SlideShare a Scribd company logo
Caissons
Module III
Course Content
• Definition, uses, construction material, types
of caissons, loads on caisson, design features
of caissons, floating of caissons, cutting edges,
sinking of caisson, tilting of caisson. Caisson
diseases.
Definition of Caissons
• Caisson is a water tight structure made of
wood, steel, R.C.C i.e. reinforced cement
constructed in connection with excavation for
the foundation of bridges, piers in rivers, dock
structures etc.
Uses of Caissons
• Caissons are more suitable for the deep foundation under water where the foundation
should be extended up to or below the river bed so as to obtain the proper stability.
• Caissons as type of well foundation is constructed in connection with excavation for
foundation of piers and abutments in rivers and lake, bridges, break water dock
structures for the point of view of shore protection, lamp house etc.
• When the construction of well foundation to be done under water. The construction
Of caisson are more preferable.
• When depth of water in river, lake, or sea etc. are more, than caisson structure is
used.
• Caisson are used as foundation for bridges piers, and abutments in rivers, seas, lakes,
break waters and other shore construction works.
• It is also used for pump house which are subjected to huge vertical as well as
horizontal forces.
• It is also occasionally used for large and multi-storey building and other structures.
Construction Material
• The Material used for the construction of caisson are
as follows:
• Wood
• Steel
• Reinforced Concrete
Shapes of Caissons
Caisson are constructed into two basic shapes and
combination of basic shape.
Shapes of Caissons:
(I) Basic Shape
(II) Combination of Basic Shape
Basic Shape:
(I) Circular
(II) Rectangular
(III) Square
(IV) Octagonal
Shapes of Caissons
Combination of Basic Shapes
• Double Circular
• Double Rectangular
• Double hexagonal
• Double-D
• Double Octagonal
Types of Caissons
• The Caissons is used for the purpose of placing a
foundation in correct position under water.
• Types of Caissons
• Open Caisson
• Box Caisson
• Pneumatic Caisson
Types of Caissons
Open Caissons
• It is a box type of structure which is open at the top
and at the bottom. Open Caisson are normally
used on sandy soils or soft bearing stratum and where
no firm bed is available at a higher depth.
• According to the shape of caissons, open caissons can
be further classified into three types as;
• Open Caisson
• Single Wall Open Caisson
• Cylindrical Open Caisson
• Open Caissons with dredging wells.
Open Caisson
Open Caisson
Construction of Open Caissons:
• The sinking process of open caisson can be done in the
following conditions:
• Dry
• Dewatered Construction
• Artificial Island
• In case of an artificial island called as sand island
method, the island can be made by raising the ground
surface above water level temporarily for obtaining
relatively dry area for the sinking process. The size of
sand island should be sufficient so that it can provide
more working space all around the caisson.
Construction of Open Caissons
• If dry Conditions is not possible on site, then caisson is built in barges or
slipways. Then it is towed to its towed to its final position by floating.
Guide piles are normally used for sinking the first few lifts. Note that
sinking of Caissons are directly done in open water.
• Excavation of soil by dredging the well sinks the caisson by its own weight
and the excavation process is done by dredging with the help of grab
buckets. The soil besides the cutting edge can be removed by man power.
Water Jets are used on exterior walls side so-as to run the sinking process
more easily.
• When the caisson is constructed to the required stage, then concrete seal
cap is provided caisson is dewatered by the method of pumping.
Advantages and Disadvantages of
Open Caissons
• Advantages of Open Caissons:
• Following are the advantages of Open Caissons:
• This type of Caisson can be extended up to large
depths.
• Cost of Construction is relatively less on bed level or
lower side.
Advantages and Disadvantages of
Open Caissons
• Disadvantages of Open Caissons:
• Following are the disadvantages of open Caissons;
• Since the placing of concrete is done for concrete seal
under water, it may not be satisfactory.
• If any obstruction of boulders or logs are encountered,
then progress of work becomes slow.
• Through cleaning and inspection at the bottom of
caisson is very difficult and hence not possible.
• The help of divers may be required for excavation near
haunches at the cutting edges.
Box Caissons
• Box caisson is similar to open caisson, only
difference is that it is closed at the bottom.
• Box caisson is cast and cured properly
on ground and then it is launched in water
by filling sand or gravel or concrete in the empty
spaces.
Box Caissons
Pneumatic Caissons
• This type of caisson is open at the bottom and close at
the top. Pneumatic caisson is specially used at the place
where it is not possible to construct the well.
• It is suitable for the depth of water more than 12 m.
• In the construction of Pneumatic Caisson,
the compressed air is used to remove water
from the working chamber and the foundation work
is carried out in dry condition.
• This type of caisson can be made of timber, concrete or
steel.
Pneumatic Caissons
Components of a Pneumatic Caissons
Following are the various components of a pneumatic
caissons:
Air Shaft
A passage connecting in between the working chamber and
air lock is termed as 'air shaft'
This passage or air shaft is used by the workmen or workers
to reach to the working chamber to ground surface.
If caisson is too large in size, the separate unit of air shaft may
be provided for workers and material.
Air Shaft is made up of steel material. The joint involved in
air shaft are sealed by rubber gasket air lock is provided on
each air shaft at top. When sinking process is going on, air
shaft is extended above the water level.
Components ofa Pneumatic Caissons
• Working Chamber:
• Working Chamber height is about 3 m and is
totally air tight and made up of structural steel.
• To prevent the entry of air and water into the
chamber, the air inside the chamber is kept at a
pressure just more than atmosphere pressure.
External surface of chamber is kept thick.
Chamber is leak proof and smooth to reduce skin
friction. To facilitate the proper processing of
sinking, a cutting edge is provided at the bottom.
Components ofa Pneumatic Caissons
• Air Lock: A chamber made of steel provided at the upper end of the
air shaft above the water level is called as 'Air Lock'. Air lock
allows the worker or workmen to enter or exit from the caisson
without releasing the air pressure in the working chamber.
• The air locks has two air tight doors, one door opens into shaft and
another door opens to the atmosphere. When workmen enters the
airlocks through the outside door, then pressure in the chamber is
kept at atmospheric level. Pressure is increased gradually till it
becomes equal to the working chamber. Under this condition
