Project Quality Management
Sections of this presentation were adapted from A Guide to the Project
Management Body of Knowledge 5th Edition, Project Management Institute
Inc., © 2013
Project Quality Management
 Project quality management includes the process required
to ensure that the project satisfies the needs for which it is
undertaken.
 PQM includes all the activities of the overall
management function that determine the quality policy,
objectives, and responsibilities and implement them
within the quality system.
Why Quality Management?
 Quality means conformance to specifications and fitness
for use – i.e. just what you need and not more
 Projects or products with unnecessary features can be
too expensive to meet the business need
 Prevention is much cheaper than inspection, build
quality in early to minimize costs/maximize quality
How to Manage Quality?Three processes
• Plan Quality
– What is quality and how will we ensure it?
• Perform Quality Assurance
– Are we following the quality standards?
• Perform Quality Control
– Are we meeting the quality standards?
Perform
Quality
Assurance
Perform
Quality
Control
Plan
Quality
How to Manage Quality?
 These processes interact with each other as well as with the
processes of other knowledge areas
 Each process involves an effort of one or more individual or
group of individuals based on the need of the project.
 Each process occurs at least once in every project phase during
the project life cycle
Perform
Quality
Assurance
Perform
Quality
Control
Plan
Quality
Plan Quality Management
 Cost-benefit analysis
 Cost of quality
 Seven basic quality tools
 Benchmarking
 Design of experiments
 Statistical sampling
 Additional quality planning
tools
 Meetings
Tools & TechniquesProject management
plan
Stakeholder register
Risk register
Requirements
documentation
Enterprise
environmental
factors
Organizational process
assets
Quality management
plan
Process improvement
plan
Quality metrics
Quality checklists
Project documents
updates
Inputs
Outputs
Perform
Quality
Assurance
Perform
Quality
Control
Plan
Quality
Plan Quality Management
Cost of Quality – Evaluating the
cost of conformance with the
cost of nonconformance to reach
a balance. Includes;
• Prevention Costs
• Appraisal Costs
• Failure Costs
Cost of
Conformance
Cost of Non
Conformance
Quality training Rework
Studies Scrap
Surveys Inventory Costs
Warranty Costs
Deming’s Costs of Quality
“85% of the costs of quality are the direct responsibility of management "- William
Edwards Deming
Plan Quality Management
PMBOOK 2013
Cost of Quality – Evaluating the cost of conformance with
the cost of nonconformance to reach a balance.
Quality Planning Terms
Gold Plating – Giving the customer extras that do
not add value to the project
Marginal Analysis – The point where the
incremental revenue from an improvement equals
the cost to implement it
Kaizen – Continuous improvement process to
reduce costs and promote consistency
ISO 9000 – International standard to ensure that
companies have quality procedures and that they
follow them
Perform Quality Assurance
 Quality management and
control tools
 Quality audits
 Process analysis
Tools & Techniques
Change requests
Project management
plan
updates
Project documents
updates
Organizational
process assets
updates
Quality management
plan
Process improvement
plan
Quality metrics
Quality control
measurements
Project documents
Inputs
Outputs
Perform
Quality
Assurance
Perform
Quality
Control
Plan
Quality
Statistics Terms Review
 Mutually Exclusive – Two
events that cannot both occur
in a single trial
 Statistical Independence –
Probability of one event
occurring does not affect the
probability of another event
occurring
 Probability – The likelihood
that something will occur
(usually expressed in percent)
Perform Quality Control
 Seven basic quality tools
 Statistical sampling
 Inspection
 Approved change requests
review
Tools & Techniques
Quality Control
Measurements
Validated Deliverables
Validated Changes
Change Requests
Project Management
Plan Updates
Work performance
information
Project Document
Updates
Project management plan
Quality metrics
Quality checklists
Work performance data
Approved change requests
Deliverables
Project documents
Organizational process assets
Inputs
Outputs
Perform
Quality
Assurance
Perform
Quality
Control
Plan
Quality
Pareto Principle/ Chart
Graph of problem type vs. frequency
80/20 Rule – a theory maintaining that 80% of the output in
a given situation or system is produced by 20% of the input.
Problem Type
Frequency
CumulativePercentage
www.techtarget.com/
Control Chart
 Upper & Lower Control Limits (UCL & LCL)
• Set by quality goal i.e. 3s
• Includes the normal and expected variation in the process
 Specification Limits
• Contracted acceptable limit, usually outside UCL & LCL
 Out of Control
A process is considered out of control when:
1. a data point exceeds a control limit;
2. seven consecutive plot points are above the mean;
3. seven consecutive plot points are below the mean.
 Assignable Change
• When the controller adjusts the process to bring the process back within process
control limits
Control Charts
Out of control point indicates unsuall process - activity

