRE
22
QUALITY MANAGEMENT PLAN
9.2 APPENDIX 2 - NON-CONFORMANCE REPORT
Project EU –ZEAT- BEAD- Feeder Roads, Greater Bahr el-Ghazal South
Sudan.
Contract No
Contractor
Trade/Activity
Date Non-conformance report number
Details Of Non Conformance:
(Note specifications, drawings, standards, procedures etc departed from, attach photos if applicable)
Type of Non Conformance:
Material Fault Workmanship Product Supply Safety Quality Environmental
Remedial Works Required:
To be completed By Date: …………………
Input and Approval required by Design Consultants: Yes No Approved: ...................
Corrective Action to Prevent Recurrence:
Corrective Action confirmed and carried out Date: ………………..... By Contractor: ……................
SOUTH SUDAN OPERATIONS CENTRE
23
QUALITY MANAGEMENT PLAN
Close Out Confirmed Date…………………………………….............. By UNOPS: …….....................
SOUTH SUDAN OPERATIONS CENTRE
24
QUALITY MANAGEMENT PLAN
9.3 APPENDIX 3 - NON-CONFORMANCE REGISTER
Project Title: EU –ZEAT –BEAD-Feeder Roads, Lakes state South Sudan.
Non
Conformance
Number
Date
Issued
Non Conformance Details
Date
Remedial
Work
Complete
Date
Corrective
Action
Complete
Non
Conformance
Closed Out
SOUTH SUDAN OPERATIONS CENTRE
25
QUALITY MANAGEMENT PLAN
9.4 APPENDIX 4 - DEFECTS REGISTER
Project: EU- ZEAD -BEAD
Feeder Roads, Lakes State
Contract No
Contractor
Defect
No.
Defect Details Date Issued
to Contractor
Remedial Actions To be
completed
by
Date Work
Started
Date Work
Completed
Sign Off
(Inspected
and approved
repairs)
Comments (Design
required, extend
periods, guarantees,
maintenance)
SOUTH SUDAN OPERATIONS CENTRE
26
QUALITY MANAGEMENT PLAN
9.5 APPENDIX 5 - DEFECT NOTIFICATION
Project EU-ZEAT-BEAD Feeder Roads, Lakes state South Sudan.
Contract No
Contractor
Trade/Activity
Date Defect notification number
Details of Defect:
(Note specifications, drawings, standards, procedures etc departed from, attach photos if applicable)
Type of Defect:
Material Fault Civil Mechanical Electrical Safety & Environmental Other
Defect Classification:
Critical (creates direct risk to proper operation of the facility or safety – to be fixed ASAP)
Operational (no direct risk to operation of facility or safety – fix date to be agreed)
Remedial Works Required:
To be completed By Date: …………………
Input and Approval required by Design Consultants: Yes No
Signed by Contractor: …………………………………….............. Date: …….....................
Signed by UNOPS: …………………………………….............. Date: …….....................
SOUTH SUDAN OPERATIONS CENTRE
27
QUALITY MANAGEMENT PLAN
9.6 APPENDIX 6 - MATERIAL STORAGE CHECKLIST
Purpose: Material Storage Location: [Insert Location]
No. Inspection Task Hold Responsibility Date Signature
1 Check if adequate space is available for the
contractor’s operations and storage areas
2 Check if approval has been obtained for
temporary sheds, buildings, etc. which the
contractor proposes to install
3 Check if materials and equipment’s are
properly stored and protected
4 Check if safety requirements, especially in
the storage of flammable or explosive
materials, are adhered to
5 Check if temporary structures are secured
against wind damage
6 Check if necessary heating and ventilating
systems are provided
7 Check on un bended nails ,debris etc
8 Check on Stacking and spacing of materials
9 Air circulation and the area below the
stacked items( materials)
Final Inspection by: Date: QMR Signature:
SOUTH SUDAN OPERATIONS CENTRE
28
QUALITY MANAGEMENT PLAN
9.7 APPENDIX 7 – QUALITY POLICY
SOUTH SUDAN OPERATIONS CENTRE
29
QUALITY MANAGEMENT PLAN
SOUTH SUDAN OPERATIONS CENTRE
30
QUALITY MANAGEMENT PLAN

More Related Content

PDF
Construction Monthly Progress Report - June 2011
Jamal Nelson, CCM
 
PDF
H.V.A.C building service in b.arch ciriculam
Kethees Waran
 
PDF
Stages Of Road Construction: Step by Step
Envirotac Inc.
 
PPTX
Disability friendly manual
tashi dorji
 
PPT
Cold chain equipment
drdduttaM
 
PPTX
17. AASHTO Rigid Pavement Design (Example).pptx
Ghulam Mehdi Sahito
 
PDF
Aci 216.1 07 code requirements for determining fire resistance of concrete an...
AdilAhmad72
 
PPTX
Project development cycle
Aswin prakash i , Xantus Technologies
 
Construction Monthly Progress Report - June 2011
Jamal Nelson, CCM
 
H.V.A.C building service in b.arch ciriculam
Kethees Waran
 
Stages Of Road Construction: Step by Step
Envirotac Inc.
 
Disability friendly manual
tashi dorji
 
Cold chain equipment
drdduttaM
 
17. AASHTO Rigid Pavement Design (Example).pptx
Ghulam Mehdi Sahito
 
Aci 216.1 07 code requirements for determining fire resistance of concrete an...
AdilAhmad72
 
Project development cycle
Aswin prakash i , Xantus Technologies
 

What's hot (20)

DOCX
Five ways to improve productivity at the construction site
Vikaslal2006
 
PPTX
MK50 Lifejacket & PSTASS EBS - Helicopter Operator Introduction new
Ross Johnston
 
PPTX
PROCUREMENT: Expediting How To - General
Sierra Romeo
 
PPTX
VSM (Lean Manufacturing) Project PPT
FASI93
 
PPTX
237db pengendalian pelaksanaan_proyek_pisk2
AndikaAkbar8
 
PDF
Material approval procedure
Mohammad Eyaz Ansari
 
PDF
Pdf primavera tutorial
Ketut Swandana
 
PDF
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
HossamNegidaPMPRMPPS
 
PPTX
Presentation kanban
Nasir Shakil
 
PDF
Rajasthan Solar Roof Top tender 2014-2015
Headway Solar
 
PPT
Ffs assessment
Muhammad Akhtar
 
PPTX
Kaizen SMT_MI_PCBA for Quality Engineerspptx
vaibhavsrivastava482521
 
DOCX
Conveyor Belt Project Report
RISHABHSIINGH
 
PPTX
Poka Yoke
Aditya Ramachandran
 
PDF
Quality Control and Improvement in Manufacturing
SSA KPI
 
PPTX
Poke-Yoke or Mistake-proofing
Akshita Pillai
 
PDF
Introduction, development and analysis of banana curve in project management....
Muhammad Mujahid PMP®, PSP®, SP®, APMC®
 
PDF
Iatf 16949 2016 block diagram flow (aug 7, 2018)
Pricha Leelanukrom
 
PDF
APQP
Pankaj Nalwa
 
PPT
DNV GL Asset Life Extension (ALE) Projects Showcase
Ian Ng
 
Five ways to improve productivity at the construction site
Vikaslal2006
 
MK50 Lifejacket & PSTASS EBS - Helicopter Operator Introduction new
Ross Johnston
 
