Electric Load Estimating
2011 SWEDE Conference
Customer’s Connected Load &
Electric Utility’s Demand Load
• Customers provide the utility company with connected load based on
the National Electric Code requirements.
• This means everything is turned on and running at instantaneous
peak loading. The code may even require them to add safety factors
that increase the load over 100%.
• The electric utility company will determine the diversified demand load
based on the customer’s total connected load information. The utility
company does not have to use the NEC requirements for sizing its
facilities.
• The customer, electrician and engineer will try to get you to match
their connected load for sizing transformers and services, but don’t let
them. Demand load will typically range from 25% to 75% of their
total connected load.
3
Electric Load Estimating
One of the most important responsibilities of the
Utility Project Manager is to accurately prepare a
commercial or industrial load estimate for service
to the customer. This load estimate influences the
design & installation cost of the electric utility
facilities. It becomes a factor in determining the
cost to the customer for electric service.
4
Demand Meters
• For all commercial and industrial customers the demand
is metered to be the highest average demand in any 15
minute period during each billing cycle month.
• Average is the key word here. It is not the maximum KW
during the 15 minute period!
• The meters reset the demand to zero every 15 minutes,
keeping only the highest.
5
Demand Factor
• How does the load data from the customer get estimated into metered
demand? This is done by using a term called demand factor.
• Demand factor is the ratio of the peak demand kW of a system or load
to the total connected kW of a system or load. It can be written as
follows:
• Demand Factor [D.F.] = peak demand kW [metered]
total connected kW
• If you are calculating the peak metered demand, the equation may be
rewritten as follows:
• Peak demand kW [metered] = total connected kW X D.F.
6
OBTAINING LOAD INFORMATION
• To calculate the peak meter demand of a load you must
know the total connected kW and the demand factor.
• It is the responsibility of the customer to provide you with
proper connected electrical load data, not the main
disconnect size, panel size, or service amps.
• The customer should provide connected kW information
for each piece of equipment as well as phase and voltage.
• This information can be obtained by having the customer
complete your Customer Load Requirements Form or by
obtaining a copy of the electrical and mechanical plans of
the project.
7
Motor Loads
• Motor horsepower [hp] - For motor loads, hp is the
common way for the customer to indicate connected load.
For large motors requiring a motor start calculation
you also need to secure the starting code of the
motor. To convert this information into the desired kW,
the following equation is used.
• connected kW = connected hp X .75
• This is derived from the fact that there are 746 watts/hp.
So, there is .746kW/hp and it is simply rounded off to .75
• Since this is just for estimating purposes, motor efficiency
is not taken into consideration.
Motor Load Example
• The typical Demand Factor for an elevator motor is 20%.
• This is because the elevator is often starting, stopping and
idle during a 15 minute period.
• A 30 hp motor would only have a 4.5 kW demand.
• 30 hp x .75 (kW/hp) x .20 (D.F.) = 4.5 kW
9
Air Conditioning Load
• Air conditioning - to properly determine air conditioning connected kW
the Energy Efficiency Rating [EER] of the air conditioning unit and the
rated tonnage of the unit must be known.
• Equation connected kW = tons X 12
EER
• This equation is derived from the fact that:
EER is in units of BTUH/watt
kW = watts
1000
1 ton=12,000 BTUH
• This equation calculates connected load. Then, a demand factor is
utilized to reduce it to the demand load.
10
Demand and Diversity Factors
• Once you have secured proper load information from the
customer you can determine the connected kW for each
load.
• After the connected kW is determined, the peak metered
demand may be calculated if the demand factor is known.
• To determine the appropriate demand factor for a
connected load the Demand Interval Factor and the
Diversity Factor need to be determined.
11
Demand Interval Factor
The demand interval factor is the percentage of operational
run time of the load during a 15 minute demand interval.
