Mumbai Ahmadabad High Speed Rail Project
Rationale and Background
•The growing transport needs of the country requires construction of
High Speed Railway (HSR) in India.
•Any Railway System having speed potential in excess of 200 kmph
are considered as High Speed Railway.
•The MAHSR project started in 2012 with initial discussions between
Govt. of India and Govt. of Japan. Feasibility study undertaken by
Japanese consultants in December 2013 and report submitted in
July 2015. The project has been approved by Government of India vide
CCEA/31/2015 dated. 09.12.2015
Rationale and Background
•National High Speed Rail Corporation (NHSRCL), A Special Purpose
Vehicle under Ministry of Railways, Govt. of India was set up with
partnership of Govt of Maharashtra and Govt. Of Gujarat on 12th
February 2016.
•On 14th September 2017, Hon’ble Prime Minister of India, Shri
Narendra Modi and Hon’ble Prime Minister of Japan Shri Shinzo Abe
laid the foundation stone for first HSR project between Mumbai and
Ahmedabad.
•All out efforts are being made to complete the Project by 15th August
2022.
Sabarmati
Mumbai
Delhi
Sabarmati
Ahmedabad
Anand
Vadodara
Bharuch
Surat
Bilimora
Vapi
Boisar
Virar
Thane
Mumbai
Legend
Capital
Majorcities
* DNH: Dadra & Nagar Haveli
Gujarat
Maharashtra
Stations: 12 ( 8 in Gujarat
& 4 in Maharashtra)
All elevated except Mumbai
(underground)
Gujarat: 349.03 Km (8 districts)
DNH* : 4.30 Km (1 UT)
Maharashtra: 154.76 Km (3 districts)
Travel Time:
2.07 Hrs (limited Stops) 2.58 Hrs (all stops)
COST: 1,08000 CRORES
(including all escalation, Interest during Construction, taxes/duties)
Total Length: 508.09 Km
460.3 Km Viaducts (90.6%)
9.22 Km Bridges (1.8%)
25.87 Km Tunneling (5.1%)
(Longest Tunnel: 21 Km with 7 Km
undersea)
12.9 Km Cut/Fill (2.5%)
GAUGE: Standard 1435 mm
SPEED: 350 Km/h (design),
320 Km/h (operating)
GENERAL OVERVIEW OF PROJECT
SALIENT FEATURES: TECHNICAL
Project Component Description
Project Cost INR 1.08 Lakh Crores
Funding Agency JICA & MoR, and State
Governments (Maharashtra
and Gujarat)
Total Land Requirement 1415.75 Ha.
Total Length 508.17 km
Elevated Viaduct 469.53 km (9.22 kms Bridges)
Embankment (Cut/Fill) 12.9 Kms
Right of Way (ROW) 17.5 m
Tunnels 25.87 kms (8 Nos.)
Longest Tunnel 21 km (7.0 kms Undersea)
Tunnel Construction Technology TBM & NATM
Railway Crossings 25 locations
Maintenance Depots 7
Rolling Stock Depots 2 - Thane and Sabarmati.
Construction Yards At every 25 km
Track Gauge Standard (1,435 mm)
Maximum Design Speed 350 km/hr
Maximum Operation Speed 320 km/hr
Number of Lines Double Track
Distance between Track Centre 4.5 m
No
.
Stations Ch. (Km)
1 BKC,
Mumbai
0.000
2 Thane 27.950
3 Virar 65.170
4 Boisar 104.207
5 Vapi 167.940
6 Bilimora 216.580
7 Surat 264.580
8 Bharuch 323.110
9 Vadodara 397.060
10 Anand 447.380
11 Ahmedabad 500.190
12 Sabarmati 505.750
Travel Time :
2.07 Hrs (Limited Stops
2.58 Hrs (all stops)
• Reduction in travel time between Mumbai and Ahmedabad from 6.5
hrs to 2.5 hrs.
• High carrying capacity of about 750 passenger per train.
• Major connectivity boost to less developed areas, potential for
development of new production bases and townships along the
corridor.
