SlideShare a Scribd company logo
which is enforceable by law to provide something in return for something
else from a second party". as stipulated in Article 864 of the Iraqi Civil Law.
A construction contract is an important document as it outlines the scope of
work, risks, duties and legal rights of both the contractor and the owner.
Civil engineering contracting contracts are administrative (governmental)
contracts governed by standard documents issued by the Iraqi Ministry of
Planning and internationally, the World Bank or FIDIC.
The two parties of contract are owners and one or more contractors. The
owner, often referred to as the 'employer' or the 'client', has full authority to
decide what type of contract should be used for a specific project to be
constructed and to set out the legally-binding terms and conditions in a
contractual agreement.
Essentials of a Valid Contract are:
1. There must be an agreement or meeting the minds
2. The agreement must be between parties competent to enter into a contract
3. The Parties must give free consent
4. The agreement must be supported by lawful consideration.
5. Subject matter must be definite and lawful
Contract types in construction:
There are many types of contracts that may be used in the construction
industry. Construction contracts are classified according to different aspects.
They may be classified according to the method of payment to the
total value of the contract can be calculated by multiplying identical units of
work by a fixed unit price.
4. Cost plus: are often used when the scope has not been clearly defined, such
as when the project design is still being finalized and the employer wants to
begin construction.
The most common cost-plus contracts are:
a. Cost plus fixed fee.
b. Cost plus fixed percentage contract.
c. Cost plus—with a guaranteed maximum price.
d. Cost plus variable percentage contract.
e. Target estimate contract.
5. Turnkey: The contractor being responsible for performing both design,
construction and project financing. Owner payment is then made at the
completion (when the contractor turns over the “key”). Partial payments may
be made in milestone such as certain arrival of machine, etc…
6. Project management contract: The Construction Management Contract is for
use on construction projects where the employer appoints separate
contracts
to carry out the works, and a construction manager to oversee the completion
of the works for a fee.
7. Public–Private Partnership (PPP): PPPs are a viable avenue for governments
to benefit from private capital and technical know-how.
8. Build-Operate-Transfer (BOT): The company is responsible for performing
the design, construction, long-term financing, and temporary operation
of the project. At the end of the operation period, which is usually more
than ten years, the operation of the project is transferred to the employer.
What is the Agreement?
contrary, the main elements of a contract are the agreement and its
enforceability by law.
2. Every agreement is not a contract, but every contract is an agreement.
3. An agreement does not need to be submitted in writing, but contracts are
usually written and recorded.
4. The Agreement does not legally obligate any party to perform. In a
contract,
people are legally obligated to fulfill their role.
5. The scope of an agreement is wider than a contract which is covers only
those agreement which have legal enforceability.
Contract contents:
It is customary in construction projects to have documents contained in the
contract in order for the owner to specify the scope of his work to the fullest
extent, and the contractor can study and analyze the project in order to be
able to accurately submit his proposal to implement the project. Figure The
contents of the contract can be described as follows:
It is a written agreement document between the two parties to the contract to
implement a specific engineering project, namely the employer (the
contracting party), usually symbolized in the construction contract by the
first party, and the implementing agency (the contractor) symbolized by the
second party. This contract (the agreement) governs and defines the
technical, financial and legal relationship between them throughout the
validity of the specified and clarified period in accordance with the terms of
the contract, which is composed of articles, clauses and conditions
specifying the type, scope and method of work, and the rights and duties of
all parties to the contract.
listed.
the contract and the
that are considered complementary to
project will not be implemented without
them, including, for example:
a) Work program and method of implementation.
b) Equipment and labor schedules.
It means the final formal agreement between
both the owner and the contractor, which is legally binding on
the two parties on the contents of the contract, including the
contractor’s approval to carry out the construction works in
return for sums of money paid by the owner, in
a certain manner and an agreed time based on the terms that
have been agreed
upon It is worth.
c) The full name of each of them.
d)The name of the witnesses to the contract, usually an official
body familiar with the legal aspects.
e) The name of the project to be implemented: giving an overview of
its
main contents.
d) The total time to implement the project, and its total cost.
c) The method of material dealing between the owner and the
contractor.
in easy-to-understand language.