For example a motor cycles 10 minutes on and 5 minutes
off during a 15 minute demand interval. Therefore the
demand interval factor would be:
Demand Interval Factor = 10 minute run time / 15 minutes = .67
12
Diversity Factor
• The diversity factor is defined as the probability that a load
will be operating during the period when the demand meter
records the high peak demand.
• Typically we use a diversity factor of 100% if the load is
expected to operate during the peak period and 0% if the
load is expected to operate only outside the peak period
(Off-Peak Load).
• For two or more loads of the same type, the diversity factor
will reflect the probability that these same types of loads will
all operate during the peak period. The range of diversity
factors for these same type of loads could be anywhere from
0% to 100%.
• For example the probability that all the receptacle outlets in
a building will all be used during the peak period is fairly low
and is typically given a diversity factor of 10%.
13
Example 1:
• Tom's Machine Shop is a building that has 5 kW of fluorescent
fixtures, 15 receptacle outlets at 1500w each, 1-10 hp lathe, 1-20 hp
air compressor and 1-15 hp fire pump.
• After questioning the customer about the various loads, the
information is further deciphered as follows:
• The shop lights are on only during the hours of 8 a.m. to 5 p.m.
• The receptacle outlets are in the office only, and will have computers
and other small loads plugged into them.
• The lathe is fully loaded for 5 minutes periods. The rest of the time is
setup time. This procedure repeats every 15 minutes.
• The air compressor supplies air to air tools and cycles off and on
about half the time.
• The fire pump only runs for 30 minutes when tested which is once a
month after hours.
14
Example 1 – Summary
• Lighting Demand Factor = Demand Interval Factor x Diversity Factor
= (15 minute run time/ 15 minutes) x 1.0
= 1.0
Lighting Demand Load = 5 kW x 1.0 = 5 kW
• Receptacle Outlet Demand Factor = Demand Interval Factor x Diversity Factor
= (15 minute run time / 15 minutes) x 0.1
= 0.1
Receptacle Outlet Demand Load = 15 x 1500 watts x 0.1 = 2.25 kW
• Lathe Demand Factor = Demand Interval Factor x Diversity Factor
= (5 minute run time / 15 minutes) x 1.0
= .33
Lathe Demand Load = 10 hp x .746 x .33 = 2.46 kW
• Air Compressor Demand Factor = Demand Interval Factor x Diversity Factor
= (7.5 minute run time / 15 minutes) x 1.0
= .5
Air Compressor Demand Load = 20 hp x .746 x .5 = 7.46 kW
• Fire Pump Demand Factor = Demand Interval Factor x Diversity Factor
= (15 minute run time/ 15 minutes) x 0.0
= 0.0
Fire Pump Demand Load = 15 hp x .746 x 0.0 = 0.0 kW
15
Example 1 – Chart
Summary of Demand Loads
Equipment HP kW D.F. Demand KW
Lighting 5.0 1.0 5.0
Receptacle Outlets 22.5 0.10 2.25
Lathe 10 7.5 0.33 2.46
Air Compressor 20 15.0 0.50 7.46
Fire Pump 15 11.25 0.0 0.0 .
TOTAL 61.25 kW 17.17 kW
Connected KW Vs Demand KW
Customer's Connected KW Vs Actual Demand KW
Project Name
Customer
Connected KW
Actual Metered
Demand KW Demand Factor
Sam's Club 1,477 773 52
HEB Grocery 2,135 1,060 50
HEB Gas & Car Wash Site 116 27 23
IKEA Store 3,409 1259 37
Stone Oak Elementary School 1,557 554 36
Holiday Inn 539 118 22
Sundance Office Building 1952 1115 57
Texas A&M Health Science Bldg 2272 930 41
Typical Demand Factors
• The following factors can be used as a guideline to check the calculated demand factor.
Good judgment must be used. Do not use this information as correct in all situations
because it is not. The demand factor and diversity factor determination must be answered to
ensure correct demand factor assignment.