• Boost to construction industry, technological enhancement of
Railways, long term infrastructure development.
• Creation of temporary and permanent employment.
• Decongestion of existing rail, road, and air traffic between Mumbai
and Ahmedabad
• Reduction in Green house gas emissions due to more efficient
transport option mode
Project Benefits
Key Alternatives chosen include:
• Route optimization and depot siting to avoid / minimize
environmentally and socially sensitive areas (such as forests and
mangroves, sanctuaries, hospitals, schools, densely populated
areas, etc.)
• Embankment option changed to Viaduct, thus substantially
reducing RoW and subsequent Land Acquisition requirement
• Elevated viaduct ensures continuity within spans, across the
alignment (LHS and RHS) without any physical severance for local
community as well as livestock
• Japanese Shinkansen technology chosen, which is one of the
most optimal among HSR, as regards noise emissions and energy
efficiency
Project Alternatives
SALIENT FEATURES: OPERATIONAL
TRAIN OPERATION PLAN (Source: Feasibility Study)
Year 2023 2033 2043 2053
Train Configuration 10 10/16 16 16
Number of Rakes 24 24 +11 44 71
Number of Trains
(per day/one-direction)
35 51 64 105
Train Capacity 750 750/1250 1250 1250
Traffic Volume (day/one direction) 17,900 31,700 56,800 92,900
Number of Trains
(per day/hour/one-direction)
Peak Hour: 3 4 6 8
Off peak: 2 3 3 6
Operational Control Centre: Sabarmati
Maintenance Depot/Workshop (Rolling Stock): Thane, Sabarmati 4
Inspection Light Maintenance Heavy Maintenance Others
(Period) Daily
(48 h)
Regular (30
days)
Bogie
(18 months)
General
(36 months)
Special &
Breakdown
Thane Depot √ √ √
Sabarmati Depot
& Workshop
√ √ √ √ √
• Power supply: 12 Traction substations, 2 Depot substations and 16
Distribution sub stations (12 Stations, 2 Depots & 2 Tunnel)
• OHE: 2X25 KV, Heavy Compound Catenary System
• Signalling: DS- ATC similar to Shinkansen
• Fitted with Disaster Prevention System for safe operation.
• State of the art High Speed Railway Training Institute at Vadodara
• Annual Energy requirements (Trains, Stations etc) -1100 million units 5
SALIENT FEATURES: MAINTENANCE
MAINTENANCE SCHEDULE
Shinkansen E7 Series JR East
X
Construction Methodology: Tunnel/ Via-duct Adopted
• Tunnel about 25-40 meters below ground
level,
• Elevated viaducts ensures continuity within
spans, across the alignment (LHS& RHS)
without any physical severance.
“THERE IS NO BIFURCATION OF
FOREST LAND”
Typical Cross Section in Tunnel & Via Duct
ALIGNMENT STUDY
•Minimum Radius (Horizontal): 6000m for 320 km/h
•Minimum Radius (Vertical): 25000m
•Over Head Clearance:7.7 m
•Maintainability of Asset
Technical
•Future Expansion to new area
•Connectivity with existing important places
•Development potential
Operational
•Location of station, River Bridges
•Minimum Disturbance to Forest & Wild Life
•Minimum Interference with existing structures i.e.
highway, metro, Location of Bridges
Obligatory
Points
Selecting 3
Most
Feasible
Options
ALIGNMENT OF
MAHASAMRIDHI
MARG
S.N. Alignment Alternative-1
(Tunnel)
Alternative -2
(Via Duct)
Alternative -3
(Along IR)
1 Proposed Terminal Bandra Kurla Complex
(Business Center)
Bandra Kurla Complex
(Business Center)
Lokmanya
Tilak (IR station)
2 Passenger
Connectivity
Connected With Metro
2B, Metro 3, Metro 8
(proposed), Airport
(Santacruz Chembur Link
Road)
Connected With
Metro 2B, Metro 8
(proposed), Airport
(Santacruz Chembur
Link Road)
Connected with
Lokmanya Tilak Station
of IR
3 Possibility of future
extension
Possible connection with
Pune, Nagpur
Possible connection
with Pune, Nagpur
Possible connection with
Pune, Nagpur
4 Development
Potential
Very High Due to
Integration with IFSC
Very High Due to
Integration with IFSC
Low, Since terminal is
heavily populated
Most Feasible Alignment: Operational Issues
S.
