Basic Contract Law
for Project Managers
Webinar 2 of 3:
Building a contract
by Sarah Schütte
of Schutte Consulting Limited
For APM
March 2018
© 2018 Schutte Consulting Limited
1
Webinar 2 topics
Today we are going to talk about:
 Components of a contract;
 ‘Boiler plate’ & negotiated clauses;
 Risk allocation;
 Who should be involved; and
 Project managing a contract’s development.
© 2018 Schutte Consulting Limited
2
Background
to the webinar series
SCL’s core belief is centred on the reality of using law in practice, applying
it to your project, as it develops and delivers outputs (“realises benefits”)!
 PMs are central to the smooth running of a project
 PMs have to juggle many things and be multi-skilled
 Parties to a project depend on the PM to administer and manage the
contract, and to give direction
 Why should PMs learn about contracts?
 2 main risks:
 The project at risk and/ or sub-par delivery
 Yourself and your organisation at risk
 NB get the basics, but know your limitations and seek legal advice
© 2018 Schutte Consulting Limited
3
Background
to this webinar
 In Webinar 1 we looked at the foundations of a contract,
and the essential features to make it legally binding
 In this Webinar 2, we are going to look at the key terms to
look out for in 2 situations:
 Drafting a contract; or
 Reviewing a proposed contract from your client or supplier
 There will be certain terms which
 You will want to include (and avoid the risk of implied terms
(Webinar 1))
 Are more risky, but commercially acceptable (how to manage
the risk becomes the important thing)
 Are unacceptable to your organisation as a matter of policy (so
you have to walk away from the deal)
© 2018 Schutte Consulting Limited
4
Components of a contract
Date: This contract/deed is made on XXXXXXXXX
Parties: Between (1) AAAAA and (2) BBBBBBBB
Recitals: A description of the background and why the parties are
making the contract
Consideration: value of the contract works or services. If nil value
(e.g. framework or collateral warranty) insert “in consideration of
£1 being paid by A to B”
Terms: conditions, conditions precedent, warranties, undertakings,
indemnities, ordinary terms
Authorised persons: Signature / execution blocks
© 2018 Schutte Consulting Limited
5
Components of a contract
Date: the last part to be completed, triggering performance
Parties: accurate name and registered office
Recitals: set out a full description of the “story” leading to
this moment, avoiding commercially sensitive minutiae
Consideration: one of the elements which makes the legally
binding (Webinar 1)
Terms: see over
Authorised persons: authority to bind the named party
© 2018 Schutte Consulting Limited
6
Components of a contract
Terms: 3 types, each has different impact (introduced in Webinar 1). Quick
run-down:
1. Conditions – go to the heart of the contract. Breach or failure to comply =
significant (“repudiatory”) and entitles the other party to terminate and
claim damages. Include:
 Conditions precedent – must be complied with before something else can happen.
Non-compliance means the something else cannot occur
2. Warranties - promises, usually secondary assurances. Breach is not
repudiatory and does not entitle termination, but damages only. Include:
 Undertakings, - promise which is legally binding without the need for the other
party to do anything
 Indemnities – promise without need for proof of breach/ loss by the other party
3. Innominate (ordinary) terms – any term which is not one of the above.
Breach gives remedy proportionate to the seriousness of the breach. Test =
Is the innocent party “deprived of substantially the whole of the benefit”
© 2018 Schutte Consulting Limited
7
Components of a contract
Tips on terms
 Take advice on drafting of content and categorisation
 Ensure that the term has the effect you want it to have
 Most terminations which fail do so because the basis for termination
was insufficient
 In any dispute or attempted termination which is challenged, the
Court will determine the type of term and evidence required to
satisfy it.
 The “face” of the term
 Its intended purpose
 Its centrality to the contract
 Plus any statutory rules, …………..are all factors to consider
© 2018 Schutte Consulting Limited
8
“Boilerplate”
 Describes a series of terms which are usually found in a
contract – not the content but the subject matter
 Be careful to avoid a cursory glance as they may look
familiar. Everyone drafts them slightly differently!