PROCUREMENT: Expediting How To - General
Sierra Romeo
 
VSM (Lean Manufacturing) Project PPT
FASI93
 
237db pengendalian pelaksanaan_proyek_pisk2
AndikaAkbar8
 
Material approval procedure
Mohammad Eyaz Ansari
 
Pdf primavera tutorial
Ketut Swandana
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
HossamNegidaPMPRMPPS
 
Presentation kanban
Nasir Shakil
 
Rajasthan Solar Roof Top tender 2014-2015
Headway Solar
 
Ffs assessment
Muhammad Akhtar
 
Kaizen SMT_MI_PCBA for Quality Engineerspptx
vaibhavsrivastava482521
 
Conveyor Belt Project Report
RISHABHSIINGH
 
Quality Control and Improvement in Manufacturing
SSA KPI
 
Poke-Yoke or Mistake-proofing
Akshita Pillai
 
Introduction, development and analysis of banana curve in project management....
Muhammad Mujahid PMP®, PSP®, SP®, APMC®
 
Iatf 16949 2016 block diagram flow (aug 7, 2018)
Pricha Leelanukrom
 
DNV GL Asset Life Extension (ALE) Projects Showcase
Ian Ng
 
Ad

Similar to Annex 4 - Quality Management Plan.pdf (20)

PDF
Vol. 8 of emap environmental management plan
zubeditufail
 
PDF
Final Certified Environmental Impact Report
StopHermosaBeachOil
 
PDF
Monitoring and evaluation_plan____a_practical_guide_to_prepare_good_quality_m...
Malik Khalid Mehmood
 
PDF
Project Safety Quality Plan For Safety00
hsemahtab2030
 
PDF
USACE Construction Quality Management manual
Jerico Awat
 
PDF
Us gsa (1992) value engineering program guide for design and construction -...
Wan Yusoff Wan Mahmood
 
DOCX
Post Implementation Review Template
Edmond Cheng
 
PDF
Monitoring of project implementation
Dejened
 
PDF
Monthly Progress Report Sample
Elias Ibrahim
 
PDF
33134 handbook ict wp2013 fixed deadline calls v2 en
Rob Blaauboer
 
PDF
Tgm comman hazardous waste treatment 010910_nk_0
Sahil Anuj
 
PDF
design_quality_assurance_plan.pdf
LuisMogrovejo3
 
PDF
design_quality_assurance_plan.pdf
LuisMogrovejo3
 
PDF
NASA_RCMGuide.pdf
GiovanniHernndez31
 
PDF
test-plan-template-05.pdf
gintpt
 
PDF
OPNAVINST 4860.7C.PDF
Thomas F. Kaplan and Associates
 
PDF
Plano gerenciamento da qualidade - exemplo real (em inglês)
Diego Minho
 
PDF
Cost studies
Sasi Cool
 
PDF
IT Project Planning Standards V 1.2
Ahmed303
 
PDF
Cementa Ab Applied Process Management Group Iv Report Process Blue Printing
dzikothunde
 
Vol. 8 of emap environmental management plan
zubeditufail
 
Final Certified Environmental Impact Report
StopHermosaBeachOil
 
Monitoring and evaluation_plan____a_practical_guide_to_prepare_good_quality_m...
Malik Khalid Mehmood
 
Project Safety Quality Plan For Safety00
hsemahtab2030
 
USACE Construction Quality Management manual
Jerico Awat
 
Us gsa (1992) value engineering program guide for design and construction -...
Wan Yusoff Wan Mahmood
 
Post Implementation Review Template
Edmond Cheng
 
Monitoring of project implementation
Dejened
 
Monthly Progress Report Sample
Elias Ibrahim
 
33134 handbook ict wp2013 fixed deadline calls v2 en
Rob Blaauboer
 
Tgm comman hazardous waste treatment 010910_nk_0
Sahil Anuj
 
design_quality_assurance_plan.pdf
LuisMogrovejo3
 
design_quality_assurance_plan.pdf
LuisMogrovejo3
 
NASA_RCMGuide.pdf
GiovanniHernndez31
 
test-plan-template-05.pdf
gintpt
 
OPNAVINST 4860.7C.PDF
Thomas F. Kaplan and Associates
 
Plano gerenciamento da qualidade - exemplo real (em inglês)
Diego Minho
 
Cost studies
Sasi Cool
 
IT Project Planning Standards V 1.2
Ahmed303
 
Cementa Ab Applied Process Management Group Iv Report Process Blue Printing
dzikothunde
 
Ad

More from LuisMogrovejo3 (20)

PDF
Diseño del sistema integrado de gestión de la calidad. Fruti-Dulces _planteam...
LuisMogrovejo3
 
PDF
Final Quality Management Plan.pdf
LuisMogrovejo3
 
PDF
CIOB_Code_of_Quality_Management.pdf
LuisMogrovejo3
 
PDF
general_civil_construction_standard.pdf
LuisMogrovejo3
 
PDF
Diseño del sistema integrado de gestión de la calidad. Fruti-Dulces _planteam...
LuisMogrovejo3
 
PDF
Design-Build Quality Management Plan (QMP) Outline.pdf
LuisMogrovejo3
 
PDF
Final Quality Management Plan.pdf
LuisMogrovejo3
 
PDF
-Constructability-Analysis-of-Monorail-Project.pdf
LuisMogrovejo3
 
PDF
_iso_9001_2008_fiscalización_.pdf
LuisMogrovejo3
 
PDF
_manual_procedimentos_2016_.pdf
LuisMogrovejo3
 
PDF
_4D_quality_.pdf
LuisMogrovejo3
 
PDF
QMSP.pdf
LuisMogrovejo3
 
PDF
CIOB_Code_of_Quality_Management.pdf
LuisMogrovejo3
 
PDF
Final Quality Management Plan.pdf
LuisMogrovejo3
 
PDF
Design-Build Quality Management Plan (QMP) Outline.pdf
LuisMogrovejo3
 
PDF
best-practices-2015_monorail_.pdf
LuisMogrovejo3
 
PDF
-Constructability-Analysis-of-Monorail-Project.pdf
LuisMogrovejo3
 
PDF
Diseño del sistema integrado de gestión de la calidad. Fruti-Dulces _planteam...
LuisMogrovejo3
 
PDF
PG-Q-03_-_Gestion_De_No_Conformidades_Rev.00.pdf
LuisMogrovejo3
 
PDF
general_civil_construction_standard.pdf
LuisMogrovejo3
 
Diseño del sistema integrado de gestión de la calidad. Fruti-Dulces _planteam...
LuisMogrovejo3
 
Final Quality Management Plan.pdf
LuisMogrovejo3
 
CIOB_Code_of_Quality_Management.pdf
LuisMogrovejo3
 
general_civil_construction_standard.pdf
LuisMogrovejo3
 
Diseño del sistema integrado de gestión de la calidad. Fruti-Dulces _planteam...
LuisMogrovejo3
 