N.
Alignment Alternative-1
(Tunnel)
Alternative -2
(Via Duct)
Alternative -3
(Along IR)
1 Horizontal Curve Min 6000R Min 6000R Radius 1500 R
2 Vertical Curve 25000 m 25000 m 25000 m
3 Infringement with
Ex/ Pro Structure
Metro 5, Metro 4 Metro 2B, Metro 5, Metro 4,
Eastern Expressway, CSMT
Kalyan Line- 2 locations, Trans
Harbour 2 locations and other
flyovers
• 22 different
locations of Road
Over Bridges &
Foot Over Bridge
4 Speed Potential Speed Potential: 320
km/h
Speed Potential: 320 km/h Speed Potential: 110
km/h
Most Feasible Alignment: Technical Aspects
S.N. Alignment Alternative-1
(Tunnel)
Alternative -2
(Via Duct)
Alternative -3
(Along IR)
1 Wild Life Alignment Passes
through ESZ and PA of
TCFS, ESZ of SGNP &
TWLS. The alignment
also touches PA 0f TWLS
(0.11 Ha). The
construction is proposed
as under ground tunnel
in TCFS, thus minimal
impact on wild life.
Alignment Passes
through ESZ and PA of
TCFS, ESZ of SGNP &
TWLS. The alignment
also touches PA of
TWLS (0.11 Ha).
Alignment Passes
over existing
alignment of IR thus
completely avoiding
the TCFS.
2 Wildlife The alignment is along existing PWD road while passing through ESZ of
TWLS & SGNP.A wildlife overpass & underpass will also be provided, as
per suggestion of NBWL, to bridge lost connectivity of SGNP & TWLS.
3 Forest The alignment passes through Reserved Forest, Protected Forest, Private
Forest etc. at various locations.
Most Feasible Alignment: Obligatory Points
Finalization of Alignment
• A detailed study of 3 alternatives has been done
during feasibility study by dedicated team of
Engineers and Technicians of NHSRCL & Japanese
Consultants.
• Minimum use of forest land, minimal disturbance to
wild life and human habitation were considered.
FINALIZED
ALIGNMENT
Alt-2 & 3
(Viaduct/ IR)
Alt-1 (Tunnel)
MAHSR Alignment in Thane District – Ch: 7.043 to Ch: 46.700 (39.657 Km)
MAHSR Alignment in Palghar District – Ch:46.700 to CH:155.642 (108.942 Km)
Thanks….
36

More Related Content

PPTX
Restaurant management presentation
PPT
Arbitration and Conciliation Act 1996
PDF
Fidic contracts management introduction
PPSX
Hr and payroll
PPTX
Construction sequence for metro Project (Elevated and Underground) and Time c...
PPTX
Consumer learning
PDF
Scope Of Work PowerPoint Presentation Slides
PPTX
CITY INFRASTRUCTURE Nashik Maharastra, Leeds UK
Restaurant management presentation
Arbitration and Conciliation Act 1996
Fidic contracts management introduction
Hr and payroll
Construction sequence for metro Project (Elevated and Underground) and Time c...
Consumer learning
Scope Of Work PowerPoint Presentation Slides
CITY INFRASTRUCTURE Nashik Maharastra, Leeds UK

What's hot (20)

PPTX
Mumbai metro project Phase I
PPTX
Rail rapid transit system (india)
PDF
Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)
PPTX
Jaipur Metro Project
PDF
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
PPTX
Chennai metro rail
PPTX
Metro rail in india
PPTX
Ahmedabad Metro Project
DOCX
project report on water supply works under supervision of indian railways
PPT
O & d survey
PPTX
Trumpet interchange
DOCX
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
PDF
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
PPTX
Origin and destination survey
PDF
Level of Service(LOS) of a road with Calculation Method
PDF
Presentation on chenab bridge by Aamir Khan
PPT
Civil Engineering
PPTX
Summer Internship Presentation on "CONSTRUCTION OF PERMANENT CAMPUS FOR INDIA...