• Air Conditioning 1 unit 100%
• several small units 85-95%
• bldg. core cooling in winter 40-60%
• Chiller systems (A/C) entire 65%
• Heating 1 unit 80%
• several small units 50-80%
• aux. heat for heat pumps 40%
• Interior lighting under 100 fixtures 100%
• over 100 fixtures 95%
• w/large storage & conference areas, etc. 90%
• External lighting (off day, on evening)
• summer 0%
• winter, closed at night 0%
• winter, open at night 100%
• Sign lighting sign on during day 100%
• summer 0%
• winter, closed at night 0%
• winter, open at night 100%
• Water heating 50-60%
• Water circulation pumps 90%
• Process equipment continuous 70-80%
• non-continuous 40-50%
• Air Compressor 40-60%
• Computers main frame 90-100%
• Welders 5-10%
• CAT or X-RAY 0-5%
• Laundry & Dry Cleaning Equipment commercial 50-60%
• Refrigeration 60%
• Miscellaneous Motors gas pump 10-20%
• pneumatic tubes 10%
• elevators 20%
• Commercial cooking fast foods 60-70%
• other applications 40%
18
Watts Per Square Foot
• Sometimes a situation exists in which obtaining accurate
load data is not possible.
• An example of this situation is a strip shopping center
where the developer does not know what type of tenants
will lease the spaces.
• Table 1 lists the watts/sq. ft. estimates for situations
where the load is not available such as speculative lease
spaces.
• This table can also be used as a comparison tool to
validate your calculated demand load.
Watts Per Square Foot
• TABLE 1 (This Information is 20 Years Old!)
• LOAD INFORMATION – WATTS per SQ. FT. ESTIMATES
• These may be used when actual load data is not available.
• Watts Per Square Foot
• Air Conditioning comfort cooling4 watts/sq ft.
• computer rooms 5 watts/sq. ft.
• Heating 6 watts/sq. ft.
• Office Lighting 3 watts/sq. ft.
• Warehouse Lighting 1 watt/sq. ft.
• Office miscellaneous 1 watt/sq. ft.
• Warehouse miscellaneous 1/2 watt/sq. ft.
• Air Conditioning – By Tons
• A/C (at 8.0 SEER) 1.5 kW/ton
• Chiller units (including auxiliary equip.)
1.0 kW/ton
• Fluorescent Lighting
• 2' x 4' lay-in 2 lamp (4') 100 watts/fixture
• 2' x 4' lay-in 4 lamp (4') 200 watts/fixture
• 2' x 8' lay-in 2 lamp (8') 200 watts/fixture
• Other Guidelines
• 1 phase or 3 phase motor 750 watts/ horsepower
• Swimming pool pumps (inefficient) 1.2 kW/horsepower
• Refrigeration compressors 1.4 kW/ton
20
Watts Per Square Foot Example
Typical Office Building
TABLE 1
LOAD INFORMATION – WATTS per SQ. FT. ESTIMATES
These may be used when actual load data is not available.
Watts Per Square Foot
Air Conditioning
comfort cooling 4 watts/sq ft.
computer rooms 5 watts/sq. ft.
[summer & winter]
Heating 6 watts/sq. ft.
Office Lighting 3 watts/sq. ft.
Warehouse Lighting 1 watt/sq. ft.
Office miscellaneous 1 watt/sq. ft.
Warehouse miscellaneous 1/2 watt/sq. ft.
TOTAL= 8 watts/sq. ft.
Do You Know Jack?
• Another way to check your Demand KW estimate is by
comparing it to an existing facility on your distribution
system.
• You are probably not serving the first “Jack in the Box”
restaurant on your electric distribution system.
• If you are serving a customer that has other existing
facilities located on the distribution system – check your
meter information system for the Demand KW of the
existing locations.

More Related Content

PDF
Power factor improvement
PDF
BIBLIA HEBREA-TANAJ.pdf
PPTX
Cpu scheduling in operating System.
PPTX
Scaffolding, underepinning and shoring
PPTX
Electrical wiring system
PPT
Basic of electrical
PPT
Power plant, Power Station and types of power plant
Power factor improvement
BIBLIA HEBREA-TANAJ.pdf
Cpu scheduling in operating System.