The contract must contain the fines for delay in terms of how to deal
with them, the time of their implementation and their cost.
Standard Documents by planning ministry:
In the past, the general conditions for contracting civil engineering works
issued by the Ministry of Planning were the documents approved in
contracting for the implementation of projects. The Ministry of Planning
issued under its letter No. 7505 on 9/4/2017, which included not adopting
the general conditions of contracting in new contracts. The 18 standard
documents were issued, which are almost identical to the terms of FIDIC,
which is the International Federation of Consulting Engineers, which was
founded in 1913 and headquartered in Geneva in Switzerland, and this
abbreviation is taken from the French (Fédération Internationale Des
Ingénieurs-Conseils).
1. General Tenders for executing general works.
2. Limited Tenders for executing the general works
Works contracts are used for projects if all information (documents,
technical specifications, plans and bills of quantities) are available to the
employer.
3. General tenders for the contracts of designing and
executing general works.
4. limited general tenders for the contracts of designing and
executing general works.
Design and implementation contracts are used for
projects whose
information (documents, technical specifications, plans and bills of
quantities) are not available to the employer.
5. General tenders for the (Turnkey) contracts to execute public works.
1. Construction Contract - Red Book
2. Electromechanical Works Contract - Yellow Book
3. Industrial Works Contract - Orange Book
4. The Short Contract - The Green Book
5. B.O.T Contract - Silver Book
6. Consulting Services Contract - White Paper
The FIDIC Red, Yellow and Silver Books known as the FIDIC Rainbow
Suite.
The difference between public tender and
limited tender:
Public Tender:
It is from one stage that includes (announcing - opening -
analysis - awarding - signing a contract) and it contains the
qualification and evaluation criteria that the Bid Analysis
Committee is working on. Limited Tender: It’s from two stages;
The first stage is the qualification: according to the independent
standard
document (pre-qualification document) that includes
announcement - opening - analysis) and does not include awarding.
The second stage: Direct invitation to at least 6 qualified
companies, and the
analysis is carried out according to the limited tender document that
includes (invitation - opening - analysis - awarding - signing a contract).
increase in the contract sum, a written notice shall be given before he
proceeds to execute the work. If the contractor believes the additional cost is
involved for reasons including but not limited to:
1. A written interpretation from the engineer.
2. A written order for a change in the works issued by the engineer.
3. Force majeure.
5. Delays due to employer causes.
6. Design deficiency or incomplete design.
7. Delayed payments by the employer; Contractual breaches by the employer
and/or the engineer then a claim shall be submitted with full
substantiation of the relevant facts. The contractor’s claim shall include an
estimate of the costs and of probable effect of the delays to the
progress of the works.
Dispute RESOLUTION:
To prevent all disputes and litigation, it is usually agreed by the parties that
any claim, question, difficulty or dispute arising from the agreement in place
or the construction process shall be first submitted to the engineer to address
the issue. Upon review of the claim, the engineer shall take one or more
of the following preliminary actions within fourteen (14) days (or
similar as noted in the contract) of receipt of a claim:
1. Request additional supporting data from the claimant.
2. Submit a schedule to the parties indicating when the engineer expects to act.
3. Reject the claim in whole or in part stating the reasons for rejection.
4. Recommend approval of the. claim by the other party; or
5. Suggest a compromise.
If a claim has not been resolved within a specified period in the
the following methods approved in the provisions of the contract:
Mediation is a method of conflict resolution that, in fact, contains elements
of negotiation and arbitration. The mediator is usually a third party who tries
to persuade the parties to the dispute to agree to resolve the dispute in a way
that works for everyone. Accordingly, the mediator must have high
negotiation skill, as well as full knowledge of technical issues related to
construction project disputes. Usually, the parties to the dispute agree to
resolve their differences by following the method of mediation, provided
that an agreed mediator is chosen by both parties. If the disputed issue
cannot be resolved in mediation, they went to arbitration or courts as the
What are the procedures followed for arbitration?