 They serve to better define the parties’ relationship i.e.
the balance of risk and how risk is allocated
 They also change the underlying (default) legal position
(i.e. implied term – Webinar 1)
 Use my sample SCL Boilerplate Bingo © as a checklist
© 2018 Schutte Consulting Limited
9
“Boilerplate”

 Boilerplate missing? Raise it with the other party and suggest the content i.e. your
organisation’s standard version
 Unhappy with proposed boilerplate? Explain why to the other party and suggest your
organisation’s standard version
 Take advice on in these scenarios as changes will affect the risk balance, and may impact on
other clauses (e.g. terms which are not cross-referenced) or legal norms (i.e. implied terms)
© 2018 Schutte Consulting Limited
10
SCL Boilerplate bingo ©
Law and jurisdiction IP/ Title Dispute resolution
Confidentiality Insurance Definitions
Entire agreement /
Representations
Force majeure Construction/ order of
precedence
Termination Notices 3rd party rights
Assignment Severability Others…
Negotiated clauses
 These are terms which are individually negotiated by the parties
 How to approach?
 Organisation’s standard term/ policy = starting point
 Authority to negotiate or to bind (or both)? Check organisation’s
protocol/ thresholds
 Skill in negotiation
 Translation of agreed commercial position into suitable words
 Take advice to nail the drafting
• Certainty and confidence in document underpinning the project, and
that it gives PM what he/ she needs
• Contra proferentum “against the proposer”
© 2018 Schutte Consulting Limited
11
Risk allocation
 A contract is an agreement whereby the parties share the risks of the venture/
objective
 The terms of the contract allocate the risk between the parties
 Some risks are unacceptable, e.g. against company policy
 Some risks are acceptable i.e. within the company norm
 Some risks start off as unacceptable, and the parties manage to agree a position which
suits them both
 How to decide which category a risk falls into?
 What is the organisational norm (policy)?
 Can the risk be avoided, managed or insured?
 Which party is best placed to do this?
 What is your exposure if you take on a risk, but are uninsured?
© 2018 Schutte Consulting Limited
12
What if?
Risk allocation
 Development of industry standard forms of contract
 They set out the market acceptability of certain terms (or do they?)
 Start with a standard form
 Take care with “special” or “additional” clauses which change* the standard
terms!
 They change the risk balance!
 What is the other party trying to achieve?
 If they are voluminous / significant, think carefully about
whether you want to enter into contract at all
 Specific industry codes of practice etc.
* “change” encompasses not only changes to the standard form’s existing words,
but the addition of new bespoke clauses, and any party’s “standard terms”
© 2018 Schutte Consulting Limited
13
Why?
Risk allocation
Lots of ways to allocate risk
 Risk can sit outright with one party or the other “ X shall…”
 Risk can be shared jointly “the parties together shall”
 Sharing the risk in the outcome can be done via incentives e.g. NEC “pain-gain” in Options C
and D
 One party takes the risk up to a certain level, and then the other takes over
 “C shall issue a CEN for any event listed in this clause, but if he does not do so with X weeks he
is time barred from pursuing it, unless the CEN results from events (1) and (2), when he shall
not”
 Always tie in risk consideration to the organisation’s policies and insurance to make sure you
are covered if the risk is borne by you, then it happens…
 Take advice from specialist risk manager as well as technical advice on the subject matter of
the risk in question (e.g. probability of occurrence etc.) and legal advice on the drafting
© 2018 Schutte Consulting Limited
14
Who should be involved
 I am often surprised at the lack of thought and time allocated given to contract
negotiation given how important it is!
 Contract value ≠ intrinsic indicator of risk or of potential liability
 Try to avoid giving to lawyer at the last minute for a “quick look”!
 Check organisation protocols: seniority = authority to bind and corporate visibility
 Include key project people (i.e. delivery team leads and PM)!
 Each needs to know what is expected of them i.e. the obligations (terms) to be
performed by their discipline/ function and how the terms impact on the way they
“usually” do their job, constraints, ways of working etc.