Scaffolding, underepinning and shoring
Electrical wiring system
Basic of electrical
Power plant, Power Station and types of power plant

What's hot (20)

PPTX
Calculation of electrical load of building
PDF
Distribution System
PPS
Electrical wiring domestic and industries
PPTX
Design of substation
PDF
Preliminary electrical load calculation course share
PPTX
1.substation layouts
PPTX
Electrical distribution system
PPTX
electrical lighting calculation
PPTX
Electric substation
PPTX
**Lightning Arrester Presentation**
PPTX
Load factor and demand factor
PPTX
Generator and Transformer Protection (PART 1)
PPTX
Power factor
PDF
Electrical bus bar and its types
PPT
Distribution boards and Protection devices ppt
DOCX
power transformer and its usage
PPTX
Earthing
PPTX
Electrical installation for commercial & public building
PPTX
Substations
Calculation of electrical load of building
Distribution System
Electrical wiring domestic and industries
Design of substation
Preliminary electrical load calculation course share
1.substation layouts
Electrical distribution system
electrical lighting calculation
Electric substation
**Lightning Arrester Presentation**
Load factor and demand factor
Generator and Transformer Protection (PART 1)
Power factor
Electrical bus bar and its types
Distribution boards and Protection devices ppt
power transformer and its usage
Earthing
Electrical installation for commercial & public building
Substations
Ad

Similar to Commercial load estimation for electrical (20)

PDF
Power station
PPTX
Economics of Power Generation
PPTX
Power_plant_ecomices.pptx
PDF
Copy of PSOC-unit1.pdf
PPTX
Shreelakshmi(power).pptx
PPTX
Lecture 8 load duration curves
PPTX
Lecture 7 load duration curves
PDF
Energy, economic and environmental issues of power plants
PPTX
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
PPTX
Bangladesh Power Stations & Power Plants Overview
PPTX
LOad curve of Bangladesh Powerplant.pptx
PPTX
chaptersnnsbs djhebehe sjjsjsjs jwhshs 7.pptx
PPT
ECNG 3013 A
PPT
SodaPDF-converted-Copy of PSOC-unit1.ppt
PPTX
Electrical Plan Electrical System Electrical Design
PDF
electric motor
DOCX
Economic Aspects.docx
PDF
elmeasure-textile-energy-and-process-management-catalog.pdf
PDF
Fact sheet u.s. efficiency
PPSX
Consumer Basics for Renewable Energy
Power station
Economics of Power Generation
Power_plant_ecomices.pptx
Copy of PSOC-unit1.pdf
Shreelakshmi(power).pptx
Lecture 8 load duration curves
Lecture 7 load duration curves
Energy, economic and environmental issues of power plants
Lecture-on-DISTRIBUTION-SYSTEM-edited.pptx
Bangladesh Power Stations & Power Plants Overview
LOad curve of Bangladesh Powerplant.pptx
chaptersnnsbs djhebehe sjjsjsjs jwhshs 7.pptx
ECNG 3013 A
SodaPDF-converted-Copy of PSOC-unit1.ppt
Electrical Plan Electrical System Electrical Design
electric motor
Economic Aspects.docx
elmeasure-textile-energy-and-process-management-catalog.pdf
Fact sheet u.s. efficiency
Consumer Basics for Renewable Energy
Ad

Recently uploaded (20)

PPTX
Onica Farming 24rsclub profitable farm business
PDF
PSYCHOLOGY IN EDUCATION.pdf ( nice pdf ...)
PPTX
Nursing Management of Patients with Disorders of Ear, Nose, and Throat (ENT) ...