Arbitration procedures differ from one country to another, but
most of them agree on the basics, which are:
Termination of the contract and withdrawal of the
project:
Termination of the contract means its cancellation before the expiry of the
time period specified in the contract documents. Most construction contracts
include a clause that the project owner has the right to withdraw works from
the contractor, terminate the contract, and in some cases confiscate the
insurance, for the following main reasons:
1. In the event of the contractor’s bankruptcy, submitting an application to
declare his bankruptcy, or having been financially insolvent.
2. If he delays in executing one of the phases of the project’s clauses in
accordance with the approved time schedule with a period of time
that is stipulated in the terms of the contract.
3. If the contractor breaches any of the terms of the contract, neglects his
obligations stipulated in the contract, or suspends implementation work for
a period of time stipulated in the contract.
4. The contractor assigning part of the work items to another contractor in
violation of the instructions of the owner or his representative in this
regard.
5. If it is proven to the owner that the contractor is using fraud, manipulation or
bribery.
work, in accordance with the terms contained in the contract. The contractual
relationship does not end with the withdrawal of the work from the
contractor. When the contract is terminated at the request of the owner alone,
the contractor should be compensated for the missed profit such as if he was
work was completed in full but the court can reduce the compensation owed
to the contractor upon termination of the contract by the amount of the
remaining time.
Employers have generally more extensive termination rights. The
employer may, without cause, order the contractor in writing to
suspend, delay, or interrupt the works in whole or in part for such
period of time as the employer may determine.
Contractors generally have relatively limited termination rights in
construction contracts. Contractors are typically entitled to terminate a
contract in the following specific events:
• Failure by the employer to pay the cost of work
• The employer has breached the financial agreements
• Employer fraud to prolong suspend work
• Employer insolvency
contract can be discharged where:
1. The contract is valid, or comes to an end because it has been carried out.
2. Contractor death
3. Announcement of bankruptcy of the employer
4. Expiry by agreement
5. Impossibility to implement
6. The majeure forces
7. Termination of the contract (judicial ruling)
1. The inability of the owner to finance the project partially or completely.
2. Owner desire to make modifications, additions or changes to the project.
3. Inability of the contractor to implement the work items at the required rate of
time in project scheduling.
4. Contractor's bankruptcy.
5. The contractor's failure to comply with the orders issued by the owner or his
representative to the directives relating to the progress of the project,
6. Stopping as a result of natural disasters or bad weather conditions.
If the suspension out of the will of the parties, the contractor has the request
right to extend the contract by the amount suspended time but not additional
sums.
Changes in engineering projects can be defined as: Making developments in
the contract documents, with a written agreement between the
contractor and the owner, these developments may be modifications,
additions, or alterations to the project clauses specified in the contract.
Conditions for change in construction projects:
1.The owner has the right to make changes in the project in the interest of the
general objective of the contract.
2.The contractor must be making the required changes.
3.The change must be in writing and signed by the owner.
Any modification in the value or time of the contract of the contract will be
evaluated by appropriate means.
1. Extent of the need for change and the consequences thereof.
2. What is the time period required for the change, and the extent of its impact
on the general plan of the project?
3. The capabilities of the contractor to make this change without affecting the
rest of the project items.
4. The feasibility study for changes in the project, and does the project budget
allow for the change to be made or not?

