Building the Professional of 2020: An
A h t B i ChApproach to Business Change
Process Integration
Change Risk Assessment Model: Results Discussion & AnalysisChange Risk Assessment Model: Results Discussion & Analysis
Harris Apostolopoulos BEng(Hons), MSc, MBA, PhDc
City University London 31 May 2013
CRAM (Change Risk Assessment Model) is a novel model
About
CRAM (Change Risk Assessment Model) is a novel model
approach which can significantly contribute to the missing formality
of business models especially in the change(s) risk assessment
area.
Project Management has long established the need for risk
management techniques to be utilised in the succinct definition of
associated risks in projects and agreement on countervailingassociated risks in projects and agreement on countervailing
actions as an aim to reduce scope creep, increase the probability
of on-time and in-budget delivery.
U t ll d h dl f i d l itUncontrolled changes, regardless of size and complexity, can
certainly pose as risks, of any magnitude, to projects and affect
project success or even an organisation’s coherence.
CCRAM’s Processes
• CRAM is composed of three interrelated processes (steps) which are continually
recorded and monitored. CRAM’s processes accomplish specific risk objectives
(identification, assessment, monitor & control) which are applied to projects or at a
greater extend to business environments with a view to facilitate and control change.
Risk IdentificationRisk Identification
Risk Monitoring & 
Control
Risk Assessment
Figure 1: CRAM’s Triple Processes
CCRAM’s Hierarchy
• CRAM hierarchical tree consists of one
(1) core (root) node, eight (8) parent
nodes, five (5) child nodes and its
respective sixty one (61) attributes Forrespective sixty-one (61) attributes. For
example, ‘Communication’ parent node
consists of seven (7) risk attributes
(sub-factors).
• Depending on the scope and
deliverables of a project, CRAM’s
nodes and related risk attributes
hierarchy per level can change so as to
accommodate more of fewer criteria.
Figure 2: CRAM’s Hierarchy Tree
CCRAM’s web page
http://www.changemodel.net
A dAgenda
Significance11
22 CRAM Overview22
33 Analysis of ResultsAnalysis of Results
44 Open Discussion
55 Summary
Analytical Hierarchy Process (AHP)
• Analytic Hierarchy Process (AHP) is an established and structured hierarchical pairwise• Analytic Hierarchy Process (AHP) is an established and structured hierarchical pairwise
process for making complex decisions that helps users sort out the "best" decision for
their challenge.
• Sets priorities being a systematic method for comparing a list of objectives leading to a• Sets priorities being a systematic method for comparing a list of objectives leading to a
decision; utilising pairwise comparisons; eigenvalues and eigenvector.
Weighting Scale
• In order to able to quantify the respondents replies a relative weights mapping scale is• In order to able to quantify the respondents replies, a relative weights mapping scale is
used, for example:
Weighting Scale (cont.)
• A typical pair wise comparison matrix is seen below (diagonal is always completed by• A typical pair wise comparison matrix is seen below (diagonal is always completed by
1’s):
• When comparing the elements together the smaller one to be compared is consideredWhen comparing the elements together, the smaller one to be compared is considered
to be the unit and the larger one is assessed to be so many times more than that it,
using the intensity of feeling and translating it to the numerical value.
Weighting Scale (cont.)
A t i l i i i t i i b l (di l i l l t d b• A typical pair wise comparison matrix is seen below (diagonal is always completed by
1’s):
• When comparing the elements together, the smaller one to be compared is considered
to be the unit and the larger one is assessed to be so many times more than that it,
using the intensity of feeling and translating it to the numerical value.
AHP Calculations
1 Let Aij equals the intensity of relative importance between criterion i and criterion j1. Let Aij equals the intensity of relative importance between criterion i and criterion j ,
as defined in previous with:
2. Compute , the sum of each column of A
3 Normalize A by dividing each element Aij in the comparison matrix A by Aj3. Normalize A by dividing each element Aij in the comparison matrix A by Aj
4. Compute the weight of criterion i
Step 3 :(normalisation), actually permits meaningful comparison among elements.
Step4:yields the percentage of overall relative priorities, or preferences. or preferences).
AHP Calculations Example
The numbers in the table represent the relative importance between the criteria ForThe numbers in the table represent the relative importance between the criteria. For
instance, the relative importance of criterion.
For example: the relative importance of criterion 1 versus criterion 3 is 5 and between
criterion 3 and criterion 1 it is 1/5. This indicates that criterion 1 is strongly important
compared with criterion3 The numbers in the weights column show the relative weightscompared with criterion3. The numbers in the weights column show the relative weights
of the corresponding criteria.