Design-Build Quality Management Plan (QMP) Outline.pdf
LuisMogrovejo3
 
Final Quality Management Plan.pdf
LuisMogrovejo3
 
-Constructability-Analysis-of-Monorail-Project.pdf
LuisMogrovejo3
 
_iso_9001_2008_fiscalización_.pdf
LuisMogrovejo3
 
_manual_procedimentos_2016_.pdf
LuisMogrovejo3
 
_4D_quality_.pdf
LuisMogrovejo3
 
QMSP.pdf
LuisMogrovejo3
 
CIOB_Code_of_Quality_Management.pdf
LuisMogrovejo3
 
Final Quality Management Plan.pdf
LuisMogrovejo3
 
Design-Build Quality Management Plan (QMP) Outline.pdf
LuisMogrovejo3
 
best-practices-2015_monorail_.pdf
LuisMogrovejo3
 
-Constructability-Analysis-of-Monorail-Project.pdf
LuisMogrovejo3
 
Diseño del sistema integrado de gestión de la calidad. Fruti-Dulces _planteam...
LuisMogrovejo3
 
PG-Q-03_-_Gestion_De_No_Conformidades_Rev.00.pdf
LuisMogrovejo3
 
general_civil_construction_standard.pdf
LuisMogrovejo3
 

Recently uploaded (20)

PDF
EVS+PRESENTATIONS EVS+PRESENTATIONS like
saiyedaqib429
 
PPTX
Edge to Cloud Protocol HTTP WEBSOCKET MQTT-SN MQTT.pptx
dhanashri894551
 
PDF
Chad Ayach - A Versatile Aerospace Professional
Chad Ayach
 
PDF
오픈소스 LLM, vLLM으로 Production까지 (Instruct.KR Summer Meetup, 2025)
Hyogeun Oh
 
PDF
67243-Cooling and Heating & Calculation.pdf
DHAKA POLYTECHNIC
 
PPTX
database slide on modern techniques for optimizing database queries.pptx
aky52024
 
PDF
dse_final_merit_2025_26 gtgfffffcjjjuuyy
rushabhjain127
 
PDF
FLEX-LNG-Company-Presentation-Nov-2017.pdf
jbloggzs
 
PPTX
MSME 4.0 Template idea hackathon pdf to understand
alaudeenaarish
 
PPTX
Module2 Data Base Design- ER and NF.pptx
gomathisankariv2
 
PPTX
Victory Precisions_Supplier Profile.pptx
victoryprecisions199
 
PDF
Introduction to Ship Engine Room Systems.pdf
Mahmoud Moghtaderi
 
PPTX
AgentX UiPath Community Webinar series - Delhi
RohitRadhakrishnan8
 
PDF
6th International Conference on Artificial Intelligence and Machine Learning ...
gerogepatton
 
PDF
Activated Carbon for Water and Wastewater Treatment_ Integration of Adsorptio...
EmilianoRodriguezTll
 
PDF
A Framework for Securing Personal Data Shared by Users on the Digital Platforms
ijcncjournal019
 
PPTX
Production of bioplastic from fruit peels.pptx
alwingeorgealwingeor
 
PDF
5 Influence line.pdf for structural engineers
Endalkazene
 
PPTX
EE3303-EM-I 25.7.25 electrical machines.pptx
Nagen87
 
PPTX
Unit 5 BSP.pptxytrrftyyydfyujfttyczcgvcd
ghousebhasha2007
 
EVS+PRESENTATIONS EVS+PRESENTATIONS like
saiyedaqib429
 
Edge to Cloud Protocol HTTP WEBSOCKET MQTT-SN MQTT.pptx
dhanashri894551
 
Chad Ayach - A Versatile Aerospace Professional
Chad Ayach
 
오픈소스 LLM, vLLM으로 Production까지 (Instruct.KR Summer Meetup, 2025)
Hyogeun Oh
 
67243-Cooling and Heating & Calculation.pdf
DHAKA POLYTECHNIC
 
database slide on modern techniques for optimizing database queries.pptx
aky52024
 
dse_final_merit_2025_26 gtgfffffcjjjuuyy
rushabhjain127
 
FLEX-LNG-Company-Presentation-Nov-2017.pdf
jbloggzs
 
MSME 4.0 Template idea hackathon pdf to understand
alaudeenaarish
 
Module2 Data Base Design- ER and NF.pptx
gomathisankariv2
 
Victory Precisions_Supplier Profile.pptx
victoryprecisions199
 
Introduction to Ship Engine Room Systems.pdf
Mahmoud Moghtaderi
 
AgentX UiPath Community Webinar series - Delhi
RohitRadhakrishnan8
 
6th International Conference on Artificial Intelligence and Machine Learning ...
gerogepatton
 
Activated Carbon for Water and Wastewater Treatment_ Integration of Adsorptio...
EmilianoRodriguezTll
 
A Framework for Securing Personal Data Shared by Users on the Digital Platforms
ijcncjournal019
 