More Related Content

PDF
Project quality management
Mohammad Ashraf Khan, PMP
 
PPTX
Project quality management
Mohammad Ashraf Khan, PMP
 
PPTX
Project Quality Management - PMBOK6
Agus Suhanto
 
PPT
Project Quality Management powerpoint
DjamadaMuhamedKAGUSU
 
PDF
PMP Chap 8 - Project Quality Management
Anand Bobade
 
PPTX
Project Quality Management
GiO Friginal
 
PDF
Project quality management - PMI PMBOK Knowledge Area
Imran Jamil
 
PPT
Episode 24 : Project Quality Management
SAJJAD KHUDHUR ABBAS
 
Project quality management
Mohammad Ashraf Khan, PMP
 
Project quality management
Mohammad Ashraf Khan, PMP
 
Project Quality Management - PMBOK6
Agus Suhanto
 
Project Quality Management powerpoint
DjamadaMuhamedKAGUSU
 
PMP Chap 8 - Project Quality Management
Anand Bobade
 
Project Quality Management
GiO Friginal
 
Project quality management - PMI PMBOK Knowledge Area
Imran Jamil
 
Episode 24 : Project Quality Management
SAJJAD KHUDHUR ABBAS
 

What's hot (20)

PPTX
An Introduction to Project Management
Krishna Kant
 
PPTX
PMP Training - 08 project quality management
ejlp12
 
PPT
Introduce Project Management
guest90bddb
 
PPT
10. Project Quality Management
BhuWan Khadka
 
PPTX
Project life cycle
Maryam Juma
 
PDF
Project quality management.ppt msm
Development Associates Link International (DALI) Inc
 
PPTX
Project quality management (1)
CQU
 
PDF
Project Quality Management - PMBOK
Arief Rahmana
 
PDF
Project Quality Management | Project Quality Control | Edureka
Edureka!
 
PPTX
Quality management
vishal patel
 
PPTX
Introduction to Project Management (workshop) - v.1
Mena M. Eissa
 
PPTX
Project Quality Management
Martin Sillaots
 
PDF
Project planning and scheduling
adeel hamid
 
PPTX
8.0 Project Quality Management Overview
DavidMcLachlan1
 
PPTX
Project Quality Control
Sheetal Narkar
 
PDF
PMP Lecture 4: Project Integration Management
Mohamed Loey
 
PPSX
Project Management Fundamentals
OxfordCambridge
 
PPTX
Project Management Framework
Wadhwani Foundation
 
PDF
PMP Chap 5 - Project Scope Management - Part 2
Anand Bobade
 
PPTX
Project management process and Project Management Knowledge areas
Mazen Zbib
 
An Introduction to Project Management
Krishna Kant
 
PMP Training - 08 project quality management
ejlp12
 
Introduce Project Management
guest90bddb
 
10. Project Quality Management
BhuWan Khadka
 
Project life cycle
Maryam Juma
 
Project quality management.ppt msm
Development Associates Link International (DALI) Inc
 
Project quality management (1)
CQU
 
Project Quality Management - PMBOK
Arief Rahmana
 
Project Quality Management | Project Quality Control | Edureka
Edureka!
 
Quality management
vishal patel
 
Introduction to Project Management (workshop) - v.1
Mena M. Eissa
 
Project Quality Management
Martin Sillaots
 
Project planning and scheduling
adeel hamid
 
8.0 Project Quality Management Overview
DavidMcLachlan1
 
Project Quality Control
Sheetal Narkar
 
PMP Lecture 4: Project Integration Management
Mohamed Loey
 
Project Management Fundamentals
OxfordCambridge
 
Project Management Framework
Wadhwani Foundation
 
PMP Chap 5 - Project Scope Management - Part 2
Anand Bobade
 
Project management process and Project Management Knowledge areas
Mazen Zbib
 
Ad

Viewers also liked (20)