More Related Content

PPTX
Chapter two.pptx
PPT
LEC - 1.ppt most important lecture note and best
 
PPT
Awareness PPT - Fidic_slide_s_show 2015.ppt
PPTX
PROJECT CONTRACTS.pptx
PDF
Contract and Types of Contract
DOC
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
PPTX
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
Chapter two.pptx
LEC - 1.ppt most important lecture note and best
 
Awareness PPT - Fidic_slide_s_show 2015.ppt
PROJECT CONTRACTS.pptx
Contract and Types of Contract
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
CONTRACT ADMINISTRATION- Presentation dated 22.11.16

Similar to 4GOVEaasdfgggtkfwseyRNMENT CONTRACTS33.pptx (20)

PDF
Cost estimates & contract documents ce224 pdf
PPTX
Contracts and their types
PPTX
Claim Management in Construction Projects
PDF
Pai 3-03
PDF
CE-CONTRACTS-REPORT.pdf
PDF
Additional Information in midterm CPE024 (1).pdf
PDF
Contractual Steps for Smooth Delivery of Infrastructure Projects
DOC
17 10 16
DOCX
07 cl-assignment-syafiq-qy-macy-huiyong-deric
PPTX
05 Contract Management.pptx . DEFINITION
PPTX
GROUP 6 - FIDIC Conditions of Contract.pptx
PPTX
Types of contracts
PPTX
unit-03 C & thokohyffsetuioxgbkvhjgevA.pptx
PPTX
unit-03 C & thokohyffsetuioxgbkvhjgevA.pptx
PPTX
Construction practices
DOCX
Civil construction draft contarct document
PDF
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
PDF
contract Management cchapter 1-6 of fourth year
PDF
PPTX
¹𝐋𝐞𝐜𝐭 1-2.pptx
Cost estimates & contract documents ce224 pdf
Contracts and their types
Claim Management in Construction Projects
Pai 3-03
CE-CONTRACTS-REPORT.pdf
Additional Information in midterm CPE024 (1).pdf
Contractual Steps for Smooth Delivery of Infrastructure Projects
17 10 16
07 cl-assignment-syafiq-qy-macy-huiyong-deric
05 Contract Management.pptx . DEFINITION
GROUP 6 - FIDIC Conditions of Contract.pptx
Types of contracts
unit-03 C & thokohyffsetuioxgbkvhjgevA.pptx
unit-03 C & thokohyffsetuioxgbkvhjgevA.pptx
Construction practices
Civil construction draft contarct document
AN EXAMPLE OF HOW PREPARING A CLAIM STEP BY STEP.pdf
contract Management cchapter 1-6 of fourth year
¹𝐋𝐞𝐜𝐭 1-2.pptx
Ad

More from zaid519176 (20)

PPTX
Risk in Infrastructure Projectsaaaaa212.pptx
PPTX
Safety and Health in Infrastructure Project11.pptx
PPTX
Appraisal and Selection of Projects6522622.pptx
PPTX
Appraisal and Selection of Projects.pptx
PDF
4_pure_vxsvxxcvcxvcxgynhmjkffbending.pdf
PDF
1 Research Methodology An Introduction (1).pdf
PPTX
lec 3 airpodsfsfergfgfgddfsst.en.ar.pptx
PPTX
Lec2 Airportfhfgyfgdyudhsmsdisdsidsi.pptx
PPTX
GIS - HGYRYGHDDGDDGDDGGGYasmin Aziz.pptx
PPTX
lastt2PARAFRAZINGZASDDFEDAZCDDSDFFS.pptx
PPTX
airport classificationjudhjdjhdfjfd.pptx
PPTX
Railwayof hfd hgft hgtyb mjgtfd hgft.pptx
PPT
Runway capachg hvfy hgfbh hft6 gfity (1).ppt
PPTX
Muntadher abdulmalik & Mustafa methaq.pptx