workmen is allowed to go into the air shaft. Complete procedure is
again done when workmen comes out of the air shaft to air lock.
• By opening a valve in the airlock, fresh air is circulated in the shaft
workers or workmen are allowed to work into the working chamber
up to 2 hrs.
• The maximum limit of working into the chamber is 2 hrs.
Components ofa Pneumatic Caissons
• Miscellaneous Equipments
• Different types of miscellaneous equipments used
in pneumatic caisson are as follows:
• Pumps
• Motors
• Air Compressors
• These equipments are normally placed above the
bed level.
• Through compressed air pipe, can be applied to
the working chamber.
Air Shaft
Advantages and Dis-advantages of
Pneumatic Caissons
• Following are the various advantages of pneumatic
caissons:
• Quality control is good because work is done in
dry conditions.
• Insitu soil tests are possible to determine the bearing
capacity.
• There is direct and easy passage to reach the bottom of
caisson, hence any obstruction can easily be removed.
• Concrete gain more strength due to dry conditions.
• For major projects, greater depths in bed rocks can be
possible.
• There is no danger of settlement of adjoining structures
because of no lowering of ground water table.
Disadvantages of Pneumatic Caisson
• Following are some of the disadvantages of pneumatic
caisson.
• Construction of pneumatic caissons is much expensive
than open caissons.
• During working the various constructional activities, a
proper care has to be taken, otherwise it may lead to
fatal accidents.
• Maximum depth below water table is limited to 30 m to
40 m. Beyond 40 m depth, construction is not possible.
• There is more chances of caisson diseases to workmen
working under high pressure.
• Labor cost is high.
Difference between Open Caisson and
Pneumatic Caissons
Loads on Caissons
Caisson is a well acted upon by the following loads:
Dead load of super-structure
Load of bearing pier
Various horizontal forces
Caissons is liable to acted upon by the following various horizontal
forces:
Wind force
Earth Pressure
Seismic load
Centrifugal forces
Water current forces
Bracking and tractive efforts ofthe moving vehicles
Force offered by the bearing against movement because of variation of
temperature.
Loads on Caissons
Floating of Caissons
• When Caisson are casted away from the site or off-
site, then these caisson are transported to the required
location by means of floating, then it is called as
floating of caissons In short, method of transportation
the casted caisson off-site to the desired location by
floating is called as floating of caissons.
• Floating Caissons are commonly termed as box
caisson. A box caisson is cast and cured on land and
when required, it is launched in water and towed to
the site by floating for sinking operation.
Floating Caisson
• After Casting the box Caission, it is taken to the site by floating
in water, then it is called as'floating' Caission.
• Sinking Process can be made-faster by increasing the self weight
of caisson, self weight is increased by adding sand or gravel
inside the caisson.
• Floating caisson are not provided by cutting edge as compared to
the other caisson. This type of caisson is simple rest on a hard
or level strata. In this way, load carrying capacity is a function
the resistance at the base since there is no skin friction on sides.
• On the top of Caission, a concrete cap is provided to carry the
loads uniformly from the super structure. To prevent the scouring
at the base of floating caisson, rip-rap is provided around the base
for better understanding.
Floating Caisson
Construction of Floating Caissons
Following are the various steps involved in the construction process of
floating caissions:
Floating Caission are cast and cured on land.
After casting and proper curing, it is floated to the desired location.
Caissons are filled with gravel or sand so as to facilitate proper sinking
process.
The required base location is excavated and levelled.
Then Caission is sunk to required location and depth.
Rip-Rap is provided all around the base of caisson which prevents the
scouring.
Concrete cap is casted at the top of caisson so as to carry the loads
uniformly from superstructure.
Floating caissons are constructed in reinforced cement concrete or steel.
When it is to floated and placed in rough waters, internal strutting and
diaphragm walls are used.
Advantages and Disadvantages of
floating Caissons
• Advantage of floating Caissons;
• Since concrete are pre-casted, good quality
control is possible
• Its installation is quick and more convenient
• These types of caissons are less expensive as
compared to other types of caissons
Advantages and Disadvantages of
floating Caissons
• The foundation of floating caisson:
• The foundation bed require levelled surface
before installation of a floating caisson
• Rip-rap should be provided to protect the
caisson from scouring
• Floating caisson or box caisson is only
advantageous when hard strata is available.
• Its load carrying capacity is less as compared
to other caisson of equal and same size.
Components of Well Foundation
• Cutting Edge:
• Sharp edge which is provided at the lower end of the well or open
and pneumatic caisson for accelerating sinking operation is called
cutting edge. It is made up steel or it is made in R.C.C. Its angle to
vertical is 30 0 and normally slope of 1 horizontal to 2 vertical given
better result.
• In concrete caissons, the lower part of the cutting edge is rigidly
fastened with 12 mm steel plates with the help of steel strap.
• The cutting edge should be sharp so as to penetrate into the soil and
it should resist the various stresses caused by blows, boulders,
blasting, etc.
• A sharp vertical edge is generally provided to the outside face of the
caisson. Edge facilities the rate of sinking.
Components of Well Foundation
• Topping
• Covering provided over the well or caisson is called as topping.
• Sand is filled in between topping and bottom plug. Topping also
acts as a part of shuttering for laying the well cap.
• Bottom Plug:
• The lower portion of well is sealed by the concrete is called as
bottom plug.
• Stening
• Stening is constructed in concrete or masonary work.
• Use of stening is to provide dead load during sinking operation.
Components of Well Foundation
• Well Curbs
• It is made of concrete or brick. Cutting edge of well or
caisson is attached to well curb. During sinking
operation well curb impart to the well-stening and
facilities the formation of bottom
• Well Cap
• R.C.C Slab covering provided over the top of well is
termed as well cap.
• Sand filling
• The portion between top and bottom plug is filled with
sand so as to increase the self weight of the well and
makes safe during earthquake.
Components of Well Foundation
Sinking of Caissons
• Sinking of Caisson in dry river bed:
• Construction of caisson curb or well curb:
• Well curb or caisson curb is built in case of a dry river
bed, so as to place at the correct position after