Production of bioplastic from fruit peels.pptx
alwingeorgealwingeor
 
5 Influence line.pdf for structural engineers
Endalkazene
 
EE3303-EM-I 25.7.25 electrical machines.pptx
Nagen87
 
Unit 5 BSP.pptxytrrftyyydfyujfttyczcgvcd
ghousebhasha2007
 

Annex 4 - Quality Management Plan.pdf

  • 1. UNOPS 2014 Quality Management Plan 88050 -EU ZEAT-BEAD Feeder Roads And [Insert Contractor's Name] Contract No.: [Insert Contract Number] Schedule No.: [Insert Schedule Number]
  • 2. SOUTH SUDAN OPERATIONS CENTRE 1 QUALITY MANAGEMENT PLAN 1. TABLE OF CONTENTS 1. Table of Contents.................................................................................................................. 1 2. Acronyms .............................................................................................................................. 2 3. Introduction ........................................................................................................................... 3 4. Approval, Distribution, Review and Audit ........................................................................... 4 4.1 Approval.............................................................................................................................................4 4.2 Distribution of complete project quality management plan................................................................4 4.3 Monitoring and review........................................................................................................................5 4.4 Inspection and Audit ..........................................................................................................................5 4.5 Record of Inspections, Audits and Reviews ......................................................................................7 4.6 QMR – Site Inspection Reporting Sheet............................................................................................8 5. QMP Objectives and Description of the Project.................................................................. 9 5.1 QMP Objectives.................................................................................................................................9 5.2 Description of the Project...................................................................................................................9 6. Organisation and Responsibilities..................................................................................... 10 6.1 Project specific Quality Management Organization Chart...............................................................10 6.2 Quality Control responsibilities (UNOPS) ........................................................................................11 6.3 Quality Control Responsibilities (UNOPS and Contractor)..............................................................12 6.4 Schedule of Key Activities ...............................................................................................................13 7. Commitment and Competency........................................................................................... 14 7.1 Leadership and Commitement.........................................................................................................14 7.2 Competency Awareness & Training ................................................................................................14 8. Control of work processes ................................................................................................. 15 8.1 Control of Works Plan Phasing........................................................................................................15 8.2 Inspection and Testing.....................................................................................................................15 8.2.1 Storage of Materials.................................................................................................................16 8.3 Submittals ........................................................................................................................................17 8.3.1 Shop Drawings.........................................................................................................................17 8.3.2 Material Submittal Schedule ....................................................................................................17 8.3.3 Process, Review and Acceptance ...........................................................................................18 8.3.4 Storage ....................................................................................................................................18 8.4 Construction Nonconformities/Deficiencies .....................................................................................18 8.4.1 Non-conformance/Deficiency Identification and Notification ...................................................18 8.4.2 Non-conformance and Non-conformance Report (NCR) ........................................................18 8.4.3 Preventive Actions ...................................................................................................................18 8.5 Documentation control.....................................................................................................................19 8.5.1 Drawings records.....................................................................................................................19 8.5.2 Final Reporting.........................................................................................................................19 8.5.3 Defect Notification Period ........................................................................................................19 9. Appendixes.......................................................................................................................... 21 9.1 Appendix 1 - Material Approval request ..........................................................................................21 9.2 Appendix 2 - Non-Conformance Report ..........................................................................................22 9.3 Appendix 3 - Non-Conformance Register........................................................................................24 9.4 Appendix 4 - Defects Register.........................................................................................................25 9.5 Appendix 5 - Defect Notification ......................................................................................................26 9.6 Appendix 6 - Material Storage Checklist .........................................................................................27 9.7 Appendix 7 – Quality Policy.............................................................................................................28
  • 3. SOUTH SUDAN OPERATIONS CENTRE 2 QUALITY MANAGEMENT PLAN 2. ACRONYMS  UNOPS-United Nations Office for Project Services  QMS-Quality Management System  QMP-Quality Management Plan  PCM-Project Centre Manager  PM-Project Manager  DPM-Deputy Project Manager/Senior Engineer  PE-Project Engineer  QMR-Quality Management Representative  SQMR-Senior Quality Management Representative  QR-Quality Representative  WP-Work Processes  ITP-Inspection and Test Plan  WIP-Work Inspection Procedures  CL-Checklist  NCR-Non Conformance Report
  • 4. SOUTH SUDAN OPERATIONS CENTRE 3 QUALITY MANAGEMENT PLAN 3. INTRODUCTION United Nations Office for Project Services (UNOPS) will perform the central role in managing Quality issues during the construction phase of the project. Our Site Management will ensure that the works are carried out to a high standard in compliance with client requirements, current legislation and guidance. This will be achieved by application of our Quality Control Management System. This information is available to all site personnel. This Quality Management Plan forms one part of the overall Quality Management System that has been developed for EU -ZEAT –BEAD- Feeder roads contract. It provides a guide for personnel involved in the construction of this project on how the quality requirements of the specifications are addressed. It has been developed from the information detailed within the ‘Contract Specification, Beneficiary Requirements and Agreement information’1 . 1 Legal Documentation provided prior to work commencing.
  • 5. SOUTH SUDAN OPERATIONS CENTRE 4 QUALITY MANAGEMENT PLAN 4. APPROVAL, DISTRIBUTION, REVIEW AND AUDIT Project Name: EU- ZEAT-BEAD-Feeder Roads Project. Project Number: 088050 4.1 APPROVAL Date Signature Approved by Donor* Approved by Project Centre Manager* Approved by Project Manager* Reviewed by the Deputy PM* Reviewed by the Project engineer* [Insert other positions that are relevant to Project/Office] * These signatures are required for the first issue only. Thereafter the Project Manager can approve changes which shall be recorded in the review section of the Plan. 4.2 DISTRIBUTION OF COMPLETE PROJECT QUALITY MANAGEMENT PLAN No Name Role Location 1 GIRLANDO PAOLO EUROPEAN UNION( EU) JUBA 2 Richard Shroeder Senior Quality Management Representative/ Project Manager JUBA 3 Solomon Kuliche Quality Management Representative/ Deputy PM JUBA 4 IBRAHIM KAMAU Quality Representative/ Project engineer GREATER BAHR EL- GHAZAL STATE 5 [Insert contractors representative] [Insert Contractor] GREATER BAHR EL- GHAZAL STATE * Copy of front page with authorized signature only to be emailed. Copy 1 is the Master QMP and is the only controlled copy containing records of all reviews and amendments.