PPTX
Ali Adnan شال ال بللريتا الAbid سثمخي.pptx
PPT
بخق شهق ةثشق سثشق الغ فخ حخقف ابقبسي.ppt
PPT
AIR REAL SDSDS HFT FOR NFJ SEDFEFXSAL.ppt
PDF
goodfif of the hams and lanch hfudtgd kfjgiy
PPT
07 Open Channels.ppt
PPT
Hoover Dam.ppt
Risk in Infrastructure Projectsaaaaa212.pptx
Safety and Health in Infrastructure Project11.pptx
Appraisal and Selection of Projects6522622.pptx
Appraisal and Selection of Projects.pptx
4_pure_vxsvxxcvcxvcxgynhmjkffbending.pdf
1 Research Methodology An Introduction (1).pdf
lec 3 airpodsfsfergfgfgddfsst.en.ar.pptx
Lec2 Airportfhfgyfgdyudhsmsdisdsidsi.pptx
GIS - HGYRYGHDDGDDGDDGGGYasmin Aziz.pptx
lastt2PARAFRAZINGZASDDFEDAZCDDSDFFS.pptx
airport classificationjudhjdjhdfjfd.pptx
Railwayof hfd hgft hgtyb mjgtfd hgft.pptx
Runway capachg hvfy hgfbh hft6 gfity (1).ppt
Muntadher abdulmalik & Mustafa methaq.pptx
Ali Adnan شال ال بللريتا الAbid سثمخي.pptx
بخق شهق ةثشق سثشق الغ فخ حخقف ابقبسي.ppt
AIR REAL SDSDS HFT FOR NFJ SEDFEFXSAL.ppt
goodfif of the hams and lanch hfudtgd kfjgiy
07 Open Channels.ppt
Hoover Dam.ppt
Ad

Recently uploaded (20)

PDF
SCB EIC expects CLMV outlook to face diverging risks amid global trade headwinds
PDF
caregiving tools.pdf...........................
PPTX
Penn毕业证如何办理:宾夕法尼亚大学Offer定制学历毕业证Penn成绩单
PPTX
Consumer-healtsusususususjjsjsjsjsjsjsjsjs
PPTX
Globalization-of-Religion. Contemporary World
PDF
ADVANCE TAX Reduction using traditional insurance
PDF
Dr Tran Quoc Bao the first Vietnamese speaker at GITEX DigiHealth Conference ...
PDF
Electricity Privatisation vs. Just Energy Transition in South Africa: A Criti...
PPT
geometric-modelingEast Coast of Kamchatka, 8.7M · 30 Jul 2025 08:52:50, Publi...
PDF
Mathematical Economics 23lec03slides.pdf
PDF
A Brief Introduction About Greg Kutzin
PPTX
HDFC Retirement Plans.pptx hdfc retirement
PDF
Melcom Copeland_Decentralized Mobile Lending Platform for Kenya (2018)
PPTX
fastest_growing_sectors_in_india_2025.pptx
PDF
Exploring Financial Services....................................................
PPTX
How to Prepare Your Pharmacy for Financial Year‑End.pptx
PDF
The Power and Future of Research Collaboration
PDF
Melcom Copeland_Ripple_XRPL_First Ledger_Case Study (2024).pdf
PPTX
UNDERSTANDING Special drawing rights. ppt
PDF
Black White Vintage Classic Music Presentation.pdf
SCB EIC expects CLMV outlook to face diverging risks amid global trade headwinds
caregiving tools.pdf...........................
Penn毕业证如何办理:宾夕法尼亚大学Offer定制学历毕业证Penn成绩单
Consumer-healtsusususususjjsjsjsjsjsjsjsjs
Globalization-of-Religion. Contemporary World
ADVANCE TAX Reduction using traditional insurance
Dr Tran Quoc Bao the first Vietnamese speaker at GITEX DigiHealth Conference ...
Electricity Privatisation vs. Just Energy Transition in South Africa: A Criti...
geometric-modelingEast Coast of Kamchatka, 8.7M · 30 Jul 2025 08:52:50, Publi...