PDF
PMP_Project Quality Management
Hisham Haridy MBA, PMP®, RMP®, SP®
 
PPTX
Construction quality management plan (Construction Productivity Analysis)
Jayson Narito
 
PPTX
Inventory management
Rahul Gupta
 
PPT
Manufacturing
jagishar
 
PPTX
Inventory and manufacturing system migration - case study
Atul Singla
 
PPSX
Planning and Resourcing a Project
Nishant Munjal
 
PPTX
Open Data Innovation from GEO DATA Perspective
Serdar Temiz
 
PPT
Fast Prototyping Customer Development Mock Ups 2014
Serdar Temiz
 
PDF
Data Privacy, Corporates and States
Serdar Temiz
 
PPT
Project Integration Management
Serdar Temiz
 
PPTX
Design of Quality Plan
Marcelo Bonzón
 
PPTX
Start up finance & venture capital
Serdar Temiz
 
PPT
Qualitycontrolinclinicallaboratory
Tapeshwar Yadav
 
PPT
UML Basics
Serdar Temiz
 
PPT
Project Scope Management
Serdar Temiz
 
PPTX
Project Management Class ( based on PMBOK) - Day 4
Highmark Health
 
PPSX
Inventory & Manufacturing System Employing E-Business Suite
Md. Moktarul Islam
 
PPTX
foram
Foram Shah
 
PDF
PMBOK_5th_Project Management Framework
Hossam Maghrabi
 
PPTX
Project Cost Management
Serdar Temiz
 
PMP_Project Quality Management
Hisham Haridy MBA, PMP®, RMP®, SP®
 
Construction quality management plan (Construction Productivity Analysis)
Jayson Narito
 
Inventory management
Rahul Gupta
 
Manufacturing
jagishar
 
Inventory and manufacturing system migration - case study
Atul Singla
 
Planning and Resourcing a Project
Nishant Munjal
 
Open Data Innovation from GEO DATA Perspective
Serdar Temiz
 
Fast Prototyping Customer Development Mock Ups 2014
Serdar Temiz
 
Data Privacy, Corporates and States
Serdar Temiz
 
Project Integration Management
Serdar Temiz
 
Design of Quality Plan
Marcelo Bonzón
 
Start up finance & venture capital
Serdar Temiz
 
Qualitycontrolinclinicallaboratory
Tapeshwar Yadav
 
UML Basics
Serdar Temiz
 
Project Scope Management
Serdar Temiz
 
Project Management Class ( based on PMBOK) - Day 4
Highmark Health
 
Inventory & Manufacturing System Employing E-Business Suite
Md. Moktarul Islam
 
foram
Foram Shah
 
PMBOK_5th_Project Management Framework
Hossam Maghrabi
 
Project Cost Management
Serdar Temiz
 
Ad

Similar to Project Quality Management (20)

PPTX
Session 12 4th edition PMP
محمد عصمت عبد الرازق
 
PPSX
Project Quality Management
mzedan
 
PDF
Topic 8 - Project Quality Management.pdf
HuyNguyen657394
 
PPT
PROJECT QUALITY KNOLEDGE AREA.ppt
RandolphRodrigues2
 
DOCX
Project quality management
syeda zoya mehdi
 
PDF
8 quality PMBOK
Waseem Siddique
 
PPT
Week 11.ppt project management course electrical engineering
hadiaiftikhar593
 
PPT
PROJECT QUALITY MANAGEMENT for Project.ppt
AhtashamArshad4
 
PPTX
Quality management mod
Mostafa Elgamala
 
PPT
Quality Management.ppt
mrigendra nath mishra
 
PPT
Quality Management.ppt
RajaRaman77
 
PPTX
Quality Management.pptx
ssuserfa5be2
 
PPTX
projectqualitymanagement-140816235544-phpapp02.pptx
HamzaKhawar4
 
PPTX
4S Akademi - QAI - Software Testing Principles and Concepts
Serdar Zeybek
 
PPTX
Quality management
APOORVNIGAM2
 
PPTX
08 projectqualitymanagement
Dhamo daran
 
PPTX
PMP Muzette Charles_Spring2019_Week4_Chapter8
Muzette Charles, PMP
 
PPTX
Quality management
Israr Khan Raja
 
PPT
Quality Software
Marius Ghetie
 
PPTX
National Postal Forum 2011 - Quality Control In Mail Center Operations
James P. Mullan, CMDSM, EMCM, MDC, MDP, LSSGB
 