  • 6. SOUTH SUDAN OPERATIONS CENTRE 5 QUALITY MANAGEMENT PLAN 4.3 MONITORING AND REVIEW The Project Manager shall ensure that the Project Quality Management Plan is reviewed monthly to ensure that:  The objectives and requirements of the Project Quality Management Plan are still valid, and are being met.  Forthcoming activities are reviewed and any necessary amendments to the Project Quality Management Plan are put in place before the relevant work begins  QMP processes shall be reviewed to ensure continuing suitability and effectiveness. The Project Manager is accountable for the development and implementation of the Quality Plan and delegates the responsibility for the development and implementation of this plan to the Quality Management Representative (QMR). The Quality Management Plan is issued with the authority of the Project Manager. All changes to the Quality Management Plan will be reviewed and authorised by the Project Manager. Everybody who works for UNOPS, whether as an employee or contractor, has a responsibility to fulfil UNOPS’s quality policy and objectives, and is expected to work towards achieving these organizational objectives. Finally the schedule in this section, which is maintained only in the Master Copy of the Project Quality Management Plan, shall be completed to confirm that the review has taken place. On a weekly basis QMP performance and production matters shall be reviewed. Problems encountered in compliance with or achievement of the processes for direct work shall be recorded, e.g. in meeting minutes, Non-conformance Report, etc. Requirements for the coming week shall also be considered to include improvements gained from the review, and noted to staff for action. Project Engineers are responsible for ongoing monitoring of QMP matters. The site based Quality Management Representative is: IBRAHIM KAMAU The site based Quality Management Representative (QMR) is responsible for monitoring quality matters and shall also conduct a phase based inspection. The information obtained from these inspections will be used by the ‘QMR (Deputy PM) to produce the monthly quality report. This monthly report will be issued to the SQMR (Project Manager)’2 . 4.4 INSPECTION AND AUDIT The DPM will conduct checks in accordance with Project Manager QMP Tours to confirm that processes are being carried out effectively. A record of these checks shall be noted in this section. Inspections will be carried out on a regular basis by QMR with a written report being submitted to PM (SQMR) for review and action. UNOPS personnel responsible for Quality Control for this project are: Quality Management Representative: IBRAHIM KAMAU 2 [Explain roles and responsibilities for your specific project].
  • 7. SOUTH SUDAN OPERATIONS CENTRE 6 QUALITY MANAGEMENT PLAN A UNOPS personnel responsible for Auditing Quality Management System for this project is: Project Manager, Richard Shroeder. UNOPS personnel responsible for Senior Auditing Quality Management System for this project is: Project Centre Manager/Programme Manager. Formal planned audits of the System shall be carried out by the UNOPS Senior Manager and reports shall be submitted to Project Manager. These audits shall include assessments of the Organisation Management System operating on this contract. Additional Supply Chain and site audits shall be conducted upon request. Audits carried out on the Project by external/client bodies shall be recorded in this section. Any reports issued by these parties to the site shall be copied to the QMP Department.
  • 8. SOUTH SUDAN OPERATIONS CENTRE 7 QUALITY MANAGEMENT PLAN 4.5 RECORD OF INSPECTIONS, AUDITS AND REVIEWS Date Q SQMR Detail of Review Action Taken Signed Q=Quality; QMR=Quality Management Representative; *Include a copy of the tour report following this page.
  • 9. SOUTH SUDAN OPERATIONS CENTRE 8 QUALITY MANAGEMENT PLAN 4.6 QMR – SITE INSPECTION REPORTING SHEET Manager: Richard Shoreder Date: Location: Greater Bahr el-Ghazal, South Sudan Project Eng.: IBRAHIM KAMAU Recommendations for Good Performance Item Good Practice Identified By Whom Issues Raised/Reviewed/Discussed Comments/Actions Priority Date to be Done By Responsibility Action By Closed Out Name Signature
  • 10. SOUTH SUDAN OPERATIONS CENTRE 9 QUALITY MANAGEMENT PLAN 5. QMP OBJECTIVES AND DESCRIPTION OF THE PROJECT 5.1 QMP OBJECTIVES This Project Quality Management Plan is specific to this project. The objective for this project is to carry out our work which will ensure that all conditions, activities and tasks, affecting Quality are planned, organized, executed, and controlled in accordance with the requirements of UNOPS statutory legislation and our clients European Union (EU). 5.2 DESCRIPTION OF THE PROJECT Some of the worst social indicators are found in South Sudan. At least 80 per cent of the population is income-poor. More than one third of the population is food insecure. The country’s economy is constrained by the sheer absence of roads and by the fact that any existing roads are of very poor quality. South Sudan’s fragmented transport infrastructure network has impeded agricultural producers in remote areas from effectively connecting to market centres. The South Sudan Development Plan (SSDP) sets out national priorities to achieve inclusive and sustainable development. A component of the SSDP’s Economic Development pillar is the achievement of rural transformation to improve livelihoods and expand employment opportunities. As identified in the SSDP, a key ingredient for rural transformation is the extension, upgrading and maintenance of feeder roads. Sustainable feeder roads can improve livelihoods, reduce poverty and improve security. In this regard and in full consultation with the Government the EU proposed to support the Greater Bahr el Ghazal (GBG) Zone in its effort to achieve agricultural development and the Zonal Effort for Agricultural Transformation: Bahr el Ghazal Effort for Agricultural Development (ZEAT-BEAD, or ZB) program was created. One of the components of this program is to build roads to increase marketing volumes and increase access to productive areas. In this connection, the EU and UNOPS have signed a contribution agreement for the implementation of the action entitled ZEAT BEAD “Feeder Road Construction in support of Trade and Market development in South Sudan” in line with the strategic objective of the EU’s programme and others complimentary existing and envisaged programmes and assessed needs of stakeholders. The key activities in this action also include Capacity Building within the State Ministries of Physical Infrastructure and local contractors; community engagement and labour intensive support activities. The action will focus on the construction and maintenance of approximately 120 km of feeder roads in Greater Bahr el Ghazal (Northern & Western Bahr el Ghazal, Warrap and Lakes State) States incorporating the implementation of a maintenance and capacity building program. The objective is to improve rural livelihoods by providing sustainable access to agricultural markets using appropriately engineered infrastructure approaches. As part of the implementation process UNOPS will undertake a feasibility study and a social and environmental impact assessment for the priority routes proposed by the respective States Ministry of Physical Infrastructure and Ministries of Agriculture. This process will allow for appropriate road section selection for construction along the
  • 11. SOUTH SUDAN OPERATIONS CENTRE 10 QUALITY MANAGEMENT PLAN priority routes that will fit with the planned project length of roads and be relevant to the ZEAT BEAD and/or SORUDEV feeder road programs by linking agricultural areas to markets. 6. ORGANISATION AND RESPONSIBILITIES 6.1 PROJECT SPECIFIC QUALITY MANAGEMENT ORGANIZATION CHART Organogram 1: UNOPS is responsible for managing Project’s Quality Infrastructure Project Manager Richard Schroeder SMQR Deputy PM Solomon Kuliche QMR Project Engineer(s) IBRAHIM KAMAU QR Contractor’s Representative [Insert Name] QR