PDF
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
PDF
Piense y hagase Rico - Napoleon Hill Ccesa007.pdf
PPTX
Introduction and Scope of Bichemistry.pptx
PPTX
Week 4 Term 3 Study Techniques revisited.pptx
PDF
Mark Klimek Lecture Notes_240423 revision books _173037.pdf
PDF
From loneliness to social connection charting
PDF
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
PPTX
Revamp in MTO Odoo 18 Inventory - Odoo Slides
PDF
Abdominal Access Techniques with Prof. Dr. R K Mishra
PPTX
Renaissance Architecture: A Journey from Faith to Humanism
PDF
Anesthesia in Laparoscopic Surgery in India
PDF
O5-L3 Freight Transport Ops (International) V1.pdf
PDF
Origin of periodic table-Mendeleev’s Periodic-Modern Periodic table
PPTX
Cardiovascular Pharmacology for pharmacy students.pptx
PDF
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
PPTX
UNDER FIVE CLINICS OR WELL BABY CLINICS.pptx
PDF
Pre independence Education in Inndia.pdf
Onica Farming 24rsclub profitable farm business
PSYCHOLOGY IN EDUCATION.pdf ( nice pdf ...)
Nursing Management of Patients with Disorders of Ear, Nose, and Throat (ENT) ...
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
Piense y hagase Rico - Napoleon Hill Ccesa007.pdf
Introduction and Scope of Bichemistry.pptx
Week 4 Term 3 Study Techniques revisited.pptx
Mark Klimek Lecture Notes_240423 revision books _173037.pdf
From loneliness to social connection charting
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
Revamp in MTO Odoo 18 Inventory - Odoo Slides
Abdominal Access Techniques with Prof. Dr. R K Mishra
Renaissance Architecture: A Journey from Faith to Humanism
Anesthesia in Laparoscopic Surgery in India
O5-L3 Freight Transport Ops (International) V1.pdf
Origin of periodic table-Mendeleev’s Periodic-Modern Periodic table
Cardiovascular Pharmacology for pharmacy students.pptx
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
UNDER FIVE CLINICS OR WELL BABY CLINICS.pptx
Pre independence Education in Inndia.pdf

Commercial load estimation for electrical

  • 1. Electric Load Estimating 2011 SWEDE Conference
  • 2. Customer’s Connected Load & Electric Utility’s Demand Load • Customers provide the utility company with connected load based on the National Electric Code requirements. • This means everything is turned on and running at instantaneous peak loading. The code may even require them to add safety factors that increase the load over 100%. • The electric utility company will determine the diversified demand load based on the customer’s total connected load information. The utility company does not have to use the NEC requirements for sizing its facilities. • The customer, electrician and engineer will try to get you to match their connected load for sizing transformers and services, but don’t let them. Demand load will typically range from 25% to 75% of their total connected load.
  • 3. 3 Electric Load Estimating One of the most important responsibilities of the Utility Project Manager is to accurately prepare a commercial or industrial load estimate for service to the customer. This load estimate influences the design & installation cost of the electric utility facilities. It becomes a factor in determining the cost to the customer for electric service.
  • 4. 4 Demand Meters • For all commercial and industrial customers the demand is metered to be the highest average demand in any 15 minute period during each billing cycle month. • Average is the key word here. It is not the maximum KW during the 15 minute period! • The meters reset the demand to zero every 15 minutes, keeping only the highest.
  • 5. 5 Demand Factor • How does the load data from the customer get estimated into metered demand? This is done by using a term called demand factor. • Demand factor is the ratio of the peak demand kW of a system or load to the total connected kW of a system or load. It can be written as follows: • Demand Factor [D.F.] = peak demand kW [metered] total connected kW • If you are calculating the peak metered demand, the equation may be rewritten as follows: • Peak demand kW [metered] = total connected kW X D.F.
  • 6. 6 OBTAINING LOAD INFORMATION • To calculate the peak meter demand of a load you must know the total connected kW and the demand factor. • It is the responsibility of the customer to provide you with proper connected electrical load data, not the main disconnect size, panel size, or service amps. • The customer should provide connected kW information for each piece of equipment as well as phase and voltage. • This information can be obtained by having the customer complete your Customer Load Requirements Form or by obtaining a copy of the electrical and mechanical plans of the project.