Session 12 4th edition PMP
محمد عصمت عبد الرازق
 
Project Quality Management
mzedan
 
Topic 8 - Project Quality Management.pdf
HuyNguyen657394
 
PROJECT QUALITY KNOLEDGE AREA.ppt
RandolphRodrigues2
 
Project quality management
syeda zoya mehdi
 
8 quality PMBOK
Waseem Siddique
 
Week 11.ppt project management course electrical engineering
hadiaiftikhar593
 
PROJECT QUALITY MANAGEMENT for Project.ppt
AhtashamArshad4
 
Quality management mod
Mostafa Elgamala
 
Quality Management.ppt
mrigendra nath mishra
 
Quality Management.ppt
RajaRaman77
 
Quality Management.pptx
ssuserfa5be2
 
projectqualitymanagement-140816235544-phpapp02.pptx
HamzaKhawar4
 
4S Akademi - QAI - Software Testing Principles and Concepts
Serdar Zeybek
 
Quality management
APOORVNIGAM2
 
08 projectqualitymanagement
Dhamo daran
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
Muzette Charles, PMP
 
Quality management
Israr Khan Raja
 
Quality Software
Marius Ghetie
 
National Postal Forum 2011 - Quality Control In Mail Center Operations
James P. Mullan, CMDSM, EMCM, MDC, MDP, LSSGB
 

More from Serdar Temiz (19)

PPTX
Introduction to OPEN INNOVATION
Serdar Temiz
 
PPTX
Busıness Model Innovation Business Model Canvas Toolbox 2016
Serdar Temiz
 
PPTX
Business Model Canvas 2015
Serdar Temiz
 
PDF
Customer Development Fast Protyping
Serdar Temiz
 
PDF
Introduction to Entepreneurship ME2603 KTH
Serdar Temiz
 
PDF
How Open Data Changes Our Life?
Serdar Temiz
 
PPTX
Innovation & Business Model & Business Model Canvas 2014
Serdar Temiz
 
PPTX
Introduction to Entrepreneurship , Entrepreneurship in Action, KTH
Serdar Temiz
 
PPTX
Project Risk Management (10)
Serdar Temiz
 
PPTX
Organization Structure - stake holder -human resources management during proj...
Serdar Temiz
 
PPTX
Project Time Management
Serdar Temiz
 
PPTX
Project Procurement Management
Serdar Temiz
 
PPTX
Project Management Introduction General PM lifecycles
Serdar Temiz
 
PDF
Open Data for Digital Activism and Civic Engegament
Serdar Temiz
 
PPTX
Introduction to OKFN
Serdar Temiz
 
PPTX
Business model canvas 2013
Serdar Temiz
 
PPTX
Open Data Open Innovation
Serdar Temiz
 
PDF
Fast prototypes and customer development for start ups
Serdar Temiz
 
PDF
Entepreneurship for engineers
Serdar Temiz
 
Introduction to OPEN INNOVATION
Serdar Temiz
 
Busıness Model Innovation Business Model Canvas Toolbox 2016
Serdar Temiz
 
Business Model Canvas 2015
Serdar Temiz
 
Customer Development Fast Protyping
Serdar Temiz
 
Introduction to Entepreneurship ME2603 KTH
Serdar Temiz
 
How Open Data Changes Our Life?
Serdar Temiz
 
Innovation & Business Model & Business Model Canvas 2014
Serdar Temiz
 
Introduction to Entrepreneurship , Entrepreneurship in Action, KTH
Serdar Temiz
 
Project Risk Management (10)
Serdar Temiz
 
Organization Structure - stake holder -human resources management during proj...
Serdar Temiz
 
Project Time Management
Serdar Temiz
 
Project Procurement Management
Serdar Temiz
 
Project Management Introduction General PM lifecycles
Serdar Temiz
 
Open Data for Digital Activism and Civic Engegament
Serdar Temiz
 
Introduction to OKFN
Serdar Temiz
 
Business model canvas 2013
Serdar Temiz
 
Open Data Open Innovation
Serdar Temiz
 
Fast prototypes and customer development for start ups
Serdar Temiz
 
Entepreneurship for engineers
Serdar Temiz
 

Recently uploaded (20)