 How can you “give” a contract to a team, and expect excellent performance?
 Same for the PM – expected to run the project according to the contract
 Encourage the right people to contribute – and if you think you should be at the table,
then make your voice heard!
© 2018 Schutte Consulting Limited
15
Project managing a
contract’s development
 I like to think of the contract negotiation (or pre-contract) phase as a “project”
 It is temporary: contract will be signed or not
 It has a defined purpose: to agree the terms of business
 There should be a strategic plan and timetable (linked to the underlying project)
 There are certain things which should be achieved before you can move on the next thing (don’t
start works before signing…or enter into LoI (Webinar 1))
 I advocate the intended/ proposed PM should be involved.. The “face of the project”
 In developing the contract, some clauses will be agreed quicker than others
 Be careful about “trade-offs” – think about why the clause is important to you, and why
 Get the framework in place first i.e. agree the principles. I find it is much easier for the detail
to then fall into place.
 Keep the principles in mind in every part of the negotiation – check back and take legal advice
to ensure consistency
 Crystal-balling: machine learning and AI are encroaching on this area e.g. check proposed
clauses against organisational norms, BUT there is no substitute for the human brain and
your ability to contextualise the project
© 2018 Schutte Consulting Limited
16
Summary of this webinar
• Take care when building your contract, or when reviewing a proposed contract
• The terms of a contract relate to risk allocation
• Boilerplate looks familiar, but is not universally the same…
• Negotiated clauses are all about which party risk sits with
• Take advice on the type of term because each has a different legal consequence
• Pitch in to the conversation about the contract: you are the PM running the project
whose foundation is the contract!
• Next time, Webinar 3: What to do when things go wrong, or the unexpected happens
 Do join us
 Please give feedback
 Any questions?
© 2018 Schutte Consulting Limited
17
Contact:
Phone: +44(0)7970101188
Email: sarah@schutteconsulting.co.uk
Website: www.schutteconsulting.co.uk
Linked In: Sarah Schutte and Schutte Consulting Limited
Twitter: @sarahschutte1 and @schutteconsulting
#SCLGlobal #SCLatSW11 #AskSarahs
Skype: Sarah Schutte Sharp
© 2018 Schutte Consulting Limited
18
This presentation was delivered
at an APM webinar
To find out more about
upcoming events please visit our
website www.apm.org.uk/events

More Related Content

PDF
Basic Contract Law for PMs webinar Part 3: What to do when things go wrong or...
PDF
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
PDF
Top 5 Methods for Resolving UK Construction Disputes
PDF
APM Presents - Contracts and Procurement: what you must know to get the contr...
PDF
Part II - What You Should Know About Non-Disclosure Agreements - Knobbe Marte...
PPT
Construction Contract Dispute Resolution
PDF
Ditching Defect Drama: Keeping Construction Claims Objective
PDF
CONSTRUCTION DISPUTES IN CONSTRUCTION WORK SITES AND THEIR PROBABLE SOLUTIONS
Basic Contract Law for PMs webinar Part 3: What to do when things go wrong or...
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
Top 5 Methods for Resolving UK Construction Disputes
APM Presents - Contracts and Procurement: what you must know to get the contr...
Part II - What You Should Know About Non-Disclosure Agreements - Knobbe Marte...