Mumbai metro project Phase I
Rail rapid transit system (india)
Capacity & Level of Service: Highways & Signalized Intersections (Indo-HCM)
Jaipur Metro Project
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
Chennai metro rail
Metro rail in india
Ahmedabad Metro Project
project report on water supply works under supervision of indian railways
O & d survey
Trumpet interchange
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
Origin and destination survey
Level of Service(LOS) of a road with Calculation Method
Presentation on chenab bridge by Aamir Khan
Civil Engineering
Summer Internship Presentation on "CONSTRUCTION OF PERMANENT CAMPUS FOR INDIA...
Ad

Similar to 428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx (20)

PPTX
Cantonment metro station a case study1 rajkumar
PPTX
Grievance redressal of Hubli railway station : A multistorey approach
PDF
Project brief updated_aug081
PPTX
Surat BRTS - Abhijit Lokre
PDF
Opportunities in Tunnelling in India 2025_Sample Slides.pdf
PPTX
INTELLIGENT TRANSPORTATION SYSTEMS
DOCX
Doubling progress report
PDF
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
PPTX
Metro project in inda
PDF
IRJET- Comparative Study of Effect of Varying Span Length on Major Elemen...
PDF
Metro elevated structures AR.pdf
PDF
Metro elevated structures AR.pdf
PDF
101024 Mafraq_Presentation_Javad_Akhtar
PDF
Railway Engineering by Sharda University
PPTX
Introduction to railway engineering (T.E 2)
PDF
varanasi ropeway and power point presentation
PDF
Transport poster
PDF
R.R.A.C.L-WB1.pdf
PPTX
Introduction to railway engineering
Cantonment metro station a case study1 rajkumar
Grievance redressal of Hubli railway station : A multistorey approach
Project brief updated_aug081
Surat BRTS - Abhijit Lokre
Opportunities in Tunnelling in India 2025_Sample Slides.pdf
INTELLIGENT TRANSPORTATION SYSTEMS
Doubling progress report
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
Metro project in inda
IRJET- Comparative Study of Effect of Varying Span Length on Major Elemen...
Metro elevated structures AR.pdf
Metro elevated structures AR.pdf
101024 Mafraq_Presentation_Javad_Akhtar
Railway Engineering by Sharda University
Introduction to railway engineering (T.E 2)
varanasi ropeway and power point presentation
Transport poster
R.R.A.C.L-WB1.pdf
Introduction to railway engineering
Ad

Recently uploaded (20)

PDF
UEFA_Embodied_Carbon_Emissions_Football_Infrastructure.pdf
PDF
Project_Mgmt_Institute_-Marc Marc Marc .pdf
PDF
IAE-V2500 Engine for Airbus Family 319/320
PPTX
MAD Unit - 3 User Interface and Data Management (Diploma IT)
PPTX
Environmental studies, Moudle 3-Environmental Pollution.pptx
PDF
Mechanics of materials week 2 rajeshwari
PDF
ASPEN PLUS USER GUIDE - PROCESS SIMULATIONS
PDF
Micro 3 New.ppt.pdf tools the laboratory the method
PPTX
AI-Reporting for Emerging Technologies(BS Computer Engineering)