  • 7. 7 Motor Loads • Motor horsepower [hp] - For motor loads, hp is the common way for the customer to indicate connected load. For large motors requiring a motor start calculation you also need to secure the starting code of the motor. To convert this information into the desired kW, the following equation is used. • connected kW = connected hp X .75 • This is derived from the fact that there are 746 watts/hp. So, there is .746kW/hp and it is simply rounded off to .75 • Since this is just for estimating purposes, motor efficiency is not taken into consideration.
  • 8. Motor Load Example • The typical Demand Factor for an elevator motor is 20%. • This is because the elevator is often starting, stopping and idle during a 15 minute period. • A 30 hp motor would only have a 4.5 kW demand. • 30 hp x .75 (kW/hp) x .20 (D.F.) = 4.5 kW
  • 9. 9 Air Conditioning Load • Air conditioning - to properly determine air conditioning connected kW the Energy Efficiency Rating [EER] of the air conditioning unit and the rated tonnage of the unit must be known. • Equation connected kW = tons X 12 EER • This equation is derived from the fact that: EER is in units of BTUH/watt kW = watts 1000 1 ton=12,000 BTUH • This equation calculates connected load. Then, a demand factor is utilized to reduce it to the demand load.
  • 10. 10 Demand and Diversity Factors • Once you have secured proper load information from the customer you can determine the connected kW for each load. • After the connected kW is determined, the peak metered demand may be calculated if the demand factor is known. • To determine the appropriate demand factor for a connected load the Demand Interval Factor and the Diversity Factor need to be determined.
  • 11. 11 Demand Interval Factor The demand interval factor is the percentage of operational run time of the load during a 15 minute demand interval. For example a motor cycles 10 minutes on and 5 minutes off during a 15 minute demand interval. Therefore the demand interval factor would be: Demand Interval Factor = 10 minute run time / 15 minutes = .67
  • 12. 12 Diversity Factor • The diversity factor is defined as the probability that a load will be operating during the period when the demand meter records the high peak demand. • Typically we use a diversity factor of 100% if the load is expected to operate during the peak period and 0% if the load is expected to operate only outside the peak period (Off-Peak Load). • For two or more loads of the same type, the diversity factor will reflect the probability that these same types of loads will all operate during the peak period. The range of diversity factors for these same type of loads could be anywhere from 0% to 100%. • For example the probability that all the receptacle outlets in a building will all be used during the peak period is fairly low and is typically given a diversity factor of 10%.
  • 13. 13 Example 1: • Tom's Machine Shop is a building that has 5 kW of fluorescent fixtures, 15 receptacle outlets at 1500w each, 1-10 hp lathe, 1-20 hp air compressor and 1-15 hp fire pump. • After questioning the customer about the various loads, the information is further deciphered as follows: • The shop lights are on only during the hours of 8 a.m. to 5 p.m. • The receptacle outlets are in the office only, and will have computers and other small loads plugged into them. • The lathe is fully loaded for 5 minutes periods. The rest of the time is setup time. This procedure repeats every 15 minutes. • The air compressor supplies air to air tools and cycles off and on about half the time. • The fire pump only runs for 30 minutes when tested which is once a month after hours.