Construction Contract Dispute Resolution
Ditching Defect Drama: Keeping Construction Claims Objective
CONSTRUCTION DISPUTES IN CONSTRUCTION WORK SITES AND THEIR PROBABLE SOLUTIONS

What's hot (20)

PDF
Rollits Construction Focus June 2016
PDF
APM Contracts and Procurement SIG - practitioner class 1
PPT
Contract Basics for Credit Unions
PDF
Power plant project finance overview
PDF
2019 ASEAN PPP Summit MPG Opening
PPTX
Construction Futures Wales - Project Bank Accounts
PDF
Practitioner class 3: Contract strategy
PPTX
Dnjcon14 session 1 ppt final
PDF
Meet the Adjudicator
PDF
Guarantee-Backed Lines of Credit
PDF
The Supreme Court and Your Business
PDF
HSE - Introduction to Project Finance
PDF
Schinnerer tips-for-reviewing-contract
PPT
Settlement Agreements, Refreshing Law ltd slides, March 2020
PDF
Resolving Shareholder Disputes
PDF
Deals Making And Breaking Them (May 2011)
PDF
Practitioner class 4 Preparing the contract 04 july13
PDF
Rims Energy Session 2008
PPTX
Project finance
PPT
Generic Contract Issues
Rollits Construction Focus June 2016
APM Contracts and Procurement SIG - practitioner class 1
Contract Basics for Credit Unions
Power plant project finance overview
2019 ASEAN PPP Summit MPG Opening
Construction Futures Wales - Project Bank Accounts
Practitioner class 3: Contract strategy
Dnjcon14 session 1 ppt final
Meet the Adjudicator
Guarantee-Backed Lines of Credit
The Supreme Court and Your Business
HSE - Introduction to Project Finance
Schinnerer tips-for-reviewing-contract
Settlement Agreements, Refreshing Law ltd slides, March 2020
Resolving Shareholder Disputes
Deals Making And Breaking Them (May 2011)
Practitioner class 4 Preparing the contract 04 july13
Rims Energy Session 2008
Project finance
Generic Contract Issues
Ad

Similar to Basic Contract Law for PMs webinar Part 2: Building a contract, 6 March 2018 (20)

PDF
10 Essentials For An Effective Construction Contract
PDF
Understanding Construction Contracts
PPT
Introduction to Commercial Contract Drafting
PPTX
Contract Review: A Comprehensive Guide (2025)
PDF
Encyclopedia on commercial contract management
PPT
Commercial T&C Mukul Draft
PDF
Get IT in Writing: The IT Pro's Guide to Essential Contracts
PPTX
Best Practices and Tips for Contract Drafting - Contract Bazar
PDF
Module 5 How to Draft a Contract
PDF
Drafting-of-Commercial-Contracts presentation
DOCX
PPTX
Class-4-Drafting of various important clauses in a contract.pptx
PPTX
Drafting of Pre Contractual Instruments-Class-2.pptx
PDF
Consortium agreement template
PPTX
Getting Down To The Details: Contract Basics for Non-Lawyers
DOC
What Is an IC Agreement: A Complete Overview
PDF
Ten bigMistakesContract Admin
DOCX
Navigating MOU Evaluation & A Manager's Guide.docx
PDF
Lessons learnt from the Carillion collapse part 2: top 10 ways to protect you...
PPTX
Contracts - A Fun Legal Primer
10 Essentials For An Effective Construction Contract
Understanding Construction Contracts
Introduction to Commercial Contract Drafting
Contract Review: A Comprehensive Guide (2025)
Encyclopedia on commercial contract management
Commercial T&C Mukul Draft
Get IT in Writing: The IT Pro's Guide to Essential Contracts
Best Practices and Tips for Contract Drafting - Contract Bazar
Module 5 How to Draft a Contract
Drafting-of-Commercial-Contracts presentation
Class-4-Drafting of various important clauses in a contract.pptx
Drafting of Pre Contractual Instruments-Class-2.pptx
Consortium agreement template
Getting Down To The Details: Contract Basics for Non-Lawyers
What Is an IC Agreement: A Complete Overview
Ten bigMistakesContract Admin
Navigating MOU Evaluation & A Manager's Guide.docx
Lessons learnt from the Carillion collapse part 2: top 10 ways to protect you...