excavating the bed for about 15cm for seating. If the
depth of water is upto 5m, then sand island is
constructed. For even distribution of load, wooden
sleeps can be placed below cutting edge. When the
shuttering of caisson curb is done, then reinforcement
for the curb is placed in position. Concreting of curb is
done in one stroke and it should be done without gap so
as to obtain monolithic concreting structure.
Sinking of Caissons
• Construction of Caisson steining or well
stening:
• For a height of 1.5 m, the caisson steining is
constructed at a time when the caisson reaches
at a depth of 6 m below ground stening can be
raised with a height of 3 m at a time. Sinking
of Caisson is commenced after concrete is set
for 24 hrs.
Sinking of Caissons
• Sinking process:
• When the curb is cast, then sinking operation is started.
• The first stage of stening is ready after curing. In inner material if
comes as a obstruction can be excavated manually or
mechanically. If hard rock comes in the way, then blasting may
be done.
• For proper sinking operation, additional loading termed as
kentledge is used if required. Sand bags can be used as kentledge
which can be placed on a suitable platform on the top surface of
caisson.
• When caisson reaches at a depth of 10 m, dewatering is done by
pumping. Jetting of water is also helpful in sinking operation.
Proper care has been done by adopting the proper measures and
techniques so as to avoid shifts and tilts of caisson during sinking
Sinking of Caissons
Sinking of Caissons
Tilting of Caissons
• At the time of sinking process caisson should sink
exact vertically downward, straight and at the
corner position without any tilting of caisson.
• If the caisson tilt any one side from its position
while sinking operation, then it is called as tilting
of caisson. During sinking operation, it may also
shift way from the required position. Hence it is
much essential to take the suitable precautions so
as to avoid tilting and shifting of caisson.
Precautions to be taken to avoid tilts
and shift
• The cutting edge of caisson must be thick and
sharp pointed
• The external surface of steining and caisson curb
should be smooth.
• Dredging should be done uniformly on all sides
and in all pockets of caisson.
• Caisson should be symmetrically placed.
• The diameter (D) of the curb must be placed from
40 mm to 80 mm or larger or more than external
diameter of steining.
Remedial Measures to Rectify Tilt
and Shift
• Following are the remedial measures to be carefully
implemented to avoid tilting of caisson during sinking
process:
• Water Jetting:
• This is the one of the method used to prevent tilting. In
this method, water jet is forcedly applied on tilt.
• Application of water jetting on higher side reduces skin
friction. Thus the tilting is rectified.
• This method is not more effective but gives the better
result if used with the combination of other methods.
Remedial Measures to Rectify Tilt
and Shift
Remedial Measures to Rectify Tilt
and Shift
• Eccentric loading:
• The caisson is normally given the additional
loading called kentledge in order to have
necessary sinking effort. In this method, eccentric
loading or kentledge is applied in higher side so
as to have greater sinking effort.
• For proper application of eccentric loading a
platform with projection on higher side can be
placed over the top of caisson
• The eccentric load is kept on projected part of
platform. Thus tilt can be rectified.
Remedial Measures to Rectify Tilt
and Shift
Remedial Measures to Rectify Tilt
and Shift
• Excavation under cutting edge;
• During sinking process, filled caisson will not
set or straighten due to unbroken stiff strata on
its higher side. In such situation, dewatering is
preferably done to loosen stiff strata. If
dewatering is not possible or unsafe, then
drivers are sent to loosen the stiff strata.
• Sometimes if possible and safe, an open
excavation is done under the cutting edge.
Excavation under cutting edge;
Remedial Measures to Rectify Tilt
and Shift
• Regulation of Excavation;
• Sinking of caisson on higher side due to
excess excavation is more. This is all right in
the early stages, otherwise dewatering of
caisson or well is needed and open excavation
may be done on higher side.
Remedial Measures to Rectify Tilt
and Shift
• Providing temporary obstacles below the
cutting edge:
• Rectification of tilt can be done by inserting
the wooden sleeper temporarily as an obstacles
below the cutting edge on the lower side so as
to prevent further tilt of the well or caisson.
• Later on, wooden sleeper can be removed, for
better understanding.
Providing temporary obstacles
below the cutting edge:
Remedial Measures to Rectify Tilt
and Shift
• Pushing the caissons or well with jack:
• Mechanical jack or hydraulic jack can be used
to rectify the tilt of well or caisson. Well or
caisson can be pushed by jack to bring it a
vertical position.
Pushing the caissons or well with
jack:
Remedial Measures to Rectify Tilt
and Shift
• Pulling the well or caisson: This method is
most suitable and effective in preliminary or
early stages of sinking operation. Steel ropes
or cables are used pull the caisson or well.
Pulling of caisson or well is done on higher
side of well or caisson
Pulling the well or caisson
Remedial Measures to Rectify Tilt
and Shift
• Strutting the caissons or well:
• Method of strutting the caisson or well is used to
prevent any further and possible rise in tilting of
the caisson or well.
• The caisson or well is supported on the tilting side
by giving inclined support of a strong wooden
member. This inclined wooden member is called
as a strut.
• The caisson or well steining is provided so as to
distribute the uniform pressure or load from strut.
Strutting the caissons or well
Caisson Diseases
• In case of sinking process of pneumatic caisson, workers or
workmen have to work in working chamber under
compressed air. If the compressed air pressure is less than
0.35 N/mm 2 to 0.4 N/ mm 2, then workmen may suffer
from the following pains:
• Workmen may suffer from giddiness
• There is pains in ears of workmen
• There is breaking of ear drums of workmen
• There is bursting of blood vessels in the nose or ears of
workmen
• The above mentioned pains are not that serious or fatal, but
workmen is actually suffering during decompression and
effect causing depression is called caisson disease.
Caisson Diseases
• Following are the caisson disease caused by decompression:
• Severe pains in joints leading to bends
• It may cause paralytic death
• Excessive oxygen get absorbed in the blood and tissues
during decompression is more trouble some to workmen.
Absorbed oxygen gas is thrown out of blood in the form of
bubbles which can block in vessels and may cause bursting
of vessels.
• If bubbles are developed in joints it causes bends
• If the bubbles are developed in spinal cord, it causes
paralysis and if the bubble are developed in heart, it causes
heart attack.
• Caisson diseases can be controlled by recompression
followed by slow decompression.
Caisson Diseases
Thanks