  • 14. 14 Example 1 – Summary • Lighting Demand Factor = Demand Interval Factor x Diversity Factor = (15 minute run time/ 15 minutes) x 1.0 = 1.0 Lighting Demand Load = 5 kW x 1.0 = 5 kW • Receptacle Outlet Demand Factor = Demand Interval Factor x Diversity Factor = (15 minute run time / 15 minutes) x 0.1 = 0.1 Receptacle Outlet Demand Load = 15 x 1500 watts x 0.1 = 2.25 kW • Lathe Demand Factor = Demand Interval Factor x Diversity Factor = (5 minute run time / 15 minutes) x 1.0 = .33 Lathe Demand Load = 10 hp x .746 x .33 = 2.46 kW • Air Compressor Demand Factor = Demand Interval Factor x Diversity Factor = (7.5 minute run time / 15 minutes) x 1.0 = .5 Air Compressor Demand Load = 20 hp x .746 x .5 = 7.46 kW • Fire Pump Demand Factor = Demand Interval Factor x Diversity Factor = (15 minute run time/ 15 minutes) x 0.0 = 0.0 Fire Pump Demand Load = 15 hp x .746 x 0.0 = 0.0 kW
  • 15. 15 Example 1 – Chart Summary of Demand Loads Equipment HP kW D.F. Demand KW Lighting 5.0 1.0 5.0 Receptacle Outlets 22.5 0.10 2.25 Lathe 10 7.5 0.33 2.46 Air Compressor 20 15.0 0.50 7.46 Fire Pump 15 11.25 0.0 0.0 . TOTAL 61.25 kW 17.17 kW
  • 16. Connected KW Vs Demand KW Customer's Connected KW Vs Actual Demand KW Project Name Customer Connected KW Actual Metered Demand KW Demand Factor Sam's Club 1,477 773 52 HEB Grocery 2,135 1,060 50 HEB Gas & Car Wash Site 116 27 23 IKEA Store 3,409 1259 37 Stone Oak Elementary School 1,557 554 36 Holiday Inn 539 118 22 Sundance Office Building 1952 1115 57 Texas A&M Health Science Bldg 2272 930 41
  • 17. Typical Demand Factors • The following factors can be used as a guideline to check the calculated demand factor. Good judgment must be used. Do not use this information as correct in all situations because it is not. The demand factor and diversity factor determination must be answered to ensure correct demand factor assignment. • Air Conditioning 1 unit 100% • several small units 85-95% • bldg. core cooling in winter 40-60% • Chiller systems (A/C) entire 65% • Heating 1 unit 80% • several small units 50-80% • aux. heat for heat pumps 40% • Interior lighting under 100 fixtures 100% • over 100 fixtures 95% • w/large storage & conference areas, etc. 90% • External lighting (off day, on evening) • summer 0% • winter, closed at night 0% • winter, open at night 100% • Sign lighting sign on during day 100% • summer 0% • winter, closed at night 0% • winter, open at night 100% • Water heating 50-60% • Water circulation pumps 90% • Process equipment continuous 70-80% • non-continuous 40-50% • Air Compressor 40-60% • Computers main frame 90-100% • Welders 5-10% • CAT or X-RAY 0-5% • Laundry & Dry Cleaning Equipment commercial 50-60% • Refrigeration 60% • Miscellaneous Motors gas pump 10-20% • pneumatic tubes 10% • elevators 20% • Commercial cooking fast foods 60-70% • other applications 40%
  • 18. 18 Watts Per Square Foot • Sometimes a situation exists in which obtaining accurate load data is not possible. • An example of this situation is a strip shopping center where the developer does not know what type of tenants will lease the spaces. • Table 1 lists the watts/sq. ft. estimates for situations where the load is not available such as speculative lease spaces. • This table can also be used as a comparison tool to validate your calculated demand load.