Contracts - A Fun Legal Primer
Ad

More from Association for Project Management (20)

PDF
APM North East Network: Micro P3 Express – A framework for all small projects
PDF
Leveraging Projects and PMOs to drive Sustainability, 2 July 2025
PDF
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
PDF
Transforming Tomorrow Managing Change in the Public Sector.pdf
PPTX
1155 Teri Okoro.pptx APM People Interest Network Presents: A People-Centric A...
PPTX
1100 Kate Howes.pptx The Value of Education and Training: Developing a Learni...
PPTX
0815 Matt Gitsham APM Conf 2025-Professor of Sustainable Development and Acad...
PPTX
1510 Rami Deen Turning Fools Gold to Sustainable Gold v0.9.pptx
PPTX
1100 Suzanne Maxted & Ellie Cady APM Sustainability Interest Network presents...
PPTX
1510 day 2 Hall 5 Arun Khuttan Building a project business case using the UN ...
PPTX
1155 Helen Clayton_Tasha Clark - ESG Slides - Final - APM Conference 25.pptx
PPTX
1100 Mark & Andrew APM Enabling Change IN Slides.pptx
PPTX
0945 APM presentation from Gabrielle Walker.pptx
PDF
How you can use behavioural insights on your projects and pitfalls to be awar...
PPTX
Sadie B Okiji - Head of projects, NHS Sussex
PPTX
Cyara Buchuck-Wilsenach.pptx Embedding DEI into Sustainable Project Managemen...
PPTX
APM 2025 Tayyab Jamil Slide Deck_Rethinking Technology Projects For Sustaina...
PPTX
1155 Robbie Warwick - Chaos to Clarity V1.0.pptx
PPTX
Daniel O’Neill Director of Project Delivery, Tevalis and Felicity Peart Count...
PPTX
1155 APM Conference 2025 - How to Embed Sustainability into the Entire Projec...
APM North East Network: Micro P3 Express – A framework for all small projects
Leveraging Projects and PMOs to drive Sustainability, 2 July 2025
IET_APM_Midlands Network_Demystifying Earned - Value_B Sarani Edit.pdf
Transforming Tomorrow Managing Change in the Public Sector.pdf
1155 Teri Okoro.pptx APM People Interest Network Presents: A People-Centric A...
1100 Kate Howes.pptx The Value of Education and Training: Developing a Learni...
0815 Matt Gitsham APM Conf 2025-Professor of Sustainable Development and Acad...
1510 Rami Deen Turning Fools Gold to Sustainable Gold v0.9.pptx
1100 Suzanne Maxted & Ellie Cady APM Sustainability Interest Network presents...
1510 day 2 Hall 5 Arun Khuttan Building a project business case using the UN ...
1155 Helen Clayton_Tasha Clark - ESG Slides - Final - APM Conference 25.pptx
1100 Mark & Andrew APM Enabling Change IN Slides.pptx
0945 APM presentation from Gabrielle Walker.pptx
How you can use behavioural insights on your projects and pitfalls to be awar...
Sadie B Okiji - Head of projects, NHS Sussex
Cyara Buchuck-Wilsenach.pptx Embedding DEI into Sustainable Project Managemen...
APM 2025 Tayyab Jamil Slide Deck_Rethinking Technology Projects For Sustaina...
1155 Robbie Warwick - Chaos to Clarity V1.0.pptx
Daniel O’Neill Director of Project Delivery, Tevalis and Felicity Peart Count...
1155 APM Conference 2025 - How to Embed Sustainability into the Entire Projec...

Recently uploaded (20)

PDF
Why Is MCP Server Development Trending Now.pdf
PDF
HOT DAY CAFE , Café Royale isn’t just another coffee shop
PPTX
Nagarajan Seyyadurai – Visionary Leadership at WS Industries.pptx
PDF
The FMS General Management Prep-Book 2025.pdf
PPTX
NTE 2025/20: Updated End User Undertaking (EUU) Form and Guidance
PPTX
Financial Chart Red Arrow PowerPoint Templates.pptx
PDF
Keppel Ltd. 1H 2025 Results Presentation Slides
PDF
SparkLabs Primer on Artificial Intelligence 2025
PPTX
GenAI at FinSage Financial Wellness Platform
PDF
Minnesota’s New Lane-Sharing Law for Motorcycles.pdf
PPTX
Virbyze_Our company profile_Preview.pptx
PPTX
Communications Recruiter Melbourne.pptx
PPTX
How to best Address your professional Training Program - August 2025.pptx
PDF
From Risk to Opportunity: How Cybersecurity Enhances Your Staffing Business
PPTX
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
PDF
WRN_Investor_Presentation_August 2025.pdf
PDF
POB bystra trading system in English Full Guide
PPTX
Unlocking Creativity Top Adobe Tools for Content Creators Buy Adobe Software...