PDF
FLEX-LNG-Company-Presentation-Nov-2017.pdf
jbloggzs
 
PPTX
Module2 Data Base Design- ER and NF.pptx
gomathisankariv2
 
PPTX
22PCOAM21 Session 2 Understanding Data Source.pptx
Guru Nanak Technical Institutions
 
PDF
20ME702-Mechatronics-UNIT-1,UNIT-2,UNIT-3,UNIT-4,UNIT-5, 2025-2026
Mohanumar S
 
PDF
2025 Laurence Sigler - Advancing Decision Support. Content Management Ecommer...
Francisco Javier Mora Serrano
 
PDF
2010_Book_EnvironmentalBioengineering (1).pdf
EmilianoRodriguezTll
 
PPTX
MSME 4.0 Template idea hackathon pdf to understand
alaudeenaarish
 
PPTX
Information Retrieval and Extraction - Module 7
premSankar19
 
PPTX
Tunnel Ventilation System in Kanpur Metro
220105053
 
PDF
67243-Cooling and Heating & Calculation.pdf
DHAKA POLYTECHNIC
 
PDF
The Effect of Artifact Removal from EEG Signals on the Detection of Epileptic...
Partho Prosad
 
PPTX
Inventory management chapter in automation and robotics.
atisht0104
 
PDF
flutter Launcher Icons, Splash Screens & Fonts
Ahmed Mohamed
 
PDF
top-5-use-cases-for-splunk-security-analytics.pdf
yaghutialireza
 
PPTX
FUNDAMENTALS OF ELECTRIC VEHICLES UNIT-1
MikkiliSuresh
 
PPT
Ppt for engineering students application on field effect
lakshmi.ec
 
PDF
67243-Cooling and Heating & Calculation.pdf
DHAKA POLYTECHNIC
 
PDF
Chad Ayach - A Versatile Aerospace Professional
Chad Ayach
 
PPTX
Civil Engineering Practices_BY Sh.JP Mishra 23.09.pptx
bineetmishra1990
 
PPTX
business incubation centre aaaaaaaaaaaaaa
hodeeesite4
 
FLEX-LNG-Company-Presentation-Nov-2017.pdf
jbloggzs
 
Module2 Data Base Design- ER and NF.pptx
gomathisankariv2
 
22PCOAM21 Session 2 Understanding Data Source.pptx
Guru Nanak Technical Institutions
 
20ME702-Mechatronics-UNIT-1,UNIT-2,UNIT-3,UNIT-4,UNIT-5, 2025-2026
Mohanumar S
 
2025 Laurence Sigler - Advancing Decision Support. Content Management Ecommer...
Francisco Javier Mora Serrano
 
2010_Book_EnvironmentalBioengineering (1).pdf
EmilianoRodriguezTll
 
MSME 4.0 Template idea hackathon pdf to understand
alaudeenaarish
 
Information Retrieval and Extraction - Module 7
premSankar19
 
Tunnel Ventilation System in Kanpur Metro
220105053
 
67243-Cooling and Heating & Calculation.pdf
DHAKA POLYTECHNIC
 
The Effect of Artifact Removal from EEG Signals on the Detection of Epileptic...
Partho Prosad
 