Mathematical Economics 23lec03slides.pdf
A Brief Introduction About Greg Kutzin
HDFC Retirement Plans.pptx hdfc retirement
Melcom Copeland_Decentralized Mobile Lending Platform for Kenya (2018)
fastest_growing_sectors_in_india_2025.pptx
Exploring Financial Services....................................................
How to Prepare Your Pharmacy for Financial Year‑End.pptx
The Power and Future of Research Collaboration
Melcom Copeland_Ripple_XRPL_First Ledger_Case Study (2024).pdf
UNDERSTANDING Special drawing rights. ppt
Black White Vintage Classic Music Presentation.pdf

4GOVEaasdfgggtkfwseyRNMENT CONTRACTS33.pptx

  • 1. which is enforceable by law to provide something in return for something else from a second party". as stipulated in Article 864 of the Iraqi Civil Law. A construction contract is an important document as it outlines the scope of work, risks, duties and legal rights of both the contractor and the owner. Civil engineering contracting contracts are administrative (governmental) contracts governed by standard documents issued by the Iraqi Ministry of Planning and internationally, the World Bank or FIDIC. The two parties of contract are owners and one or more contractors. The owner, often referred to as the 'employer' or the 'client', has full authority to decide what type of contract should be used for a specific project to be constructed and to set out the legally-binding terms and conditions in a contractual agreement. Essentials of a Valid Contract are: 1. There must be an agreement or meeting the minds 2. The agreement must be between parties competent to enter into a contract 3. The Parties must give free consent 4. The agreement must be supported by lawful consideration. 5. Subject matter must be definite and lawful Contract types in construction: There are many types of contracts that may be used in the construction industry. Construction contracts are classified according to different aspects. They may be classified according to the method of payment to the
  • 2. total value of the contract can be calculated by multiplying identical units of work by a fixed unit price. 4. Cost plus: are often used when the scope has not been clearly defined, such as when the project design is still being finalized and the employer wants to begin construction. The most common cost-plus contracts are: a. Cost plus fixed fee. b. Cost plus fixed percentage contract. c. Cost plus—with a guaranteed maximum price. d. Cost plus variable percentage contract. e. Target estimate contract. 5. Turnkey: The contractor being responsible for performing both design, construction and project financing. Owner payment is then made at the completion (when the contractor turns over the “key”). Partial payments may be made in milestone such as certain arrival of machine, etc… 6. Project management contract: The Construction Management Contract is for use on construction projects where the employer appoints separate contracts to carry out the works, and a construction manager to oversee the completion of the works for a fee. 7. Public–Private Partnership (PPP): PPPs are a viable avenue for governments to benefit from private capital and technical know-how. 8. Build-Operate-Transfer (BOT): The company is responsible for performing the design, construction, long-term financing, and temporary operation of the project. At the end of the operation period, which is usually more than ten years, the operation of the project is transferred to the employer. What is the Agreement?
  • 3. contrary, the main elements of a contract are the agreement and its enforceability by law. 2. Every agreement is not a contract, but every contract is an agreement. 3. An agreement does not need to be submitted in writing, but contracts are usually written and recorded. 4. The Agreement does not legally obligate any party to perform. In a contract, people are legally obligated to fulfill their role. 5. The scope of an agreement is wider than a contract which is covers only those agreement which have legal enforceability. Contract contents: It is customary in construction projects to have documents contained in the contract in order for the owner to specify the scope of his work to the fullest extent, and the contractor can study and analyze the project in order to be able to accurately submit his proposal to implement the project. Figure The contents of the contract can be described as follows: It is a written agreement document between the two parties to the contract to implement a specific engineering project, namely the employer (the contracting party), usually symbolized in the construction contract by the first party, and the implementing agency (the contractor) symbolized by the second party. This contract (the agreement) governs and defines the technical, financial and legal relationship between them throughout the validity of the specified and clarified period in accordance with the terms of the contract, which is composed of articles, clauses and conditions specifying the type, scope and method of work, and the rights and duties of all parties to the contract.