More Related Content

PPTX
Modes of failure of retaining walls
Ritesh Chinchawade
 
PPTX
Pile foundation
Sherchandra Shrestha
 
PPT
Chapter 3 caisson
KHUSHBU SHAH
 
PPTX
Caisson
bhavin punjani
 
PDF
Illegal mining and its impacts in India presentation
nachiketvyawahare
 
PPT
X-Ray Diffractogram for clay mineralogy Identification, analytical bckv, P.K...
P.K. Mani
 
PPTX
DIFFERENT TYPE OF SHALLOW FOUNDATION
bishal120
 
PDF
Longwall Mining
RAMANA M V
 
Modes of failure of retaining walls
Ritesh Chinchawade
 
Pile foundation
Sherchandra Shrestha
 
Chapter 3 caisson
KHUSHBU SHAH
 
Illegal mining and its impacts in India presentation
nachiketvyawahare
 
X-Ray Diffractogram for clay mineralogy Identification, analytical bckv, P.K...
P.K. Mani
 
DIFFERENT TYPE OF SHALLOW FOUNDATION
bishal120
 
Longwall Mining
RAMANA M V
 

What's hot (20)

DOCX
Different types of pile
Gaurang Kakadiya
 
PPTX
Dewatering techniques
jamali husain
 
PDF
coulomb's theory of earth pressure
SANJEEV Wazir
 
PPT
Soil stabilisation (1)
Safiullah Khan
 
PDF
Load carrying capacity of piles
Latif Hyder Wadho
 
PDF
Under reamed piles
AkhilaSaraVarghese1
 
PPTX
Settlement of soil/foundation
Jam Shoaib Ahmed veeha
 
PPTX
Burmister 2 layer
SandeepUpadhyay41
 
PPTX
Embankment
civilguna
 
PPTX
Cbr test
Kaushal Gamit
 
PPTX
Bearing Capacity of Shallow Foundation
Arbaz Kazi
 
PPTX
Khosla theory
AparnaRath
 
PPTX
Abstractions of precipitation ppt
pradeepkumawat4142
 
PPTX
Theory for impervious floor
Divya Vishnoi
 
PPTX
Storage head works
Anirudhan K M
 
PDF
Chapter 1: Foundation Engineering
anandpanta1
 
PPTX
Pile foundation
ghildiyal8811
 
PPTX
Stress distribution of the soil
Dharmik Navadiya
 
PPTX
Gravity dams galleries
saibabu48
 
PPTX
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
Shivananda Roy
 
Different types of pile
Gaurang Kakadiya
 
Dewatering techniques
jamali husain
 
coulomb's theory of earth pressure
SANJEEV Wazir
 
Soil stabilisation (1)
Safiullah Khan
 
Load carrying capacity of piles
Latif Hyder Wadho
 
Under reamed piles
AkhilaSaraVarghese1
 
Settlement of soil/foundation
Jam Shoaib Ahmed veeha
 
Burmister 2 layer
SandeepUpadhyay41
 
Embankment
civilguna
 
Cbr test
Kaushal Gamit
 
Bearing Capacity of Shallow Foundation
Arbaz Kazi
 
Khosla theory
AparnaRath
 
Abstractions of precipitation ppt
pradeepkumawat4142
 
Theory for impervious floor
Divya Vishnoi
 
Storage head works
Anirudhan K M
 
Chapter 1: Foundation Engineering
anandpanta1
 
Pile foundation
ghildiyal8811
 
Stress distribution of the soil
Dharmik Navadiya
 
Gravity dams galleries
saibabu48
 
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
Shivananda Roy
 
Ad

Similar to Well foundations notes (20)

PPTX
Caissons
GAURAV. H .TANDON
 
PPTX
caissons.pptx
PavanNadgouda2
 
PPTX
Underwater construction is a method on how to place the concrete underwater.
chanchalmodi2
 
PPTX
CAISSON PPT.pptx
kushpatel927805
 
PPTX
2. CAISSONS (ACE) 2160601 GTU
VATSAL PATEL
 
PPTX
Underwater construction
Pranay Kumar
 
PPTX
Underwater construction
HetviPatel58
 
PPTX
Chapter 4.2 coffer dam, well foundation-final1
DYPCET
 
PPT
1.6 caisson
Rafique Ahmed Sayed
 
PPTX
caissons and cofferdam in substructure construction
ChinnuNinan
 
PPTX
Cofferdams
GAURAV. H .TANDON
 
PPT
Cofferdam
Shashank Namdeo
 
PDF
Caissons_Advanced Construction Technology (Semester-6), Civil Engineering
A Makwana
 
PPTX
1619929813526_College Deep Well Foundation Project.pptx
AkshayGhorpade19
 
PPTX
Well Foundation
Dave Chinmyee
 
PPTX
WELL COMPLETIONS.pptx
DagogoGreenFurosigha
 
PPTX
Cofferdam_ppt.pptx
JackRider12
 
PPTX
Chapter 4.3 well foundation-final-ppt
DYPCET
 
PPT
Caisson
Piash Saha
 
PDF
CB 523 Methods and Equipment for Construction 1 Lecture 8&9: Construction Dew...
lrbol
 
caissons.pptx
PavanNadgouda2
 
Underwater construction is a method on how to place the concrete underwater.
chanchalmodi2
 
CAISSON PPT.pptx
kushpatel927805
 
2. CAISSONS (ACE) 2160601 GTU
VATSAL PATEL
 
Underwater construction
Pranay Kumar
 
Underwater construction
HetviPatel58
 
Chapter 4.2 coffer dam, well foundation-final1
DYPCET
 
1.6 caisson
Rafique Ahmed Sayed
 
caissons and cofferdam in substructure construction
ChinnuNinan
 
Cofferdams
GAURAV. H .TANDON
 
Cofferdam
Shashank Namdeo
 
Caissons_Advanced Construction Technology (Semester-6), Civil Engineering
A Makwana
 
1619929813526_College Deep Well Foundation Project.pptx
AkshayGhorpade19
 
Well Foundation
Dave Chinmyee
 
WELL COMPLETIONS.pptx
DagogoGreenFurosigha
 
Cofferdam_ppt.pptx
JackRider12
 
Chapter 4.3 well foundation-final-ppt
DYPCET
 
Caisson
Piash Saha
 
CB 523 Methods and Equipment for Construction 1 Lecture 8&9: Construction Dew...
lrbol
 