  • 12. SOUTH SUDAN OPERATIONS CENTRE 11 QUALITY MANAGEMENT PLAN 6.2 QUALITY CONTROL RESPONSIBILITIES (UNOPS) Richard Schroeder Senior Quality Management Representative Solomon Kulicher Quality Management Representative IBRAHIM KAMAU Quality Representatives Area of Designated Responsibility Area of Designated Responsibility Area of Designated Responsibility  Reviewing and authorizing the project Quality Management Plan (QMP) and other project plans  Assigning quality responsibilities to all project personnel  Ensuring all project personnel are suitably trained, and possess the necessary skills, to undertake their designated quality responsibilities  Ensuring the provision of appropriate training in quality for all project personnel  Continually monitoring of quality performance to ensure compatibility and continued effectiveness with the UNOPS’s policy, objectives and other requirements  Allocating resources to ensure the project quality objectives are achieved  Participating in the review of the quality system and other relevant quality meetings and programs  Liaising with the Client on Quality issues.  Preparing Quality Management Plan  Ensuring procedures in the Quality Management Plan are followed  Ensuring the project QMP is correctly implemented to meet the requirements of the project  Allocating project staff to perform inspection duties Preparation of work Method Statements (MS), Work Procedures and Checklists (WIP and CL) and Inspection & Test Plans (ITP’s)  Reviewing prepared ITP’s, WIP’s and CL’s.  Reviewing inspection reports and ensuring any actions required are initiated  Implement, verify and review the project’s preventive and corrective action effectiveness  Ensuring and verifying that agreed rectification works and corrective action is taken when required for non- conforming work  Ensuring construction targets and programs are met  Attending meetings called to discuss quality issues  Identifying and reporting any quality management system issues  Auditing and assessment of contractor (report to SQMR).  Assisting in preparation of QMP  Preparing Work Inspection Procedures and Checklists (WIP and CL) and Inspection & Test Plans (ITP’s)  Performing verifications and quality inspections as requested  Monitoring the implementation of manufacture/construction activities  Identifying and reporting material and/or workmanship non-conformity and notifying the SQMR and QMR of the suspected non-conformity  Rejecting defective workmanship and materials  Assisting with the maintenance of the project program  Performing verifications and quality inspections as requested by the SQMR and QMR  Completing a diary on a project daily report  Technical and logistic support to the SQMR and QMR  Supervision of construction activities  Identifying and reporting material deficiency and issuing to contractor Defect Notification Report  And every activity listed under 8.3 which is not included above . Designated Signature: Designated Signature: Designated Signature:
  • 13. SOUTH SUDAN OPERATIONS CENTRE 12 QUALITY MANAGEMENT PLAN 6.3 QUALITY CONTROL RESPONSIBILITIES (UNOPS AND CONTRACTOR) Richard Schroeder Senior Quality Management Representative IBRAHIM KAMAU Quality Representatives [insert Contractor's PM name] Quality Management Representative [Insert Contractor's PEs Name] Quality Representatives [insert contact number] [insert contact number] [insert contact number] [insert contact number] Area of Designated Responsibility Area of Designated Responsibility Area of Designated Responsibility Area of Designated Responsibility  Reviewing and authorizing the project Quality Management Plan (QMP) and other project plans  Ensuring all project personnel are suitably trained, and possess the necessary skills, to undertake their designated quality responsibilities  Reviewing Contractor’s Quality Control reports, tests and inspection results  Participating in the review of the quality system and other relevant quality meetings and programs  Liaising with the Client on Quality issues.  Ensuring procedures in the Quality Management Plan are followed  Conducting independent inspection to verify quality of the works  Reviewing inspection reports and ensuring any actions required are initiated  Implement, verify and review the project’s preventive and corrective action effectiveness  Reviewing and verifying that agreed rectification works and corrective action is taken when required for non- conforming work  Ensuring construction targets and programs are met  Attending meetings called to discuss quality issues  Ensuring that all QMP issues have been identified and reported  Ensuring that required documentation is submitted  Auditing and assessment of contractor (report to SQMR).  Preparing Quality Management Plan  Assigning quality responsibilities to all project personnel  Ensuring procedures in the Quality Management Plan are followed  Ensuring the project QMP is correctly implemented to meet the requirements of the project  Ensuring the provision of appropriate training in quality for all project personnel  Continually monitoring of quality performance to ensure compatibility and continued effectiveness with the UNOPS’s policy, objectives and other requirements  Allocating resources to ensure the project quality objectives are achieved  Identifying and reporting any quality management system issues  Implement, verify and review the project’s preventive and corrective action effectiveness  Ensuring and verifying that agreed rectification works and corrective action is taken when required for non-conforming work.  Assisting in preparation of QMP  Preparing Work Inspection Procedures and Checklists (WIP and CL) and Inspection & Test Plans (ITP’s)  Performing verifications and quality inspections as requested  Monitoring the implementation of manufacture/construction activities  Identifying and reporting material and/or workmanship non-conformity and notifying QMR  Rejecting defective workmanship and materials  Assisting with the maintenance of the project program  Performing verifications and quality inspections as requested by QMR  Completing a diary on a project daily report  Technical and logistic support to QMR  Supervision of construction activities  Identifying and reporting any quality management system issues  And every activity listed under point 8.3 which is not included above. Designated Signature: Designated Signature: Designated Signature: Designated Signature:
  • 14. SOUTH SUDAN OPERATIONS CENTRE 13 QUALITY MANAGEMENT PLAN 6.4 SCHEDULE OF KEY ACTIVITIES No. Work Activity Inspection and Test Plan Work Procedure Date required Action by: Reviewed by: 01 Mobilization Complete/impartial Take inspection and record all items in question before commencement 02 Camp site layout As specs, Before set out obtain land approval from local authority. 02 Setting/Survey work Chain ages set, Survey team with survey equipment Request to survey( RTS) and approval to proceed issued by Client Engineer 03 Bush clearance Within specs ,stamps, roots are removed Obtain letter of commencement from PM and local authority 04 Trees cutting Tree falling within working area ,No and options of pruning branches only Letter from forestry and fishery 05 Embankment Layers, compaction, materials and moisture contents Request for testing ( RFT) form filled and signed 06 Sub base layers Compaction ,material and moisture contents 07 Gravel wearing course Borrow pit and compaction test/inspection Request for testing 08 Road Furniture’s Sign posts ,KM stone, Alienators’ ,safety installation 09 Drainage works De-silting ,invert level, position and size
  • 15. SOUTH SUDAN OPERATIONS CENTRE 14 QUALITY MANAGEMENT PLAN 7. COMMITMENT AND COMPETENCY 7.1 LEADERSHIP AND COMMITEMENT It is UNOPS’s intent that its managers and supervisors at all levels, by means of their actions and behaviour, provide visible and pro-active commitment to Quality Management. Demonstrated proactive and visible leadership and commitment to Quality on this Project shall include carrying out activities such as:  Setting clear quality objectives  Project Management conducting site visits  Senior management participating in audits  Involving the workforce in addressing quality issues  Encouraging open communication on quality issues  Encouraging an environment of continual improvement  Adhering to the Standards set by UNOPS Management System  The recognition and reward of outstanding contributions to quality performance 7.2 COMPETENCY AWARENESS & TRAINING The competency needs of all personnel performing activities which affect the quality of manufacture/construction shall be identified by UNOPS SQMR and QMR. Personnel performing specified assigned tasks shall be appropriately qualified on the basis of training, skills and/or experience, which will be confirmed by UNOPS and /or the Contractors Project Management team as required. The QMR shall be responsible for ensuring site personnel hold current and relevant qualifications for the work they are required to perform and maintain training records. Records of training and competencies (written confirmation by Contractors PM) will be kept and maintained in relevant project files. Training needs for project personnel shall be identified giving consideration to: the knowledge and skills required from the position to fulfil the realization of the requirements within UNOPS Management System.