PPTX
INTERNET OF THINGS - EMBEDDED SYSTEMS AND INTERNET OF THINGS
PPTX
SE unit 1.pptx aaahshdhajdviwhsiehebeiwheiebeiev
PDF
MLpara ingenieira CIVIL, meca Y AMBIENTAL
PPTX
Design ,Art Across Digital Realities and eXtended Reality
PPT
UNIT-I Machine Learning Essentials for 2nd years
PDF
IAE-V2500 Engine Airbus Family A319/320
PPTX
Unit IImachinemachinetoolopeartions.pptx
PPT
Programmable Logic Controller PLC and Industrial Automation
PPTX
Software-Development-Life-Cycle-SDLC.pptx
PDF
Micro 4 New.ppt.pdf a servay of cells and microorganism
PDF
AIGA 012_04 Cleaning of equipment for oxygen service_reformat Jan 12.pdf
UEFA_Embodied_Carbon_Emissions_Football_Infrastructure.pdf
Project_Mgmt_Institute_-Marc Marc Marc .pdf
IAE-V2500 Engine for Airbus Family 319/320
MAD Unit - 3 User Interface and Data Management (Diploma IT)
Environmental studies, Moudle 3-Environmental Pollution.pptx
Mechanics of materials week 2 rajeshwari
ASPEN PLUS USER GUIDE - PROCESS SIMULATIONS
Micro 3 New.ppt.pdf tools the laboratory the method
AI-Reporting for Emerging Technologies(BS Computer Engineering)
INTERNET OF THINGS - EMBEDDED SYSTEMS AND INTERNET OF THINGS
SE unit 1.pptx aaahshdhajdviwhsiehebeiwheiebeiev
MLpara ingenieira CIVIL, meca Y AMBIENTAL
Design ,Art Across Digital Realities and eXtended Reality
UNIT-I Machine Learning Essentials for 2nd years
IAE-V2500 Engine Airbus Family A319/320
Unit IImachinemachinetoolopeartions.pptx
Programmable Logic Controller PLC and Industrial Automation
Software-Development-Life-Cycle-SDLC.pptx
Micro 4 New.ppt.pdf a servay of cells and microorganism
AIGA 012_04 Cleaning of equipment for oxygen service_reformat Jan 12.pdf

428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx

  • 1. 1 Mumbai Ahmadabad High Speed Rail Project
  • 2. Rationale and Background •The growing transport needs of the country requires construction of High Speed Railway (HSR) in India. •Any Railway System having speed potential in excess of 200 kmph are considered as High Speed Railway. •The MAHSR project started in 2012 with initial discussions between Govt. of India and Govt. of Japan. Feasibility study undertaken by Japanese consultants in December 2013 and report submitted in July 2015. The project has been approved by Government of India vide CCEA/31/2015 dated. 09.12.2015
  • 3. Rationale and Background •National High Speed Rail Corporation (NHSRCL), A Special Purpose Vehicle under Ministry of Railways, Govt. of India was set up with partnership of Govt of Maharashtra and Govt. Of Gujarat on 12th February 2016. •On 14th September 2017, Hon’ble Prime Minister of India, Shri Narendra Modi and Hon’ble Prime Minister of Japan Shri Shinzo Abe laid the foundation stone for first HSR project between Mumbai and Ahmedabad. •All out efforts are being made to complete the Project by 15th August 2022.