  • 4. listed. the contract and the that are considered complementary to project will not be implemented without them, including, for example: a) Work program and method of implementation. b) Equipment and labor schedules. It means the final formal agreement between both the owner and the contractor, which is legally binding on the two parties on the contents of the contract, including the contractor’s approval to carry out the construction works in return for sums of money paid by the owner, in a certain manner and an agreed time based on the terms that have been agreed upon It is worth. c) The full name of each of them. d)The name of the witnesses to the contract, usually an official body familiar with the legal aspects. e) The name of the project to be implemented: giving an overview of its main contents. d) The total time to implement the project, and its total cost. c) The method of material dealing between the owner and the contractor.
  • 5. in easy-to-understand language. The contract must contain the fines for delay in terms of how to deal with them, the time of their implementation and their cost. Standard Documents by planning ministry: In the past, the general conditions for contracting civil engineering works issued by the Ministry of Planning were the documents approved in contracting for the implementation of projects. The Ministry of Planning issued under its letter No. 7505 on 9/4/2017, which included not adopting the general conditions of contracting in new contracts. The 18 standard documents were issued, which are almost identical to the terms of FIDIC, which is the International Federation of Consulting Engineers, which was founded in 1913 and headquartered in Geneva in Switzerland, and this abbreviation is taken from the French (Fédération Internationale Des Ingénieurs-Conseils). 1. General Tenders for executing general works. 2. Limited Tenders for executing the general works Works contracts are used for projects if all information (documents, technical specifications, plans and bills of quantities) are available to the employer. 3. General tenders for the contracts of designing and executing general works. 4. limited general tenders for the contracts of designing and executing general works. Design and implementation contracts are used for projects whose information (documents, technical specifications, plans and bills of quantities) are not available to the employer. 5. General tenders for the (Turnkey) contracts to execute public works.
  • 6. 1. Construction Contract - Red Book 2. Electromechanical Works Contract - Yellow Book 3. Industrial Works Contract - Orange Book 4. The Short Contract - The Green Book 5. B.O.T Contract - Silver Book 6. Consulting Services Contract - White Paper The FIDIC Red, Yellow and Silver Books known as the FIDIC Rainbow Suite. The difference between public tender and limited tender: Public Tender: It is from one stage that includes (announcing - opening - analysis - awarding - signing a contract) and it contains the qualification and evaluation criteria that the Bid Analysis Committee is working on. Limited Tender: It’s from two stages; The first stage is the qualification: according to the independent standard document (pre-qualification document) that includes announcement - opening - analysis) and does not include awarding. The second stage: Direct invitation to at least 6 qualified companies, and the analysis is carried out according to the limited tender document that includes (invitation - opening - analysis - awarding - signing a contract).