Ad

More from PRASANTHI PETLURU (20)

PDF
Unit VI : Boundary layer theory notes
PRASANTHI PETLURU
 
PDF
Flow through pipes notes
PRASANTHI PETLURU
 
PDF
Unit III : Fluid dynamics notes
PRASANTHI PETLURU
 
PDF
unit II : Fluid kinematics notes
PRASANTHI PETLURU
 
PDF
Unit I : Fluid statics notes
PRASANTHI PETLURU
 
PDF
Ay 2020 2021 fe supply key
PRASANTHI PETLURU
 
PDF
Ay 2020 2021 fe supply qp
PRASANTHI PETLURU
 
PDF
Ay 2017 2018 fe see key
PRASANTHI PETLURU
 
PDF
Ay 2017 2018 fe see qp
PRASANTHI PETLURU
 
PDF
Ay 2016 2017 fe see qp
PRASANTHI PETLURU
 
PDF
2018 2019 a26 a3 fe see qp
PRASANTHI PETLURU
 
PDF
2018 2019 a26 a3 fe see qp key
PRASANTHI PETLURU
 
PDF
Unit ii pile foundations hand written notes
PRASANTHI PETLURU
 
PDF
Slope stability Hand written notes
PRASANTHI PETLURU
 
PDF
Earth Pressure Theories and Retaining Walls Hand written Notes
PRASANTHI PETLURU
 
PDF
Unit 2 shallow foundations Hand written notes
PRASANTHI PETLURU
 
PDF
Unit 1 soil exploration Hand written notes
PRASANTHI PETLURU
 
PDF
Boundary layer theory hand written notes
PRASANTHI PETLURU
 
PDF
Unit IV - Flow through pipes hand written notes
PRASANTHI PETLURU
 
PDF
Unit III - Fluid dynamics notes
PRASANTHI PETLURU
 
Unit VI : Boundary layer theory notes
PRASANTHI PETLURU
 
Flow through pipes notes
PRASANTHI PETLURU
 
Unit III : Fluid dynamics notes
PRASANTHI PETLURU
 
unit II : Fluid kinematics notes
PRASANTHI PETLURU
 
Unit I : Fluid statics notes
PRASANTHI PETLURU
 
Ay 2020 2021 fe supply key
PRASANTHI PETLURU
 
Ay 2020 2021 fe supply qp
PRASANTHI PETLURU
 
Ay 2017 2018 fe see key
PRASANTHI PETLURU
 
Ay 2017 2018 fe see qp
PRASANTHI PETLURU
 
Ay 2016 2017 fe see qp
PRASANTHI PETLURU
 
2018 2019 a26 a3 fe see qp
PRASANTHI PETLURU
 
2018 2019 a26 a3 fe see qp key
PRASANTHI PETLURU
 
Unit ii pile foundations hand written notes
PRASANTHI PETLURU
 
Slope stability Hand written notes
PRASANTHI PETLURU
 
Earth Pressure Theories and Retaining Walls Hand written Notes
PRASANTHI PETLURU
 
Unit 2 shallow foundations Hand written notes
PRASANTHI PETLURU
 
Unit 1 soil exploration Hand written notes
PRASANTHI PETLURU
 
Boundary layer theory hand written notes
PRASANTHI PETLURU
 
Unit IV - Flow through pipes hand written notes
PRASANTHI PETLURU
 
Unit III - Fluid dynamics notes
PRASANTHI PETLURU
 

Recently uploaded (20)

PPTX
Practice Questions on recent development part 1.pptx
JaspalSingh402
 
PPTX
ANIMAL INTERVENTION WARNING SYSTEM (4).pptx
dodultrongaming
 
PDF
6th International Conference on Artificial Intelligence and Machine Learning ...
gerogepatton
 
PDF
LEAP-1B presedntation xxxxxxxxxxxxxxxxxxxxxxxxxxxxx
hatem173148
 
PDF
Introduction to Data Science: data science process
ShivarkarSandip
 
PPTX
Production of bioplastic from fruit peels.pptx
alwingeorgealwingeor
 
PPTX
Unit 5 BSP.pptxytrrftyyydfyujfttyczcgvcd
ghousebhasha2007
 
PDF
July 2025: Top 10 Read Articles Advanced Information Technology
ijait
 
PDF
algorithms-16-00088-v2hghjjnjnhhhnnjhj.pdf
Ajaykumar966781
 
PPT
Ppt for engineering students application on field effect
lakshmi.ec
 
PDF
Traditional Exams vs Continuous Assessment in Boarding Schools.pdf
The Asian School
 
PDF
BRKDCN-2613.pdf Cisco AI DC NVIDIA presentation
demidovs1
 
PPTX
Module2 Data Base Design- ER and NF.pptx
gomathisankariv2
 
PDF
Monitoring Global Terrestrial Surface Water Height using Remote Sensing - ARS...
VICTOR MAESTRE RAMIREZ
 
PDF
dse_final_merit_2025_26 gtgfffffcjjjuuyy
rushabhjain127
 
PPTX
Chapter----five---Resource Recovery.pptx
078bce110prashant
 
PDF
ETO & MEO Certificate of Competency Questions and Answers
Mahmoud Moghtaderi
 
PDF
Structs to JSON How Go Powers REST APIs.pdf
Emily Achieng
 
PDF
Queuing formulas to evaluate throughputs and servers
gptshubham
 
PDF
Unit I Part II.pdf : Security Fundamentals
Dr. Madhuri Jawale
 
Practice Questions on recent development part 1.pptx
JaspalSingh402
 
ANIMAL INTERVENTION WARNING SYSTEM (4).pptx
dodultrongaming
 
6th International Conference on Artificial Intelligence and Machine Learning ...
gerogepatton
 
LEAP-1B presedntation xxxxxxxxxxxxxxxxxxxxxxxxxxxxx
hatem173148
 
Introduction to Data Science: data science process
ShivarkarSandip
 
Production of bioplastic from fruit peels.pptx
alwingeorgealwingeor
 
Unit 5 BSP.pptxytrrftyyydfyujfttyczcgvcd
ghousebhasha2007
 
July 2025: Top 10 Read Articles Advanced Information Technology
ijait
 
algorithms-16-00088-v2hghjjnjnhhhnnjhj.pdf
Ajaykumar966781
 
Ppt for engineering students application on field effect
lakshmi.ec
 
Traditional Exams vs Continuous Assessment in Boarding Schools.pdf
The Asian School
 