PPTX
Untitled presentation (2).quiz presention
PDF
Traveri Digital Marketing Seminar 2025 by Corey and Jessica Perlman
Why Is MCP Server Development Trending Now.pdf
HOT DAY CAFE , Café Royale isn’t just another coffee shop
Nagarajan Seyyadurai – Visionary Leadership at WS Industries.pptx
The FMS General Management Prep-Book 2025.pdf
NTE 2025/20: Updated End User Undertaking (EUU) Form and Guidance
Financial Chart Red Arrow PowerPoint Templates.pptx
Keppel Ltd. 1H 2025 Results Presentation Slides
SparkLabs Primer on Artificial Intelligence 2025
GenAI at FinSage Financial Wellness Platform
Minnesota’s New Lane-Sharing Law for Motorcycles.pdf
Virbyze_Our company profile_Preview.pptx
Communications Recruiter Melbourne.pptx
How to best Address your professional Training Program - August 2025.pptx
From Risk to Opportunity: How Cybersecurity Enhances Your Staffing Business
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
WRN_Investor_Presentation_August 2025.pdf
POB bystra trading system in English Full Guide
Unlocking Creativity Top Adobe Tools for Content Creators Buy Adobe Software...
Untitled presentation (2).quiz presention
Traveri Digital Marketing Seminar 2025 by Corey and Jessica Perlman

Basic Contract Law for PMs webinar Part 2: Building a contract, 6 March 2018

  • 1. Basic Contract Law for Project Managers Webinar 2 of 3: Building a contract by Sarah Schütte of Schutte Consulting Limited For APM March 2018 © 2018 Schutte Consulting Limited 1
  • 2. Webinar 2 topics Today we are going to talk about:  Components of a contract;  ‘Boiler plate’ & negotiated clauses;  Risk allocation;  Who should be involved; and  Project managing a contract’s development. © 2018 Schutte Consulting Limited 2
  • 3. Background to the webinar series SCL’s core belief is centred on the reality of using law in practice, applying it to your project, as it develops and delivers outputs (“realises benefits”)!  PMs are central to the smooth running of a project  PMs have to juggle many things and be multi-skilled  Parties to a project depend on the PM to administer and manage the contract, and to give direction  Why should PMs learn about contracts?  2 main risks:  The project at risk and/ or sub-par delivery  Yourself and your organisation at risk  NB get the basics, but know your limitations and seek legal advice © 2018 Schutte Consulting Limited 3
  • 4. Background to this webinar  In Webinar 1 we looked at the foundations of a contract, and the essential features to make it legally binding  In this Webinar 2, we are going to look at the key terms to look out for in 2 situations:  Drafting a contract; or  Reviewing a proposed contract from your client or supplier  There will be certain terms which  You will want to include (and avoid the risk of implied terms (Webinar 1))  Are more risky, but commercially acceptable (how to manage the risk becomes the important thing)  Are unacceptable to your organisation as a matter of policy (so you have to walk away from the deal) © 2018 Schutte Consulting Limited 4
  • 5. Components of a contract Date: This contract/deed is made on XXXXXXXXX Parties: Between (1) AAAAA and (2) BBBBBBBB Recitals: A description of the background and why the parties are making the contract Consideration: value of the contract works or services. If nil value (e.g. framework or collateral warranty) insert “in consideration of £1 being paid by A to B” Terms: conditions, conditions precedent, warranties, undertakings, indemnities, ordinary terms Authorised persons: Signature / execution blocks © 2018 Schutte Consulting Limited 5
  • 6. Components of a contract Date: the last part to be completed, triggering performance Parties: accurate name and registered office Recitals: set out a full description of the “story” leading to this moment, avoiding commercially sensitive minutiae Consideration: one of the elements which makes the legally binding (Webinar 1) Terms: see over Authorised persons: authority to bind the named party © 2018 Schutte Consulting Limited 6