  • 19. Watts Per Square Foot • TABLE 1 (This Information is 20 Years Old!) • LOAD INFORMATION – WATTS per SQ. FT. ESTIMATES • These may be used when actual load data is not available. • Watts Per Square Foot • Air Conditioning comfort cooling4 watts/sq ft. • computer rooms 5 watts/sq. ft. • Heating 6 watts/sq. ft. • Office Lighting 3 watts/sq. ft. • Warehouse Lighting 1 watt/sq. ft. • Office miscellaneous 1 watt/sq. ft. • Warehouse miscellaneous 1/2 watt/sq. ft. • Air Conditioning – By Tons • A/C (at 8.0 SEER) 1.5 kW/ton • Chiller units (including auxiliary equip.) 1.0 kW/ton • Fluorescent Lighting • 2' x 4' lay-in 2 lamp (4') 100 watts/fixture • 2' x 4' lay-in 4 lamp (4') 200 watts/fixture • 2' x 8' lay-in 2 lamp (8') 200 watts/fixture • Other Guidelines • 1 phase or 3 phase motor 750 watts/ horsepower • Swimming pool pumps (inefficient) 1.2 kW/horsepower • Refrigeration compressors 1.4 kW/ton
  • 20. 20 Watts Per Square Foot Example Typical Office Building TABLE 1 LOAD INFORMATION – WATTS per SQ. FT. ESTIMATES These may be used when actual load data is not available. Watts Per Square Foot Air Conditioning comfort cooling 4 watts/sq ft. computer rooms 5 watts/sq. ft. [summer & winter] Heating 6 watts/sq. ft. Office Lighting 3 watts/sq. ft. Warehouse Lighting 1 watt/sq. ft. Office miscellaneous 1 watt/sq. ft. Warehouse miscellaneous 1/2 watt/sq. ft. TOTAL= 8 watts/sq. ft.
  • 21. Do You Know Jack? • Another way to check your Demand KW estimate is by comparing it to an existing facility on your distribution system. • You are probably not serving the first “Jack in the Box” restaurant on your electric distribution system. • If you are serving a customer that has other existing facilities located on the distribution system – check your meter information system for the Demand KW of the existing locations.

Editor's Notes

  • #3: Read Slide
  • #4: Accurate load estimating is one of your most important responsibilities because it effects the project cost and the customer’s cost
  • #5: Read Slide
  • #6: Read slide
  • #7: Now lets talk about getting good load information from the customer. Read Slide
  • #8: Read Slide How do you determine if a motor is large and needs a motor start calculation? Ask someone in audience – What horsepower size do you consider to be large? A 25 hp motor may be considered large and a 100 hp may not! It depends on where it is located on our distribution system!
  • #9: Read Slide I hope it doesn’t take 15 minutes for the elevator to take you from the 1st floor to the 21st floor! Also – the 30 hp was sized to pull 1600 pounds of people up the to the top of the building. Is it using 30 hp of load to pull only 2 people? Not unless they each weigh 800 pounds!
  • #10: Rule of Thumb: 1 Ton = 1 kW of Connected Load (if the EER is 12) 1 Ton times 12 divided by EER Rating of 12 = 1 KW Ask – What if this was a very old A/C unit and the EER was 8? If the EER was 8 --- 1 Ton x 12 divided by 8 = 1.5 kW You can see the difference efficiency makes in A/C Load!! EER = Energy Efficiency Rating (3 phase units) SEER = Seasonal Energy Efficiency Rating (single phase units)
  • #11: Read Slide
  • #12: Read Slide 10 divided by 15 = .67 or 67% demand factor
  • #13: Read Slide
  • #14: Read Slide
  • #15: Read Slide
  • #16: This chart shows that 61.25 kW of connected load is only 17.17 kW of demand load (28% of connected load) This makes a significant difference in the sizing of our facilities! Typically your diversified demand load will be between 25% and 75% of the customers connected load.
  • #17: This slide compares the customer’s connected load to the actual demand load on a few projects in Round Rock.
  • #18: Read first Bullet of this slide
  • #19: Read slide
  • #20: The information in this table is over 20 years old and some of the numbers need to be revised! I would probably use 3 watts for A/C instead of 4 and 2 watts for office lighting instead of 3 New Fluorescent Lighting is more efficient than shown in table. You can see this table uses 8.0 SEER for A/C and you cannot buy a new ac unit that has a SEER less than 12?
  • #21: Read Slide 8 watts per sq ft may be too high! This table has not been updated in over 20 years and with higher efficiency a/c and lighting -- 6 watts may more accurate.
  • #22: Give example stories: Stone Oak Elementary School, HEB Gas Station & Car Wash, Red, Hot & Blue Restaurant.