BRKDCN-2613.pdf Cisco AI DC NVIDIA presentation
demidovs1
 
Module2 Data Base Design- ER and NF.pptx
gomathisankariv2
 
Monitoring Global Terrestrial Surface Water Height using Remote Sensing - ARS...
VICTOR MAESTRE RAMIREZ
 
dse_final_merit_2025_26 gtgfffffcjjjuuyy
rushabhjain127
 
Chapter----five---Resource Recovery.pptx
078bce110prashant
 
ETO & MEO Certificate of Competency Questions and Answers
Mahmoud Moghtaderi
 
Structs to JSON How Go Powers REST APIs.pdf
Emily Achieng
 
Queuing formulas to evaluate throughputs and servers
gptshubham
 
Unit I Part II.pdf : Security Fundamentals
Dr. Madhuri Jawale
 

Well foundations notes

  • 2. Course Content • Definition, uses, construction material, types of caissons, loads on caisson, design features of caissons, floating of caissons, cutting edges, sinking of caisson, tilting of caisson. Caisson diseases.
  • 3. Definition of Caissons • Caisson is a water tight structure made of wood, steel, R.C.C i.e. reinforced cement constructed in connection with excavation for the foundation of bridges, piers in rivers, dock structures etc.
  • 4. Uses of Caissons • Caissons are more suitable for the deep foundation under water where the foundation should be extended up to or below the river bed so as to obtain the proper stability. • Caissons as type of well foundation is constructed in connection with excavation for foundation of piers and abutments in rivers and lake, bridges, break water dock structures for the point of view of shore protection, lamp house etc. • When the construction of well foundation to be done under water. The construction Of caisson are more preferable. • When depth of water in river, lake, or sea etc. are more, than caisson structure is used. • Caisson are used as foundation for bridges piers, and abutments in rivers, seas, lakes, break waters and other shore construction works. • It is also used for pump house which are subjected to huge vertical as well as horizontal forces. • It is also occasionally used for large and multi-storey building and other structures.
  • 5. Construction Material • The Material used for the construction of caisson are as follows: • Wood • Steel • Reinforced Concrete
  • 6. Shapes of Caissons Caisson are constructed into two basic shapes and combination of basic shape. Shapes of Caissons: (I) Basic Shape (II) Combination of Basic Shape Basic Shape: (I) Circular (II) Rectangular (III) Square (IV) Octagonal
  • 8. Combination of Basic Shapes • Double Circular • Double Rectangular • Double hexagonal • Double-D • Double Octagonal
  • 9. Types of Caissons • The Caissons is used for the purpose of placing a foundation in correct position under water. • Types of Caissons • Open Caisson • Box Caisson • Pneumatic Caisson
  • 11. Open Caissons • It is a box type of structure which is open at the top and at the bottom. Open Caisson are normally used on sandy soils or soft bearing stratum and where no firm bed is available at a higher depth. • According to the shape of caissons, open caissons can be further classified into three types as; • Open Caisson • Single Wall Open Caisson • Cylindrical Open Caisson • Open Caissons with dredging wells.
  • 14. Construction of Open Caissons: • The sinking process of open caisson can be done in the following conditions: • Dry • Dewatered Construction • Artificial Island • In case of an artificial island called as sand island method, the island can be made by raising the ground surface above water level temporarily for obtaining relatively dry area for the sinking process. The size of sand island should be sufficient so that it can provide more working space all around the caisson.
  • 15. Construction of Open Caissons • If dry Conditions is not possible on site, then caisson is built in barges or slipways. Then it is towed to its towed to its final position by floating. Guide piles are normally used for sinking the first few lifts. Note that sinking of Caissons are directly done in open water. • Excavation of soil by dredging the well sinks the caisson by its own weight and the excavation process is done by dredging with the help of grab buckets. The soil besides the cutting edge can be removed by man power. Water Jets are used on exterior walls side so-as to run the sinking process more easily. • When the caisson is constructed to the required stage, then concrete seal cap is provided caisson is dewatered by the method of pumping.
  • 16. Advantages and Disadvantages of Open Caissons • Advantages of Open Caissons: • Following are the advantages of Open Caissons: • This type of Caisson can be extended up to large depths. • Cost of Construction is relatively less on bed level or lower side.
  • 17. Advantages and Disadvantages of Open Caissons • Disadvantages of Open Caissons: • Following are the disadvantages of open Caissons; • Since the placing of concrete is done for concrete seal under water, it may not be satisfactory. • If any obstruction of boulders or logs are encountered, then progress of work becomes slow. • Through cleaning and inspection at the bottom of caisson is very difficult and hence not possible. • The help of divers may be required for excavation near haunches at the cutting edges.
  • 18. Box Caissons • Box caisson is similar to open caisson, only difference is that it is closed at the bottom. • Box caisson is cast and cured properly on ground and then it is launched in water by filling sand or gravel or concrete in the empty spaces.
  • 20. Pneumatic Caissons • This type of caisson is open at the bottom and close at the top. Pneumatic caisson is specially used at the place where it is not possible to construct the well. • It is suitable for the depth of water more than 12 m. • In the construction of Pneumatic Caisson, the compressed air is used to remove water from the working chamber and the foundation work is carried out in dry condition. • This type of caisson can be made of timber, concrete or steel.
  • 22. Components of a Pneumatic Caissons Following are the various components of a pneumatic caissons: Air Shaft A passage connecting in between the working chamber and air lock is termed as 'air shaft' This passage or air shaft is used by the workmen or workers to reach to the working chamber to ground surface. If caisson is too large in size, the separate unit of air shaft may be provided for workers and material. Air Shaft is made up of steel material. The joint involved in air shaft are sealed by rubber gasket air lock is provided on each air shaft at top. When sinking process is going on, air shaft is extended above the water level.
  • 23. Components ofa Pneumatic Caissons • Working Chamber: • Working Chamber height is about 3 m and is totally air tight and made up of structural steel. • To prevent the entry of air and water into the chamber, the air inside the chamber is kept at a pressure just more than atmosphere pressure. External surface of chamber is kept thick. Chamber is leak proof and smooth to reduce skin friction. To facilitate the proper processing of sinking, a cutting edge is provided at the bottom.