  • 7. Components of a contract Terms: 3 types, each has different impact (introduced in Webinar 1). Quick run-down: 1. Conditions – go to the heart of the contract. Breach or failure to comply = significant (“repudiatory”) and entitles the other party to terminate and claim damages. Include:  Conditions precedent – must be complied with before something else can happen. Non-compliance means the something else cannot occur 2. Warranties - promises, usually secondary assurances. Breach is not repudiatory and does not entitle termination, but damages only. Include:  Undertakings, - promise which is legally binding without the need for the other party to do anything  Indemnities – promise without need for proof of breach/ loss by the other party 3. Innominate (ordinary) terms – any term which is not one of the above. Breach gives remedy proportionate to the seriousness of the breach. Test = Is the innocent party “deprived of substantially the whole of the benefit” © 2018 Schutte Consulting Limited 7
  • 8. Components of a contract Tips on terms  Take advice on drafting of content and categorisation  Ensure that the term has the effect you want it to have  Most terminations which fail do so because the basis for termination was insufficient  In any dispute or attempted termination which is challenged, the Court will determine the type of term and evidence required to satisfy it.  The “face” of the term  Its intended purpose  Its centrality to the contract  Plus any statutory rules, …………..are all factors to consider © 2018 Schutte Consulting Limited 8
  • 9. “Boilerplate”  Describes a series of terms which are usually found in a contract – not the content but the subject matter  Be careful to avoid a cursory glance as they may look familiar. Everyone drafts them slightly differently!  They serve to better define the parties’ relationship i.e. the balance of risk and how risk is allocated  They also change the underlying (default) legal position (i.e. implied term – Webinar 1)  Use my sample SCL Boilerplate Bingo © as a checklist © 2018 Schutte Consulting Limited 9
  • 10. “Boilerplate”   Boilerplate missing? Raise it with the other party and suggest the content i.e. your organisation’s standard version  Unhappy with proposed boilerplate? Explain why to the other party and suggest your organisation’s standard version  Take advice on in these scenarios as changes will affect the risk balance, and may impact on other clauses (e.g. terms which are not cross-referenced) or legal norms (i.e. implied terms) © 2018 Schutte Consulting Limited 10 SCL Boilerplate bingo © Law and jurisdiction IP/ Title Dispute resolution Confidentiality Insurance Definitions Entire agreement / Representations Force majeure Construction/ order of precedence Termination Notices 3rd party rights Assignment Severability Others…
  • 11. Negotiated clauses  These are terms which are individually negotiated by the parties  How to approach?  Organisation’s standard term/ policy = starting point  Authority to negotiate or to bind (or both)? Check organisation’s protocol/ thresholds  Skill in negotiation  Translation of agreed commercial position into suitable words  Take advice to nail the drafting • Certainty and confidence in document underpinning the project, and that it gives PM what he/ she needs • Contra proferentum “against the proposer” © 2018 Schutte Consulting Limited 11
  • 12. Risk allocation  A contract is an agreement whereby the parties share the risks of the venture/ objective  The terms of the contract allocate the risk between the parties  Some risks are unacceptable, e.g. against company policy  Some risks are acceptable i.e. within the company norm  Some risks start off as unacceptable, and the parties manage to agree a position which suits them both  How to decide which category a risk falls into?  What is the organisational norm (policy)?  Can the risk be avoided, managed or insured?  Which party is best placed to do this?  What is your exposure if you take on a risk, but are uninsured? © 2018 Schutte Consulting Limited 12 What if?