  • 7. increase in the contract sum, a written notice shall be given before he proceeds to execute the work. If the contractor believes the additional cost is involved for reasons including but not limited to: 1. A written interpretation from the engineer. 2. A written order for a change in the works issued by the engineer. 3. Force majeure. 5. Delays due to employer causes. 6. Design deficiency or incomplete design. 7. Delayed payments by the employer; Contractual breaches by the employer and/or the engineer then a claim shall be submitted with full substantiation of the relevant facts. The contractor’s claim shall include an estimate of the costs and of probable effect of the delays to the progress of the works. Dispute RESOLUTION: To prevent all disputes and litigation, it is usually agreed by the parties that any claim, question, difficulty or dispute arising from the agreement in place or the construction process shall be first submitted to the engineer to address the issue. Upon review of the claim, the engineer shall take one or more of the following preliminary actions within fourteen (14) days (or similar as noted in the contract) of receipt of a claim: 1. Request additional supporting data from the claimant. 2. Submit a schedule to the parties indicating when the engineer expects to act. 3. Reject the claim in whole or in part stating the reasons for rejection. 4. Recommend approval of the. claim by the other party; or 5. Suggest a compromise. If a claim has not been resolved within a specified period in the
  • 8. the following methods approved in the provisions of the contract: Mediation is a method of conflict resolution that, in fact, contains elements of negotiation and arbitration. The mediator is usually a third party who tries to persuade the parties to the dispute to agree to resolve the dispute in a way that works for everyone. Accordingly, the mediator must have high negotiation skill, as well as full knowledge of technical issues related to construction project disputes. Usually, the parties to the dispute agree to resolve their differences by following the method of mediation, provided that an agreed mediator is chosen by both parties. If the disputed issue cannot be resolved in mediation, they went to arbitration or courts as the
  • 9. What are the procedures followed for arbitration? Arbitration procedures differ from one country to another, but most of them agree on the basics, which are: Termination of the contract and withdrawal of the project: Termination of the contract means its cancellation before the expiry of the time period specified in the contract documents. Most construction contracts include a clause that the project owner has the right to withdraw works from the contractor, terminate the contract, and in some cases confiscate the insurance, for the following main reasons: 1. In the event of the contractor’s bankruptcy, submitting an application to declare his bankruptcy, or having been financially insolvent. 2. If he delays in executing one of the phases of the project’s clauses in accordance with the approved time schedule with a period of time that is stipulated in the terms of the contract. 3. If the contractor breaches any of the terms of the contract, neglects his obligations stipulated in the contract, or suspends implementation work for a period of time stipulated in the contract. 4. The contractor assigning part of the work items to another contractor in violation of the instructions of the owner or his representative in this regard. 5. If it is proven to the owner that the contractor is using fraud, manipulation or bribery.
  • 10. work, in accordance with the terms contained in the contract. The contractual relationship does not end with the withdrawal of the work from the contractor. When the contract is terminated at the request of the owner alone, the contractor should be compensated for the missed profit such as if he was work was completed in full but the court can reduce the compensation owed to the contractor upon termination of the contract by the amount of the remaining time. Employers have generally more extensive termination rights. The employer may, without cause, order the contractor in writing to suspend, delay, or interrupt the works in whole or in part for such period of time as the employer may determine. Contractors generally have relatively limited termination rights in construction contracts. Contractors are typically entitled to terminate a contract in the following specific events: • Failure by the employer to pay the cost of work • The employer has breached the financial agreements • Employer fraud to prolong suspend work • Employer insolvency contract can be discharged where: 1. The contract is valid, or comes to an end because it has been carried out. 2. Contractor death 3. Announcement of bankruptcy of the employer 4. Expiry by agreement 5. Impossibility to implement 6. The majeure forces 7. Termination of the contract (judicial ruling)
  • 11. 1. The inability of the owner to finance the project partially or completely. 2. Owner desire to make modifications, additions or changes to the project. 3. Inability of the contractor to implement the work items at the required rate of time in project scheduling. 4. Contractor's bankruptcy. 5. The contractor's failure to comply with the orders issued by the owner or his representative to the directives relating to the progress of the project, 6. Stopping as a result of natural disasters or bad weather conditions. If the suspension out of the will of the parties, the contractor has the request right to extend the contract by the amount suspended time but not additional sums. Changes in engineering projects can be defined as: Making developments in the contract documents, with a written agreement between the contractor and the owner, these developments may be modifications, additions, or alterations to the project clauses specified in the contract. Conditions for change in construction projects: 1.The owner has the right to make changes in the project in the interest of the general objective of the contract. 2.The contractor must be making the required changes. 3.The change must be in writing and signed by the owner. Any modification in the value or time of the contract of the contract will be evaluated by appropriate means.
  • 12. 1. Extent of the need for change and the consequences thereof. 2. What is the time period required for the change, and the extent of its impact on the general plan of the project? 3. The capabilities of the contractor to make this change without affecting the rest of the project items. 4. The feasibility study for changes in the project, and does the project budget allow for the change to be made or not?