  • 24. Components ofa Pneumatic Caissons • Air Lock: A chamber made of steel provided at the upper end of the air shaft above the water level is called as 'Air Lock'. Air lock allows the worker or workmen to enter or exit from the caisson without releasing the air pressure in the working chamber. • The air locks has two air tight doors, one door opens into shaft and another door opens to the atmosphere. When workmen enters the airlocks through the outside door, then pressure in the chamber is kept at atmospheric level. Pressure is increased gradually till it becomes equal to the working chamber. Under this condition workmen is allowed to go into the air shaft. Complete procedure is again done when workmen comes out of the air shaft to air lock. • By opening a valve in the airlock, fresh air is circulated in the shaft workers or workmen are allowed to work into the working chamber up to 2 hrs. • The maximum limit of working into the chamber is 2 hrs.
  • 25. Components ofa Pneumatic Caissons • Miscellaneous Equipments • Different types of miscellaneous equipments used in pneumatic caisson are as follows: • Pumps • Motors • Air Compressors • These equipments are normally placed above the bed level. • Through compressed air pipe, can be applied to the working chamber.
  • 27. Advantages and Dis-advantages of Pneumatic Caissons • Following are the various advantages of pneumatic caissons: • Quality control is good because work is done in dry conditions. • Insitu soil tests are possible to determine the bearing capacity. • There is direct and easy passage to reach the bottom of caisson, hence any obstruction can easily be removed. • Concrete gain more strength due to dry conditions. • For major projects, greater depths in bed rocks can be possible. • There is no danger of settlement of adjoining structures because of no lowering of ground water table.
  • 28. Disadvantages of Pneumatic Caisson • Following are some of the disadvantages of pneumatic caisson. • Construction of pneumatic caissons is much expensive than open caissons. • During working the various constructional activities, a proper care has to be taken, otherwise it may lead to fatal accidents. • Maximum depth below water table is limited to 30 m to 40 m. Beyond 40 m depth, construction is not possible. • There is more chances of caisson diseases to workmen working under high pressure. • Labor cost is high.
  • 29. Difference between Open Caisson and Pneumatic Caissons
  • 30. Loads on Caissons Caisson is a well acted upon by the following loads: Dead load of super-structure Load of bearing pier Various horizontal forces Caissons is liable to acted upon by the following various horizontal forces: Wind force Earth Pressure Seismic load Centrifugal forces Water current forces Bracking and tractive efforts ofthe moving vehicles Force offered by the bearing against movement because of variation of temperature.
  • 32. Floating of Caissons • When Caisson are casted away from the site or off- site, then these caisson are transported to the required location by means of floating, then it is called as floating of caissons In short, method of transportation the casted caisson off-site to the desired location by floating is called as floating of caissons. • Floating Caissons are commonly termed as box caisson. A box caisson is cast and cured on land and when required, it is launched in water and towed to the site by floating for sinking operation.
  • 33. Floating Caisson • After Casting the box Caission, it is taken to the site by floating in water, then it is called as'floating' Caission. • Sinking Process can be made-faster by increasing the self weight of caisson, self weight is increased by adding sand or gravel inside the caisson. • Floating caisson are not provided by cutting edge as compared to the other caisson. This type of caisson is simple rest on a hard or level strata. In this way, load carrying capacity is a function the resistance at the base since there is no skin friction on sides. • On the top of Caission, a concrete cap is provided to carry the loads uniformly from the super structure. To prevent the scouring at the base of floating caisson, rip-rap is provided around the base for better understanding.
  • 35. Construction of Floating Caissons Following are the various steps involved in the construction process of floating caissions: Floating Caission are cast and cured on land. After casting and proper curing, it is floated to the desired location. Caissons are filled with gravel or sand so as to facilitate proper sinking process. The required base location is excavated and levelled. Then Caission is sunk to required location and depth. Rip-Rap is provided all around the base of caisson which prevents the scouring. Concrete cap is casted at the top of caisson so as to carry the loads uniformly from superstructure. Floating caissons are constructed in reinforced cement concrete or steel. When it is to floated and placed in rough waters, internal strutting and diaphragm walls are used.
  • 36. Advantages and Disadvantages of floating Caissons • Advantage of floating Caissons; • Since concrete are pre-casted, good quality control is possible • Its installation is quick and more convenient • These types of caissons are less expensive as compared to other types of caissons
  • 37. Advantages and Disadvantages of floating Caissons • The foundation of floating caisson: • The foundation bed require levelled surface before installation of a floating caisson • Rip-rap should be provided to protect the caisson from scouring • Floating caisson or box caisson is only advantageous when hard strata is available. • Its load carrying capacity is less as compared to other caisson of equal and same size.
  • 38. Components of Well Foundation • Cutting Edge: • Sharp edge which is provided at the lower end of the well or open and pneumatic caisson for accelerating sinking operation is called cutting edge. It is made up steel or it is made in R.C.C. Its angle to vertical is 30 0 and normally slope of 1 horizontal to 2 vertical given better result. • In concrete caissons, the lower part of the cutting edge is rigidly fastened with 12 mm steel plates with the help of steel strap. • The cutting edge should be sharp so as to penetrate into the soil and it should resist the various stresses caused by blows, boulders, blasting, etc. • A sharp vertical edge is generally provided to the outside face of the caisson. Edge facilities the rate of sinking.
  • 39. Components of Well Foundation • Topping • Covering provided over the well or caisson is called as topping. • Sand is filled in between topping and bottom plug. Topping also acts as a part of shuttering for laying the well cap. • Bottom Plug: • The lower portion of well is sealed by the concrete is called as bottom plug. • Stening • Stening is constructed in concrete or masonary work. • Use of stening is to provide dead load during sinking operation.
  • 40. Components of Well Foundation • Well Curbs • It is made of concrete or brick. Cutting edge of well or caisson is attached to well curb. During sinking operation well curb impart to the well-stening and facilities the formation of bottom • Well Cap • R.C.C Slab covering provided over the top of well is termed as well cap. • Sand filling • The portion between top and bottom plug is filled with sand so as to increase the self weight of the well and makes safe during earthquake.
  • 41. Components of Well Foundation