  • 13. Risk allocation  Development of industry standard forms of contract  They set out the market acceptability of certain terms (or do they?)  Start with a standard form  Take care with “special” or “additional” clauses which change* the standard terms!  They change the risk balance!  What is the other party trying to achieve?  If they are voluminous / significant, think carefully about whether you want to enter into contract at all  Specific industry codes of practice etc. * “change” encompasses not only changes to the standard form’s existing words, but the addition of new bespoke clauses, and any party’s “standard terms” © 2018 Schutte Consulting Limited 13 Why?
  • 14. Risk allocation Lots of ways to allocate risk  Risk can sit outright with one party or the other “ X shall…”  Risk can be shared jointly “the parties together shall”  Sharing the risk in the outcome can be done via incentives e.g. NEC “pain-gain” in Options C and D  One party takes the risk up to a certain level, and then the other takes over  “C shall issue a CEN for any event listed in this clause, but if he does not do so with X weeks he is time barred from pursuing it, unless the CEN results from events (1) and (2), when he shall not”  Always tie in risk consideration to the organisation’s policies and insurance to make sure you are covered if the risk is borne by you, then it happens…  Take advice from specialist risk manager as well as technical advice on the subject matter of the risk in question (e.g. probability of occurrence etc.) and legal advice on the drafting © 2018 Schutte Consulting Limited 14
  • 15. Who should be involved  I am often surprised at the lack of thought and time allocated given to contract negotiation given how important it is!  Contract value ≠ intrinsic indicator of risk or of potential liability  Try to avoid giving to lawyer at the last minute for a “quick look”!  Check organisation protocols: seniority = authority to bind and corporate visibility  Include key project people (i.e. delivery team leads and PM)!  Each needs to know what is expected of them i.e. the obligations (terms) to be performed by their discipline/ function and how the terms impact on the way they “usually” do their job, constraints, ways of working etc.  How can you “give” a contract to a team, and expect excellent performance?  Same for the PM – expected to run the project according to the contract  Encourage the right people to contribute – and if you think you should be at the table, then make your voice heard! © 2018 Schutte Consulting Limited 15
  • 16. Project managing a contract’s development  I like to think of the contract negotiation (or pre-contract) phase as a “project”  It is temporary: contract will be signed or not  It has a defined purpose: to agree the terms of business  There should be a strategic plan and timetable (linked to the underlying project)  There are certain things which should be achieved before you can move on the next thing (don’t start works before signing…or enter into LoI (Webinar 1))  I advocate the intended/ proposed PM should be involved.. The “face of the project”  In developing the contract, some clauses will be agreed quicker than others  Be careful about “trade-offs” – think about why the clause is important to you, and why  Get the framework in place first i.e. agree the principles. I find it is much easier for the detail to then fall into place.  Keep the principles in mind in every part of the negotiation – check back and take legal advice to ensure consistency  Crystal-balling: machine learning and AI are encroaching on this area e.g. check proposed clauses against organisational norms, BUT there is no substitute for the human brain and your ability to contextualise the project © 2018 Schutte Consulting Limited 16
  • 17. Summary of this webinar • Take care when building your contract, or when reviewing a proposed contract • The terms of a contract relate to risk allocation • Boilerplate looks familiar, but is not universally the same… • Negotiated clauses are all about which party risk sits with • Take advice on the type of term because each has a different legal consequence • Pitch in to the conversation about the contract: you are the PM running the project whose foundation is the contract! • Next time, Webinar 3: What to do when things go wrong, or the unexpected happens  Do join us  Please give feedback  Any questions? © 2018 Schutte Consulting Limited 17
  • 18. Contact: Phone: +44(0)7970101188 Email: [email protected] Website: www.schutteconsulting.co.uk Linked In: Sarah Schutte and Schutte Consulting Limited Twitter: @sarahschutte1 and @schutteconsulting #SCLGlobal #SCLatSW11 #AskSarahs Skype: Sarah Schutte Sharp © 2018 Schutte Consulting Limited 18
  • 19. This presentation was delivered at an APM webinar To find out more about upcoming events please visit our website www.apm.org.uk/events