AGILE PLANNING
PROCESS
John Derrico
www.linkedin.com/in/johnaderrico
Scope and Questions on Agile
 Planning
                      • At the end of this presentation you
Agile and Waterfall
                       will be able to answer these
Agile Framework        questions about Agile Planning:
                        • Where is the planning executed?
Release Planning        • Who is part of the planning?
                        • When is the planning executed? (E.g. 1
Sprint Planning           time?)
                        • How is the planning performed?
                        • What is required for the planning
                          meetings and what is expected as an
                          outcome from the meetings?
Cats and Dogs (Agile and Waterfall)
Comparison
                                   Waterfall

Requirements              Design               Develop              Validate

                                                                         Time

                              Iterative / Agile




  Define        Define         Define      Define         Define        Define
 Design        Design         Design      Design         Design        Design
 Develop       Develop        Develop     Develop        Develop       Develop
 Validate      Validate       Validate    Validate       Validate      Validate
                                                                          Time
                                                                                  4
Agile Framework



Strategic
Planning




                            Release Planning
                            Sprint Planning


            Planning and estimating depend on a key metric: velocity, which describes
            how much work the team can get done per sprint.

                                                                                        5
Release Planning
Goal: Establish the overall release schedule and determine in what sprint stories will likely be
delivered.

                             • Who: Scrum Coach, Product Owner, Scrum               Release Plan
                               Team, Scrum Master, Key Stakeholders
   Product Vision            • When: before release n+1 begins (.5 -2 days)
                             • How / Topic(s):
                                                                                   Selected stories
                                • PO presents the vision, strategy and              for the release
     High level                   goals.
 prioritized goals &            • PO present key dates and milestones.
      roadmap                   • PO presents draft of the prioritized            Prioritized product
                                  backlog.                                              backlog
                                • Discussion to understand user stories.
  Product Backlog               • Review rough estimates + prioritized
   (priority draft)               features.                                          Stakeholder
                                • Agreement on Sprint length (in weeks)              consensus
                                  and target release dates.
 Rough Estimates                • Release Plan is organized by scope
                                  (functionality) or time (release every N
                                  sprints).                                         Key risks and
                                • Continual Planning. The initial release           assumptions
                                  plan is a ‘blueprint’ to get started and will
                                  be revised.

                                      “Sprint towards Change”

                                                                                                        6
Sprint (Iteration) Planning
Goal: Team to plan and agree on backlog items they can complete and confirm the tasks
required to support acceptance.

                         • Who: Scrum Coach, Product Owner,
  Release Plan                                                               Sprint Plan
                           Scrum Team, Scrum Master.
                         • When: before Sprint n+1 begins (2-3 hrs).
Prioritized product      • How / Topic(s):                                 Selected stories
      backlog               • PO presents the backlog items in              for the sprint
                              priority order for review.
                            • Stories with failed acceptance tests
Teams capabilities            from prior sprints are added*.                Key risks and
    (hours)                 • Discuss story creation for defects from       assumptions
                              prior sprints*.
  Prior Velocity            • Review and clarify user stories.              Stakeholder
                            • Breakdown larger stories and each             consensus
                              story into tasks and acceptance
   Story Effort               criteria.
   Estimation               • Tasks are estimated in hours.
                            • 1 developer and tester assigned to be
                              on point per story.
 Schedule risks /           • Process continues until all available
    Business                  hours are used for the sprint.
   conditions


                                                                                              7
Note on Experience Challenges
 Problem: The team does not have past experience of Sprint planning,
 capacity is not known and story points may be inaccurate.
 Over time estimation of capacity and story sizing will improve.


Tactics, look at variation:
 Determine the Sprint variation (Estimated Capacity in Story Points Vs.. Actual Completed
  Story Points) at the end of each sprint.

 Determine Story Point variation for each story (No of hours expected Vs.. No of Hours
  used to complete).




                                                                                             8
Agile Planning Recap
For both Release and Sprint planning sessions we addressed
• Where in the framework the planning is executed.
• Who is part of the planning sessions.
• When the planning sessions are executed.
• How is the planning performed.
• What is required for the planning session and what is expected as an
outcome.




                                                                         9

More Related Content

PPTX
Agile2013 sustainable change
Dennis Stevens
 
PDF
Agile Scrum Overview
Jason Dean
 
PPT
What Is A Sprint Planning Meeting
Vikrama Dhiman
 
PPTX
Agile Release Planning
Michael J Geiser
 
PDF
How to do effective pi planning
SwatiKapoor43
 
PPTX
Agile Roles & responsibilities
Ravi Tadwalkar
 
PPTX
Scrum master checklist
Shaju Rasheed
 
Agile2013 sustainable change
Dennis Stevens
 
Agile Scrum Overview
Jason Dean
 
What Is A Sprint Planning Meeting
Vikrama Dhiman
 
Agile Release Planning
Michael J Geiser
 
How to do effective pi planning
SwatiKapoor43
 
Agile Roles & responsibilities
Ravi Tadwalkar
 
Scrum master checklist
Shaju Rasheed
 

What's hot (20)

PDF
SAFe® - scaled agile framework in practice
Intland Software GmbH
 
PDF
Agile practices using jira atlassian
Michal Epstein
 
PPTX
The Essence of Sprint Planning : Presented by Sprint Planning
oGuild .
 