  • 42. Sinking of Caissons • Sinking of Caisson in dry river bed: • Construction of caisson curb or well curb: • Well curb or caisson curb is built in case of a dry river bed, so as to place at the correct position after excavating the bed for about 15cm for seating. If the depth of water is upto 5m, then sand island is constructed. For even distribution of load, wooden sleeps can be placed below cutting edge. When the shuttering of caisson curb is done, then reinforcement for the curb is placed in position. Concreting of curb is done in one stroke and it should be done without gap so as to obtain monolithic concreting structure.
  • 43. Sinking of Caissons • Construction of Caisson steining or well stening: • For a height of 1.5 m, the caisson steining is constructed at a time when the caisson reaches at a depth of 6 m below ground stening can be raised with a height of 3 m at a time. Sinking of Caisson is commenced after concrete is set for 24 hrs.
  • 44. Sinking of Caissons • Sinking process: • When the curb is cast, then sinking operation is started. • The first stage of stening is ready after curing. In inner material if comes as a obstruction can be excavated manually or mechanically. If hard rock comes in the way, then blasting may be done. • For proper sinking operation, additional loading termed as kentledge is used if required. Sand bags can be used as kentledge which can be placed on a suitable platform on the top surface of caisson. • When caisson reaches at a depth of 10 m, dewatering is done by pumping. Jetting of water is also helpful in sinking operation. Proper care has been done by adopting the proper measures and techniques so as to avoid shifts and tilts of caisson during sinking
  • 47. Tilting of Caissons • At the time of sinking process caisson should sink exact vertically downward, straight and at the corner position without any tilting of caisson. • If the caisson tilt any one side from its position while sinking operation, then it is called as tilting of caisson. During sinking operation, it may also shift way from the required position. Hence it is much essential to take the suitable precautions so as to avoid tilting and shifting of caisson.
  • 48. Precautions to be taken to avoid tilts and shift • The cutting edge of caisson must be thick and sharp pointed • The external surface of steining and caisson curb should be smooth. • Dredging should be done uniformly on all sides and in all pockets of caisson. • Caisson should be symmetrically placed. • The diameter (D) of the curb must be placed from 40 mm to 80 mm or larger or more than external diameter of steining.
  • 49. Remedial Measures to Rectify Tilt and Shift • Following are the remedial measures to be carefully implemented to avoid tilting of caisson during sinking process: • Water Jetting: • This is the one of the method used to prevent tilting. In this method, water jet is forcedly applied on tilt. • Application of water jetting on higher side reduces skin friction. Thus the tilting is rectified. • This method is not more effective but gives the better result if used with the combination of other methods.
  • 50. Remedial Measures to Rectify Tilt and Shift
  • 51. Remedial Measures to Rectify Tilt and Shift • Eccentric loading: • The caisson is normally given the additional loading called kentledge in order to have necessary sinking effort. In this method, eccentric loading or kentledge is applied in higher side so as to have greater sinking effort. • For proper application of eccentric loading a platform with projection on higher side can be placed over the top of caisson • The eccentric load is kept on projected part of platform. Thus tilt can be rectified.
  • 52. Remedial Measures to Rectify Tilt and Shift
  • 53. Remedial Measures to Rectify Tilt and Shift • Excavation under cutting edge; • During sinking process, filled caisson will not set or straighten due to unbroken stiff strata on its higher side. In such situation, dewatering is preferably done to loosen stiff strata. If dewatering is not possible or unsafe, then drivers are sent to loosen the stiff strata. • Sometimes if possible and safe, an open excavation is done under the cutting edge.
  • 55. Remedial Measures to Rectify Tilt and Shift • Regulation of Excavation; • Sinking of caisson on higher side due to excess excavation is more. This is all right in the early stages, otherwise dewatering of caisson or well is needed and open excavation may be done on higher side.
  • 56. Remedial Measures to Rectify Tilt and Shift • Providing temporary obstacles below the cutting edge: • Rectification of tilt can be done by inserting the wooden sleeper temporarily as an obstacles below the cutting edge on the lower side so as to prevent further tilt of the well or caisson. • Later on, wooden sleeper can be removed, for better understanding.
  • 58. Remedial Measures to Rectify Tilt and Shift • Pushing the caissons or well with jack: • Mechanical jack or hydraulic jack can be used to rectify the tilt of well or caisson. Well or caisson can be pushed by jack to bring it a vertical position.
  • 59. Pushing the caissons or well with jack:
  • 60. Remedial Measures to Rectify Tilt and Shift • Pulling the well or caisson: This method is most suitable and effective in preliminary or early stages of sinking operation. Steel ropes or cables are used pull the caisson or well. Pulling of caisson or well is done on higher side of well or caisson
  • 61. Pulling the well or caisson
  • 62. Remedial Measures to Rectify Tilt and Shift • Strutting the caissons or well: • Method of strutting the caisson or well is used to prevent any further and possible rise in tilting of the caisson or well. • The caisson or well is supported on the tilting side by giving inclined support of a strong wooden member. This inclined wooden member is called as a strut. • The caisson or well steining is provided so as to distribute the uniform pressure or load from strut.
  • 64. Caisson Diseases • In case of sinking process of pneumatic caisson, workers or workmen have to work in working chamber under compressed air. If the compressed air pressure is less than 0.35 N/mm 2 to 0.4 N/ mm 2, then workmen may suffer from the following pains: • Workmen may suffer from giddiness • There is pains in ears of workmen • There is breaking of ear drums of workmen • There is bursting of blood vessels in the nose or ears of workmen • The above mentioned pains are not that serious or fatal, but workmen is actually suffering during decompression and effect causing depression is called caisson disease.
  • 65. Caisson Diseases • Following are the caisson disease caused by decompression: • Severe pains in joints leading to bends • It may cause paralytic death • Excessive oxygen get absorbed in the blood and tissues during decompression is more trouble some to workmen. Absorbed oxygen gas is thrown out of blood in the form of bubbles which can block in vessels and may cause bursting of vessels. • If bubbles are developed in joints it causes bends • If the bubbles are developed in spinal cord, it causes paralysis and if the bubble are developed in heart, it causes heart attack. • Caisson diseases can be controlled by recompression followed by slow decompression.