To evaluate the credibility of the estimated weights, Saaty (1980, 1983) proposed an
eigenvector which is considered a theoretically and practically proven methodeigenvector which is considered a theoretically and practically proven method
for evaluating the credibility of the weights.
Credibility of Weights – Eigenvectors
1 Calculate the maximum eigenvalue λ of the pair-wise comparison matrix A;1. Calculate the maximum eigenvalue λmax of the pair-wise comparison matrix A;
After computing the nth root of the products of the values in each row, λmax can be found
as follows. The priority vector is the nth root divided by the sum of the nth root values.
λmax = Sum of Priority Row
Priority Row = (sum of the row value) x Priority vector
2. Compute the consistency index (C.I.) defined by Saaty as:
If a matrix [A] which represents the pairwise comparisons elements is absolutely
consistent then it should be equal to the the matrix which denotes the ratios of theconsistent, then it should be equal to the the matrix which denotes the ratios of the
weights matrix [W].
In effect if A = W , then λmax = n
The weights (w1...n) which can be obtained by using the eigenvectors, should
be positive and normalized, in effect satisfy the reciprocity property.
Credibility of Weights – Eigenvectors (cont.)
N id d th t th i b l t i t th λ i ff t thi l l fNow, provided that there is no absolute consistency then, λmax > n, in effect this level of
inconsistency has to be measured. For this reason Saaty, defined the consistency ratio
(CR).
3 C l l t th i t ti (C R )3. Calculate the consistency ratio (C.R.)
C R = C. I/R.I
h th d i d (R I ) f diff t b bt i d fwhere the random index (R.I.) for different n can be obtained from:
Random Index (RI)
Random Index (RI) is the average of (CI) for random matrices using the Saaty scaleRandom Index (RI) is the average of (CI) for random matrices using the Saaty scale.
500 random reciprocal n x n matrices were generated for n = 3 to n = 15 using the 1 to 9
scale. CR in a sense is normalised as a value as it is divided by the arithmetic mean of
random consistency indexes (RI)random consistency indexes (RI).
Consistency Ratio (CR)
After a lot of experiments Alonso & Lamata (2006) concluded to the following calculationAfter a lot of experiments Alonso & Lamata (2006) concluded to the following calculation
of consistency ratio (CR) as better results can be obtained:
The maximum eigenvalue, based on Saaty, can be determined by raising each random
matrix to increasing powers and normalizing the result until the process converged. The
consistency index was then computed on each matrix for n = 1 through n = 15consistency index was then computed on each matrix for n = 1 through n = 15.
As a rule of thumb, a value of C.R. ≤ 0.1 is typically considered acceptable.
In other word inconsistency is permitted in AHP as long as it does not exceed the ratio ofIn other word inconsistency is permitted in AHP as long as it does not exceed the ratio of
0.1. Nevertheless, AHP is flexible enough that can trace the inconsistent elements and
reform the matrix where required; taking into account that changes in the hierarchy or
judgements may lead to changes in the outcome.
If CR equals 0 then that means that the judgments are perfectly consistent..
Further Examples (Consolidated)
k = 3 (number of participants)k = 3 (number of participants)
n = 3 (number of criteria), with respective pairwise values as seen below:
Further Examples (cont.)
For the consolidated matrix taking as an example the pairwise comparison of nFor the consolidated matrix, taking as an example the pairwise comparison of n1,2
(shaded light gray) then:
All remaining elements of the consolidated matrix as calculated with the use of geometric
mean formula.
So:So:
Respondent’s Background
Figure 3: PM Methodology Use
Figure 4: PM Experience
( )Respondent’s Background (cont.)
Figure 5: PM Team Members
Figure 6: Current Industry
• Leadership: Project success is accounted in many ways to strong leadership and commitment to
Leadership
• Leadership: Project success is accounted in many ways to strong leadership and commitment to
project scope and objectives. Active leadership remains important throughout the entire project
lifecycle, with the application of skills and determinacy to succeed. Therefore, efficient resource
management is necessary to complete each task in its predefined priority. Senior management’s
accountability is key to effective decision making in the context of ‘firm but fair’ handling, to inspire
and lead the project team in achieving high performance levels and overall high adaptation rate to
proposed and authorised changes.
Figure 7: Leadership's Risk Attributes Process
C
• Communication: Refers to the exchange of ideas or information among stakeholders e g project
Communication
• Communication: Refers to the exchange of ideas or information among stakeholders e.g. project
manager, team members, board of directors, which are related to change and associated risks.
The more complex the organisational structure or the proposed changes, the more communication
channels have to be engaged. Effective communication is a bi-directional activity which has to be
controlled and monitored. Communication is an important business environment factor
incorporating cultural values) as project’s success is highly dependent on communication.