Inventory management chapter in automation and robotics.
atisht0104
 
flutter Launcher Icons, Splash Screens & Fonts
Ahmed Mohamed
 
top-5-use-cases-for-splunk-security-analytics.pdf
yaghutialireza
 
FUNDAMENTALS OF ELECTRIC VEHICLES UNIT-1
MikkiliSuresh
 
Ppt for engineering students application on field effect
lakshmi.ec
 
67243-Cooling and Heating & Calculation.pdf
DHAKA POLYTECHNIC
 
Chad Ayach - A Versatile Aerospace Professional
Chad Ayach
 
Civil Engineering Practices_BY Sh.JP Mishra 23.09.pptx
bineetmishra1990
 
business incubation centre aaaaaaaaaaaaaa
hodeeesite4
 

Project Quality Management

  • 1. Project Quality Management Sections of this presentation were adapted from A Guide to the Project Management Body of Knowledge 5th Edition, Project Management Institute Inc., © 2013
  • 2. Project Quality Management  Project quality management includes the process required to ensure that the project satisfies the needs for which it is undertaken.  PQM includes all the activities of the overall management function that determine the quality policy, objectives, and responsibilities and implement them within the quality system.
  • 3. Why Quality Management?  Quality means conformance to specifications and fitness for use – i.e. just what you need and not more  Projects or products with unnecessary features can be too expensive to meet the business need  Prevention is much cheaper than inspection, build quality in early to minimize costs/maximize quality
  • 4. How to Manage Quality?Three processes • Plan Quality – What is quality and how will we ensure it? • Perform Quality Assurance – Are we following the quality standards? • Perform Quality Control – Are we meeting the quality standards? Perform Quality Assurance Perform Quality Control Plan Quality
  • 5. How to Manage Quality?  These processes interact with each other as well as with the processes of other knowledge areas  Each process involves an effort of one or more individual or group of individuals based on the need of the project.  Each process occurs at least once in every project phase during the project life cycle Perform Quality Assurance Perform Quality Control Plan Quality
  • 6. Plan Quality Management  Cost-benefit analysis  Cost of quality  Seven basic quality tools  Benchmarking  Design of experiments  Statistical sampling  Additional quality planning tools  Meetings Tools & TechniquesProject management plan Stakeholder register Risk register Requirements documentation Enterprise environmental factors Organizational process assets Quality management plan Process improvement plan Quality metrics Quality checklists Project documents updates Inputs Outputs Perform Quality Assurance Perform Quality Control Plan Quality
  • 7. Plan Quality Management Cost of Quality – Evaluating the cost of conformance with the cost of nonconformance to reach a balance. Includes; • Prevention Costs • Appraisal Costs • Failure Costs Cost of Conformance Cost of Non Conformance Quality training Rework Studies Scrap Surveys Inventory Costs Warranty Costs Deming’s Costs of Quality “85% of the costs of quality are the direct responsibility of management "- William Edwards Deming
  • 8. Plan Quality Management PMBOOK 2013 Cost of Quality – Evaluating the cost of conformance with the cost of nonconformance to reach a balance.
  • 9. Quality Planning Terms Gold Plating – Giving the customer extras that do not add value to the project Marginal Analysis – The point where the incremental revenue from an improvement equals the cost to implement it Kaizen – Continuous improvement process to reduce costs and promote consistency ISO 9000 – International standard to ensure that companies have quality procedures and that they follow them
  • 10. Perform Quality Assurance  Quality management and control tools  Quality audits  Process analysis Tools & Techniques Change requests Project management plan updates Project documents updates Organizational process assets updates Quality management plan Process improvement plan Quality metrics Quality control measurements Project documents Inputs Outputs Perform Quality Assurance Perform Quality Control Plan Quality
  • 11. Statistics Terms Review  Mutually Exclusive – Two events that cannot both occur in a single trial  Statistical Independence – Probability of one event occurring does not affect the probability of another event occurring  Probability – The likelihood that something will occur (usually expressed in percent)
  • 12. Perform Quality Control  Seven basic quality tools  Statistical sampling  Inspection  Approved change requests review Tools & Techniques Quality Control Measurements Validated Deliverables Validated Changes Change Requests Project Management Plan Updates Work performance information Project Document Updates Project management plan Quality metrics Quality checklists Work performance data Approved change requests Deliverables Project documents Organizational process assets Inputs Outputs Perform Quality Assurance Perform Quality Control Plan Quality
  • 13. Pareto Principle/ Chart Graph of problem type vs. frequency 80/20 Rule – a theory maintaining that 80% of the output in a given situation or system is produced by 20% of the input. Problem Type Frequency CumulativePercentage www.techtarget.com/
  • 14. Control Chart  Upper & Lower Control Limits (UCL & LCL) • Set by quality goal i.e. 3s • Includes the normal and expected variation in the process  Specification Limits • Contracted acceptable limit, usually outside UCL & LCL  Out of Control A process is considered out of control when: 1. a data point exceeds a control limit; 2. seven consecutive plot points are above the mean; 3. seven consecutive plot points are below the mean.  Assignable Change • When the controller adjusts the process to bring the process back within process control limits
  • 15. Control Charts Out of control point indicates unsuall process - activity