  • 4. Sabarmati Mumbai Delhi Sabarmati Ahmedabad Anand Vadodara Bharuch Surat Bilimora Vapi Boisar Virar Thane Mumbai Legend Capital Majorcities * DNH: Dadra & Nagar Haveli Gujarat Maharashtra Stations: 12 ( 8 in Gujarat & 4 in Maharashtra) All elevated except Mumbai (underground) Gujarat: 349.03 Km (8 districts) DNH* : 4.30 Km (1 UT) Maharashtra: 154.76 Km (3 districts) Travel Time: 2.07 Hrs (limited Stops) 2.58 Hrs (all stops) COST: 1,08000 CRORES (including all escalation, Interest during Construction, taxes/duties) Total Length: 508.09 Km 460.3 Km Viaducts (90.6%) 9.22 Km Bridges (1.8%) 25.87 Km Tunneling (5.1%) (Longest Tunnel: 21 Km with 7 Km undersea) 12.9 Km Cut/Fill (2.5%) GAUGE: Standard 1435 mm SPEED: 350 Km/h (design), 320 Km/h (operating) GENERAL OVERVIEW OF PROJECT
  • 5. SALIENT FEATURES: TECHNICAL Project Component Description Project Cost INR 1.08 Lakh Crores Funding Agency JICA & MoR, and State Governments (Maharashtra and Gujarat) Total Land Requirement 1415.75 Ha. Total Length 508.17 km Elevated Viaduct 469.53 km (9.22 kms Bridges) Embankment (Cut/Fill) 12.9 Kms Right of Way (ROW) 17.5 m Tunnels 25.87 kms (8 Nos.) Longest Tunnel 21 km (7.0 kms Undersea) Tunnel Construction Technology TBM & NATM Railway Crossings 25 locations Maintenance Depots 7 Rolling Stock Depots 2 - Thane and Sabarmati. Construction Yards At every 25 km Track Gauge Standard (1,435 mm) Maximum Design Speed 350 km/hr Maximum Operation Speed 320 km/hr Number of Lines Double Track Distance between Track Centre 4.5 m No . Stations Ch. (Km) 1 BKC, Mumbai 0.000 2 Thane 27.950 3 Virar 65.170 4 Boisar 104.207 5 Vapi 167.940 6 Bilimora 216.580 7 Surat 264.580 8 Bharuch 323.110 9 Vadodara 397.060 10 Anand 447.380 11 Ahmedabad 500.190 12 Sabarmati 505.750 Travel Time : 2.07 Hrs (Limited Stops 2.58 Hrs (all stops)
  • 6. • Reduction in travel time between Mumbai and Ahmedabad from 6.5 hrs to 2.5 hrs. • High carrying capacity of about 750 passenger per train. • Major connectivity boost to less developed areas, potential for development of new production bases and townships along the corridor. • Boost to construction industry, technological enhancement of Railways, long term infrastructure development. • Creation of temporary and permanent employment. • Decongestion of existing rail, road, and air traffic between Mumbai and Ahmedabad • Reduction in Green house gas emissions due to more efficient transport option mode Project Benefits
  • 7. Key Alternatives chosen include: • Route optimization and depot siting to avoid / minimize environmentally and socially sensitive areas (such as forests and mangroves, sanctuaries, hospitals, schools, densely populated areas, etc.) • Embankment option changed to Viaduct, thus substantially reducing RoW and subsequent Land Acquisition requirement • Elevated viaduct ensures continuity within spans, across the alignment (LHS and RHS) without any physical severance for local community as well as livestock • Japanese Shinkansen technology chosen, which is one of the most optimal among HSR, as regards noise emissions and energy efficiency Project Alternatives
  • 8. SALIENT FEATURES: OPERATIONAL TRAIN OPERATION PLAN (Source: Feasibility Study) Year 2023 2033 2043 2053 Train Configuration 10 10/16 16 16 Number of Rakes 24 24 +11 44 71 Number of Trains (per day/one-direction) 35 51 64 105 Train Capacity 750 750/1250 1250 1250 Traffic Volume (day/one direction) 17,900 31,700 56,800 92,900 Number of Trains (per day/hour/one-direction) Peak Hour: 3 4 6 8 Off peak: 2 3 3 6 Operational Control Centre: Sabarmati Maintenance Depot/Workshop (Rolling Stock): Thane, Sabarmati 4