PDF
Agile Transformation v1.27
LiminalArc
 
PDF
An Introduction to Scaled Agile Framework (SAFe)
CA Technologies
 
PPTX
Agile-overview: Agile Manifesto, Agile principles and Agile Methodologies
Balaji Sathram
 
PPTX
Introduction to Scrum.ppt
Mohan Late
 
PPTX
Product Owner
Robin Surland
 
PDF
Introduction to JIRA & Agile Project Management
Dan Chuparkoff
 
PPTX
Scaled Agile Framework (SAFe) Roles and Meetings
Rob Betcher
 
PDF
Agile Transformation in Telco Guide
ACM
 
PPTX
Release planning using feature points
Madhur Kathuria
 
PPTX
Introduction to scaled agile framework
Srinath Ramakrishnan
 
PPTX
Scaled agile framework (SAFe) - adopting agile at enterprise scale
Vadim Mikhnevych
 
PPT
Scrum In 15 Minutes
Srikanth Shreenivas
 
PDF
Scrum 101: Introduction to Scrum
Arrielle Mali
 
PDF
Agile Scrum Training Process
Clarion Marketing
 
PDF
A. Kamran's DoD and DoR: Definition of Done and Definition of Ready in Scrum
Arman Kamran
 
PDF
Scrum - Agile Methodology
Niel Deckx
 
PDF
Scrum Process
Rodrigo Paolucci
 
SAFe® - scaled agile framework in practice
Intland Software GmbH
 
Agile practices using jira atlassian
Michal Epstein
 
The Essence of Sprint Planning : Presented by Sprint Planning
oGuild .
 
Agile Transformation v1.27
LiminalArc
 
An Introduction to Scaled Agile Framework (SAFe)
CA Technologies
 
Agile-overview: Agile Manifesto, Agile principles and Agile Methodologies
Balaji Sathram
 
Introduction to Scrum.ppt
Mohan Late
 
Product Owner
Robin Surland
 
Introduction to JIRA & Agile Project Management
Dan Chuparkoff
 
Scaled Agile Framework (SAFe) Roles and Meetings
Rob Betcher
 
Agile Transformation in Telco Guide
ACM
 
Release planning using feature points
Madhur Kathuria
 
Introduction to scaled agile framework
Srinath Ramakrishnan
 
Scaled agile framework (SAFe) - adopting agile at enterprise scale
Vadim Mikhnevych
 
Scrum In 15 Minutes
Srikanth Shreenivas
 
Scrum 101: Introduction to Scrum
Arrielle Mali
 
Agile Scrum Training Process
Clarion Marketing
 
A. Kamran's DoD and DoR: Definition of Done and Definition of Ready in Scrum
Arman Kamran
 
Scrum - Agile Methodology
Niel Deckx
 
Scrum Process
Rodrigo Paolucci
 
Ad

Similar to Understanding the Agile Release and Sprint Planning Process (20)

PPTX
Zen of Scrum
Magnus Nord
 
PDF
Managing Scope Time Cost And Team In Agile
mlaulin
 
PDF
Agile SCRUM Methodology
Angelin R
 
PPTX
Scrum methodology
C.T.Co
 
PDF
Agile Estimation & Planning by Bachan Anand
Conscires Agile Practices
 
PPTX
Agile 101
Bill McGehee
 
KEY
Agile intro module 1
André Heijstek
 
PDF
Agile intro module 1
André Heijstek
 
PPTX
Using Agile to move from info centric to user centric
Mia Horrigan
 
PPTX
Introduction to scrum
William Simms
 
PDF
Introduction to Agile software testing
KMS Technology
 
PDF
Agile estimation and planning by bachan anand ( sep 10th)
Conscires Agile Practices
 