  • 16. SOUTH SUDAN OPERATIONS CENTRE 15 QUALITY MANAGEMENT PLAN 8. CONTROL OF WORK PROCESSES Effective Quality Control requires a serious and concerted effort on the part of the supervisory and inspection personnel. Tools for the accomplishment of effective Quality Control are as follow:  Before start of construction, the UNOPS SQMR/QMR shall conduct a mutual understanding meeting with the contractor and discuss the contractor’s quality management system  Construction Works will commence only after mutual understanding between UNOPS and Contractor has been achieved. 8.1 CONTROL OF WORKS PLAN PHASING Control of Work Processes will comprise the following 3 phases:  Preparatory phase meetings: WP meeting will be held before each definable feature of work to ensure that the documentation is complete, materials are on hand, and the people who are to perform the work understand what they need to know about the feature of work. Both the actual contract specifications and those referenced in the contract specifications shall be in the contractor’s library and available to the control of WP inspections.  Initial Inspections: Control of WP inspections shall be conducted in a timely manner at the beginning of a definable feature of work. A check of the preliminary work will determine whether or not the Contractor, through his craftsmen involved, thoroughly understand and is capable of accomplishing the work as specified.  Follow-up Inspections: follow- up inspections also conducted by UNOPS and contractor’s quality management personnel, occur daily when work is in progress and are for the purpose of assuring that the controls established in the earlier phases of inspection continue to provide work which conforms to the contract requirements. 3 8.2 INSPECTION AND TESTING The status of the constructed works will be identified by the progressive completion of Inspection and testing documentation which are Inspection & Test Plans, Work Inspection Procedures and Checklists. UNOPS team and contractors shall be responsible for the quality of the works. Checklists will be signed for each operation (earth work, concrete work, metal work, roofing work, finishes work, landscape work, etc. including mechanical, electrical and hydraulic works) to verify that works have been completed in accordance with requirements. Independent inspections shall be carried out to verify that the self-certification process is being operated correctly. Requirements for independent inspections shall be identified on Inspection & 3 In all projects, there is work that is ‘cut and cover’, work that cannot be inspected “after the fact”. This includes concrete where the size, number and location of reinforcing steel cannot be readily determined after the concrete is placed. Most of the underground utilities cannot be inspected after covering. Work of this nature shall be closely controlled and monitored. A disadvantage with the system arises from the fact that Contractor’s personnel, are unlikely to readily take actions which will result in delay and expense to the contractor for the ask of quality. for example, if concrete is to be placed with a maximum slump of 6cm, it is unlikely that a load with 10cm or 12cm slump will be rejected. If roofing bituminous material is overheated, it is unlikely that it will be rejected. The deficiencies occasioned by these conditions may become latent defects revealed long after any possible contractor liability can be enforced.
  • 17. SOUTH SUDAN OPERATIONS CENTRE 16 QUALITY MANAGEMENT PLAN Test Plan, Check-lists. Independent inspections can be completed by appointed persons within the Project team. Non- conformances, defects or outstanding works shall be recorded as specific in UNOPS Procedures. Where an independent inspection is completed with all matters correct, this inspection can be recorded as “right first time” and used as a performance indicator. Inspections and Test Plans define the inspection and testing requirements of the project including:  Activity Description  Inspection or Item Description  Acceptance Criteria  Inspection Frequency  Inspection Test/Procedure  Hold Point Identification  Responsibility for carrying the inspection. UNOPS QMR will monitor the preparation of ITP’s4 :  Watch for omissions  Watch for discrepancies between plans and specifications  Check plans and specifications against requirements of which problems occurred on similar jobs  Compare elevations, grades and details shown on plans as exiting, with those at the actual site  Report all errors, omissions, discrepancies, and deficiencies to the SQMR. *Always keep a posted and marked up set of plans and specifications convenient for ready reference. *Make sure that construction contractor has this same information. 8.2.1 Storage of Materials UNOPS QR shall5 :  ensure/produce site organisation and management plan (location of material storage)  ensure that adequate space is available for the contractor’s operations and storage areas  ensure that approval has been obtained for temporary sheds, buildings, etc. which the contractor proposes to install  ensure that materials and equipment’s are properly stored and protected  ensure that safety requirements, especially in the storage of flammable or explosive materials, are adhered to  ensure temporary structures are secured against wind damage  ensure the necessary heating and ventilating systems are provided. 4 See: Point 6.2 Quality Control Responsibilities. 5 Appendix 7.
  • 18. SOUTH SUDAN OPERATIONS CENTRE 17 QUALITY MANAGEMENT PLAN 8.3 SUBMITTALS This section describes the procedures for submittals. 8.3.1 Shop Drawings The QR shall:  administer, control, and process submittals from the construction contractor(s)6  review all contractor submittals, and related supporting documents, to ensure compliance with project specifications and drawings  prepare submittal register for plans, and specifications  Check submittal register for inclusion of all shop drawings required including layouts of equipment, equipment rooms, etc.  ensure that all data is registered and submitted to the QMR  ensure that the submittal register is periodically updated  make continual checks of the submittal register to avoid untimely and omitted submittals so as to avoid delay of constructions  compare the shop drawings to the contract requirements and report apparent differences to the QMR and SQMR  ensure each detail on the shop drawings is clearly understood by the constructions contract requirements  ensure that the contractor makes note on his submittal of items which deviate from contract requirements  check materials being installed against the approved shop drawing (if the contractor installs unapproved material, inform him in writing that the material, if not subsequently approved, will be removed at his expense). *The submittals disposition will be noted on the submittal, which will be signed, dated and recorded. If required, the QR will return the submittal to the contractor for revision, incorporating the comments. The contractor shall resubmit it for review and verification for compliance. Submittals will be logged and copies will be retained in the project files. Results shall be recorded and available for review. [see conditions of contract] 8.3.2 Material Submittal Schedule The construction contractor will prepare and submit a submittal schedule to the QR, which will then be provided to UNOPS project manager, the schedule should be linked to the Contractor’s approved programme of works. The schedule will be initially submitted within [see conditions of contract] after the award of the contract and updated on a monthly basis. The QMR shall work with the contractor to prioritize and sequence submittals so that the most critical submittals are received and processed first (preparation of submittal schedule). The submittal schedule will become the baseline against which receipt of all required submittals will be compared. The approved submittal schedule will be forwarded to the UNOPS PM for resource availability planning. 7 6 See: 8.3.3 Process Review and Acceptance. 7 Appendix 1.
  • 19. SOUTH SUDAN OPERATIONS CENTRE 18 QUALITY MANAGEMENT PLAN 8.3.3 Process, Review and Acceptance Submittals will be managed as follows: [Fill this section according to contractor’s capacity and Project Construction Contract conditions; for further detailed information see example provided together with this template] 8.3.4 Storage The QMR will maintain all submittal files via a combination of a secure document filing and storage system. All submittal records will be provided to the UNOPS PM as part of the project closeout documentation. 8.4 CONSTRUCTION NONCONFORMITIES/DEFICIENCIES This section provides procedures for tracking construction nonconformities/deficiencies from identification through acceptable corrective action. It defines the controls and related responsibilities and authorities for dealing with noncompliant products or services. 8.4.1 Non-conformance/Deficiency Identification and Notification Non-conformance/deficiency occurs when a material, performed work, or installation does not meet the plans and/or specifications for the project. Any item of work found to be deficient will be identified by the inspector on the Non-conformance Report as described in this section. 8.4.2 Non-conformance and Non-conformance Report (NCR)8 Non-conformances are major deviations from the project specifications and the contract requirement and/or accepted standard of quality, which shall be formally documented for corrective action by UNOPS project staff or the third party testing group. Failure by a contractor to correct a minor deficiency after having been put on notice will also result in a non-conformance if it is not corrected within time frame stated in the Condition of Contract. Non-conformances shall be formally documented on the example Non Conformance Report form. The Non-conformance report shall be distributed to the contractor and UNOPS SQMR and QMR. The Non-Conformance Report (NCR) is a formal notification to the contractor that work does not meet the plans or the specifications for the project. Any item of work found to be deficient- out of conformance with the construction drawings and/or specifications - will be identified by the inspector on the non-conformance report as described in this section. Non-conformance reports will be included on the non-conformance register9 and tracked through verification that the non- conformance has been corrected. 8.4.3 Preventive Actions Preventive actions are to be taken to eliminate the cause of a potential non-conformity. For example, defects that appear on the surface of concrete during construction or within a relatively short time after completion are usually caused by poor quality materials, improper mix design, lack 8 Appendix 2 9 Appendix3