  • 9. Inspection Light Maintenance Heavy Maintenance Others (Period) Daily (48 h) Regular (30 days) Bogie (18 months) General (36 months) Special & Breakdown Thane Depot √ √ √ Sabarmati Depot & Workshop √ √ √ √ √ • Power supply: 12 Traction substations, 2 Depot substations and 16 Distribution sub stations (12 Stations, 2 Depots & 2 Tunnel) • OHE: 2X25 KV, Heavy Compound Catenary System • Signalling: DS- ATC similar to Shinkansen • Fitted with Disaster Prevention System for safe operation. • State of the art High Speed Railway Training Institute at Vadodara • Annual Energy requirements (Trains, Stations etc) -1100 million units 5 SALIENT FEATURES: MAINTENANCE MAINTENANCE SCHEDULE
  • 10. Shinkansen E7 Series JR East X Construction Methodology: Tunnel/ Via-duct Adopted • Tunnel about 25-40 meters below ground level, • Elevated viaducts ensures continuity within spans, across the alignment (LHS& RHS) without any physical severance. “THERE IS NO BIFURCATION OF FOREST LAND”
  • 11. Typical Cross Section in Tunnel & Via Duct
  • 12. ALIGNMENT STUDY •Minimum Radius (Horizontal): 6000m for 320 km/h •Minimum Radius (Vertical): 25000m •Over Head Clearance:7.7 m •Maintainability of Asset Technical •Future Expansion to new area •Connectivity with existing important places •Development potential Operational •Location of station, River Bridges •Minimum Disturbance to Forest & Wild Life •Minimum Interference with existing structures i.e. highway, metro, Location of Bridges Obligatory Points
  • 15. S.N. Alignment Alternative-1 (Tunnel) Alternative -2 (Via Duct) Alternative -3 (Along IR) 1 Proposed Terminal Bandra Kurla Complex (Business Center) Bandra Kurla Complex (Business Center) Lokmanya Tilak (IR station) 2 Passenger Connectivity Connected With Metro 2B, Metro 3, Metro 8 (proposed), Airport (Santacruz Chembur Link Road) Connected With Metro 2B, Metro 8 (proposed), Airport (Santacruz Chembur Link Road) Connected with Lokmanya Tilak Station of IR 3 Possibility of future extension Possible connection with Pune, Nagpur Possible connection with Pune, Nagpur Possible connection with Pune, Nagpur 4 Development Potential Very High Due to Integration with IFSC Very High Due to Integration with IFSC Low, Since terminal is heavily populated Most Feasible Alignment: Operational Issues
  • 16. S. N. Alignment Alternative-1 (Tunnel) Alternative -2 (Via Duct) Alternative -3 (Along IR) 1 Horizontal Curve Min 6000R Min 6000R Radius 1500 R 2 Vertical Curve 25000 m 25000 m 25000 m 3 Infringement with Ex/ Pro Structure Metro 5, Metro 4 Metro 2B, Metro 5, Metro 4, Eastern Expressway, CSMT Kalyan Line- 2 locations, Trans Harbour 2 locations and other flyovers • 22 different locations of Road Over Bridges & Foot Over Bridge 4 Speed Potential Speed Potential: 320 km/h Speed Potential: 320 km/h Speed Potential: 110 km/h Most Feasible Alignment: Technical Aspects
  • 17. S.N. Alignment Alternative-1 (Tunnel) Alternative -2 (Via Duct) Alternative -3 (Along IR) 1 Wild Life Alignment Passes through ESZ and PA of TCFS, ESZ of SGNP & TWLS. The alignment also touches PA 0f TWLS (0.11 Ha). The construction is proposed as under ground tunnel in TCFS, thus minimal impact on wild life. Alignment Passes through ESZ and PA of TCFS, ESZ of SGNP & TWLS. The alignment also touches PA of TWLS (0.11 Ha). Alignment Passes over existing alignment of IR thus completely avoiding the TCFS. 2 Wildlife The alignment is along existing PWD road while passing through ESZ of TWLS & SGNP.A wildlife overpass & underpass will also be provided, as per suggestion of NBWL, to bridge lost connectivity of SGNP & TWLS. 3 Forest The alignment passes through Reserved Forest, Protected Forest, Private Forest etc. at various locations. Most Feasible Alignment: Obligatory Points
  • 18. Finalization of Alignment • A detailed study of 3 alternatives has been done during feasibility study by dedicated team of Engineers and Technicians of NHSRCL & Japanese Consultants. • Minimum use of forest land, minimal disturbance to wild life and human habitation were considered.
  • 20. MAHSR Alignment in Thane District – Ch: 7.043 to Ch: 46.700 (39.657 Km)
  • 21. MAHSR Alignment in Palghar District – Ch:46.700 to CH:155.642 (108.942 Km)