PPTX
Scrum training
Qasim Mehmood MBA-PM
 
PPTX
Scrum Training
Qasim Mehmood MBA-PM
 
PPTX
Agile – scrum +
Alon Lahav
 
PDF
Llllllllllllllllllllllllllllllllllllllllllllllllll9.pdf
rahulprasad894389
 
PPTX
Untangling Agile Estimation - PMI Houston 2019 Symposium
Jami Anderson
 
PDF
Agile course Part 1
ABDEL RAHMAN KARIM
 
PDF
Agile Course
ABDEL RAHMAN KARIM
 
PDF
Scrum in practice
meij200
 
Zen of Scrum
Magnus Nord
 
Managing Scope Time Cost And Team In Agile
mlaulin
 
Agile SCRUM Methodology
Angelin R
 
Scrum methodology
C.T.Co
 
Agile Estimation & Planning by Bachan Anand
Conscires Agile Practices
 
Agile 101
Bill McGehee
 
Agile intro module 1
André Heijstek
 
Agile intro module 1
André Heijstek
 
Using Agile to move from info centric to user centric
Mia Horrigan
 
Introduction to scrum
William Simms
 
Introduction to Agile software testing
KMS Technology
 
Agile estimation and planning by bachan anand ( sep 10th)
Conscires Agile Practices
 
Scrum training
Qasim Mehmood MBA-PM
 
Scrum Training
Qasim Mehmood MBA-PM
 
Agile – scrum +
Alon Lahav
 
Llllllllllllllllllllllllllllllllllllllllllllllllll9.pdf
rahulprasad894389
 
Untangling Agile Estimation - PMI Houston 2019 Symposium
Jami Anderson
 
Agile course Part 1
ABDEL RAHMAN KARIM
 
Agile Course
ABDEL RAHMAN KARIM
 
Scrum in practice
meij200
 
Ad

Understanding the Agile Release and Sprint Planning Process

  • 2. Scope and Questions on Agile Planning • At the end of this presentation you Agile and Waterfall will be able to answer these Agile Framework questions about Agile Planning: • Where is the planning executed? Release Planning • Who is part of the planning? • When is the planning executed? (E.g. 1 Sprint Planning time?) • How is the planning performed? • What is required for the planning meetings and what is expected as an outcome from the meetings?
  • 3. Cats and Dogs (Agile and Waterfall)
  • 4. Comparison Waterfall Requirements Design Develop Validate Time Iterative / Agile Define Define Define Define Define Define Design Design Design Design Design Design Develop Develop Develop Develop Develop Develop Validate Validate Validate Validate Validate Validate Time 4
  • 5. Agile Framework Strategic Planning Release Planning Sprint Planning Planning and estimating depend on a key metric: velocity, which describes how much work the team can get done per sprint. 5
  • 6. Release Planning Goal: Establish the overall release schedule and determine in what sprint stories will likely be delivered. • Who: Scrum Coach, Product Owner, Scrum Release Plan Team, Scrum Master, Key Stakeholders Product Vision • When: before release n+1 begins (.5 -2 days) • How / Topic(s): Selected stories • PO presents the vision, strategy and for the release High level goals. prioritized goals & • PO present key dates and milestones. roadmap • PO presents draft of the prioritized Prioritized product backlog. backlog • Discussion to understand user stories. Product Backlog • Review rough estimates + prioritized (priority draft) features. Stakeholder • Agreement on Sprint length (in weeks) consensus and target release dates. Rough Estimates • Release Plan is organized by scope (functionality) or time (release every N sprints). Key risks and • Continual Planning. The initial release assumptions plan is a ‘blueprint’ to get started and will be revised. “Sprint towards Change” 6
  • 7. Sprint (Iteration) Planning Goal: Team to plan and agree on backlog items they can complete and confirm the tasks required to support acceptance. • Who: Scrum Coach, Product Owner, Release Plan Sprint Plan Scrum Team, Scrum Master. • When: before Sprint n+1 begins (2-3 hrs). Prioritized product • How / Topic(s): Selected stories backlog • PO presents the backlog items in for the sprint priority order for review. • Stories with failed acceptance tests Teams capabilities from prior sprints are added*. Key risks and (hours) • Discuss story creation for defects from assumptions prior sprints*. Prior Velocity • Review and clarify user stories. Stakeholder • Breakdown larger stories and each consensus story into tasks and acceptance Story Effort criteria. Estimation • Tasks are estimated in hours. • 1 developer and tester assigned to be on point per story. Schedule risks / • Process continues until all available Business hours are used for the sprint. conditions 7
  • 8. Note on Experience Challenges Problem: The team does not have past experience of Sprint planning, capacity is not known and story points may be inaccurate. Over time estimation of capacity and story sizing will improve. Tactics, look at variation:  Determine the Sprint variation (Estimated Capacity in Story Points Vs.. Actual Completed Story Points) at the end of each sprint.  Determine Story Point variation for each story (No of hours expected Vs.. No of Hours used to complete). 8
  • 9. Agile Planning Recap For both Release and Sprint planning sessions we addressed • Where in the framework the planning is executed. • Who is part of the planning sessions. • When the planning sessions are executed. • How is the planning performed. • What is required for the planning session and what is expected as an outcome. 9