  • 20. SOUTH SUDAN OPERATIONS CENTRE 19 QUALITY MANAGEMENT PLAN of proper placing and curing procedures, or poor workmanship. UNOPS shall take preventive actions as necessary to eliminate the causes of potential deficiencies so as to prevent their occurrence. 8.5 DOCUMENTATION CONTROL Quality Documentation developed specifically for the project shall be controlled on site by the QR. 8.5.1 Drawings records  The contractor’s record drawings shall be reviewed monthly by UNOPS  Project and design office staff to ensure that they are correct  Ensure that as soon as a change or addition is made in construction it is noted on the record drawing  See that the following items are considered in the changes for Record  Drawings: · [Insert List of Drawings Specific for the Project]  Draft final record drawings will be prepared and submitted by Contractor to UNOPS SQMR for review in order to prepare final drawings record (As built) based on UNOPS PM Comments. [See: Conditions of Contract for Works] 8.5.2 Final Reporting The following quality related documents will be generated during implementation of the Project and will be submitted to the Quality Control file that will be handed over to the end user on project completion. Work Completion Report:  Record (as-built) drawings  Operation and maintenance manuals; and Results of the Start-up and Testing Plan and the Commissioning Plan implemented for each major piece of equipment or system before system turnover, in accordance with Technical Specification Contractor Quality Program Requirements. 8.5.3 Defect Notification Period Defect Notification Period means the period for notifying defects in the Works (as the case may be) under the clause 1)"Defects Notification Period and Final Completion", as stated in the “Minor Works Contract”; 2-3)“Defect Liability”, as stated in the “Measured Price Construction Contract” and “Lump Sum Construction Contract”, which is calculated from the date on which the Works is completed as certified under the clause 1) "Substantial Completion and Taking Over", within “Minor Works Contract”; 2-3)”Employer’s Taking Over” within “Measured Price Construction Contract” and “Lump Sum Construction Contract”. When material, performed work or installation is found to be deficient, the QR will assure deficiency correction is implemented. The QR shall ensure that the defected material, work or installation is identified and controlled to prevent unintended use or delivery.
  • 21. SOUTH SUDAN OPERATIONS CENTRE 20 QUALITY MANAGEMENT PLAN UNOPS will instruct contractor to implement corrective actions to remedy work that is not in accordance with the drawings and specifications. The corrective actions will include removal and replacement of deficient work using methods approved by the UNOPS Project Manager. Removal shall be done in a manner that does not disturb operation of the product; otherwise, the disturbed material shall also be removed and replaced. Replacement shall be done in accordance with the corresponding technical specifications. Replacement will be subjected to the same scope of Quality Control inspection and testing as the original work. If the replacement work is not in accordance with the drawings and specifications, the replacement work will be removed, replaced, re inspected, and re-tested. All activities undertaken with regards to defects shall be recorded in Defects Register.10 Any item of work found to be deficient will be identified by the PE and issued by Contractor on the Defect Notification 11 as described in this section. FINALLY It is essential that work is carried out in line with the contract requirements and the UNOPS systems. Therefore please follow instructions and if work appears to be carried out incorrectly, please inform your supervisor before you go too far and it is covered up. If in doubt please ask! 10 Appendix 4. 11 Appendix 5.
  • 22. SOUTH SUDAN OPERATIONS CENTRE 21 QUALITY MANAGEMENT PLAN 9. APPENDIXES 9.1 APPENDIX 1 - MATERIAL APPROVAL REQUEST Project: EU-ZEAT BEAD Feeder Roads, Greater Bahr el- Ghazal ,RSS Request No: Contractor: Date: Item Submitted: Discipline : Civil Building Mechanical Electrical Description: Supplier/Manufacture, including model number: BOQ Ref.: Specification Ref.: Attachments: Data Sheet Catalogue Sample For Contractor Discipline Engineer Name: Signature: Project Manager Name: Signature: For UNOPS Received Date: Received Time: Received By: Signature: UNOPS Action: Approved Not Approved Approved As Noted Others: ................................................... Remarks: ........................................................................................................................................................ Action by: Signature: Date: For UNOPS Project Manager Use: ........................................................................................................................................................................ Project Manager Name: Signature: Date: Contractor Receive Received Date: Received Time: Received By: Signature:
  • 23. SOUTH SUDAN OPERATIONS CENTRE 22 QUALITY MANAGEMENT PLAN 9.2 APPENDIX 2 - NON-CONFORMANCE REPORT Project EU –ZEAT- BEAD- Feeder Roads, Greater Bahr el-Ghazal South Sudan. Contract No Contractor Trade/Activity Date Non-conformance report number Details Of Non Conformance: (Note specifications, drawings, standards, procedures etc departed from, attach photos if applicable) Type of Non Conformance: Material Fault Workmanship Product Supply Safety Quality Environmental Remedial Works Required: To be completed By Date: ………………… Input and Approval required by Design Consultants: Yes No Approved: ................... Corrective Action to Prevent Recurrence: Corrective Action confirmed and carried out Date: ………………..... By Contractor: ……................
  • 24. SOUTH SUDAN OPERATIONS CENTRE 23 QUALITY MANAGEMENT PLAN Close Out Confirmed Date…………………………………….............. By UNOPS: …….....................
  • 25. SOUTH SUDAN OPERATIONS CENTRE 24 QUALITY MANAGEMENT PLAN 9.3 APPENDIX 3 - NON-CONFORMANCE REGISTER Project Title: EU –ZEAT –BEAD-Feeder Roads, Lakes state South Sudan. Non Conformance Number Date Issued Non Conformance Details Date Remedial Work Complete Date Corrective Action Complete Non Conformance Closed Out
  • 26. SOUTH SUDAN OPERATIONS CENTRE 25 QUALITY MANAGEMENT PLAN 9.4 APPENDIX 4 - DEFECTS REGISTER Project: EU- ZEAD -BEAD Feeder Roads, Lakes State Contract No Contractor Defect No. Defect Details Date Issued to Contractor Remedial Actions To be completed by Date Work Started Date Work Completed Sign Off (Inspected and approved repairs) Comments (Design required, extend periods, guarantees, maintenance)
  • 27. SOUTH SUDAN OPERATIONS CENTRE 26 QUALITY MANAGEMENT PLAN 9.5 APPENDIX 5 - DEFECT NOTIFICATION Project EU-ZEAT-BEAD Feeder Roads, Lakes state South Sudan. Contract No Contractor Trade/Activity Date Defect notification number Details of Defect: (Note specifications, drawings, standards, procedures etc departed from, attach photos if applicable) Type of Defect: Material Fault Civil Mechanical Electrical Safety & Environmental Other Defect Classification: Critical (creates direct risk to proper operation of the facility or safety – to be fixed ASAP) Operational (no direct risk to operation of facility or safety – fix date to be agreed) Remedial Works Required: To be completed By Date: ………………… Input and Approval required by Design Consultants: Yes No Signed by Contractor: …………………………………….............. Date: ……..................... Signed by UNOPS: …………………………………….............. Date: …….....................
  • 28. SOUTH SUDAN OPERATIONS CENTRE 27 QUALITY MANAGEMENT PLAN 9.6 APPENDIX 6 - MATERIAL STORAGE CHECKLIST Purpose: Material Storage Location: [Insert Location] No. Inspection Task Hold Responsibility Date Signature 1 Check if adequate space is available for the contractor’s operations and storage areas 2 Check if approval has been obtained for temporary sheds, buildings, etc. which the contractor proposes to install 3 Check if materials and equipment’s are properly stored and protected 4 Check if safety requirements, especially in the storage of flammable or explosive materials, are adhered to 5 Check if temporary structures are secured against wind damage 6 Check if necessary heating and ventilating systems are provided 7 Check on un bended nails ,debris etc 8 Check on Stacking and spacing of materials 9 Air circulation and the area below the stacked items( materials) Final Inspection by: Date: QMR Signature:
  • 29. SOUTH SUDAN OPERATIONS CENTRE 28 QUALITY MANAGEMENT PLAN 9.7 APPENDIX 7 – QUALITY POLICY
  • 30. SOUTH SUDAN OPERATIONS CENTRE 29 QUALITY MANAGEMENT PLAN
  • 31. SOUTH SUDAN OPERATIONS CENTRE 30 QUALITY MANAGEMENT PLAN