Figure 8: Communication's Risk Attributes
C
• Culture: Collection (but not limited to) of beliefs attitudes core values ways of acting and
Culture
• Culture: Collection (but not limited to) of beliefs, attitudes, core values, ways of acting and
thinking shared among members or organisations. Culture can impact the way of business
conduction, decision making process, communication attitude and in effect influence project
success. A supportive, knowledge sharing organisational culture can be enough ‘risk taking’ so as
to match complicated project’s scope and objectives with success. A risk averse business culture
might be problematic against accepting proposed changes which in turn, might cause problems to
over decision making, communication and leadership of the project.
Figure 9: Culture's Risk Attributes
• Resistance: Change is a time consuming (transitional) and risky process often resisted by
Resistance
• Resistance: Change is a time consuming (transitional) and risky process, often resisted by
employees. If changes are not communicated in the right way, then team members might feel
threatened and undervalued. Because change actually ‘changes’ the way things used to operate
in projects, resistance is frequently observed as a phenomenon which might jeopardise project’s
success. Feeling anxious which is associated to anticipated changes is more or less normal,
nevertheless the project processes have to run as planned.
Figure 10: Resistance's Risk Attributes
• Requirements: Conditions often dictated by the project’s user which the deliverables
Requirements
• Requirements: Conditions often dictated by the project s user which the deliverables
of the project should meet. Any non conformance to customer’s requirements may
lead to partially or full unacceptance of the project’s deliverables. Change
requirements have to be documented and closely monitored from start till end of the
projectproject.
Figure 11: Requirement's Risk Attributes
(
Monitoring
• Monitoring: The change process monitoring should be continuous (but have an end
at some point), involving benchmarking, milestones establishment, Key Performance
Indicators (KPIs) and proper feedback. The end at some point, may become
unnecessary for a reason e.g. if the change becomes obsolete and does not serve
any purpose anymore.
Figure 12: Monitoring's Risk Attributes
/
• Flexibility (Adaptation): Refers to the ability to affect changes and to the level which are
Flexibility / Adaptation
• Flexibility (Adaptation): Refers to the ability to affect changes, and to the level which are
adaptable to the project scope. Flexibility is also related to the level of quick response to change.
For example, there are cases where time is limited and quick decision making is required. Since
not all organisations are adaptable to changes the responsiveness to change is an overall added
value. Changes process flexibility results from ability to embed changes in project management
policies and procedures; sometimes proactively in response to anticipated changes in the project
life cycle.
Figure 13: Flexibility's Risk Attributes
• Project Management Team (PMT): Project team members who are directly involved
Project Management Team
• Project Management Team (PMT): Project team members who are directly involved
in project management activities, processes and in effect ‘execute’ the project within
defined scope and objectives.
Figure 14: PMT’s Risk Attributes
f
Performance: Based on the achievement of preset metrics such as KPI’s (Key
Performance
• Performance: Based on the achievement of preset metrics such as KPI’s (Key
Performance Indicators), Balanced Score Cards, KSFs, (Key Success Factors), 360,
SLAs (Service Level Agreements); assessing measurement and trends to effect
processes improvement and goals.
Figure 15: Performance’s Risk Attributes
• Motivation: Motivation can inspire and encourage individuals (create value) or
Motivation
• Motivation: Motivation can inspire and encourage individuals (create value) or
groups of people who constitute the project management team to cope with the
changes strategy and increase their overall performance. If motivation is weak then
this might have serious effects on the project constraints which consequently might
lead to project failure Effectively motivation can be seen also as a driver forlead to project failure. Effectively, motivation can be seen also as a driver for
successful project management.
Figure 16: Motivation’s Risk Attributes
• Appraisal: Assessing the performance of employees against agreed change targets
Appraisal
• Appraisal: Assessing the performance of employees against agreed change targets
and consequently to project’s deliverables. Appraisals are better conducted on a
systematic, periodic basis. In such a way individual’s job performance and
productivity will be assessed in relation to certain pre-established criteria and
organisational project change objectivesorganisational project change objectives.
Figure 17: Appraisal’s Risk Attributes
• Rewards: Tangible and/or intangible benefits given or received in recompense for worthy
Rewards
• Rewards: Tangible and/or intangible benefits given or received in recompense for worthy
behaviour, for example after the successful result of change/s have been acknowledged. In many
cases rewards may lead to internal team member’s competition which up to a point may be
considered healthy. People who will place change effort on their priorities list, and especially those
who will succeed change goals can be rewarded with benefits. The reward, if any, should not be
an incentive for competition among team members rather than for effective cooperation and goals
and performance accomplishments.
Figure 18: Reward’s Risk Attributes
• Training: Training can be regarded as the acquisition of knowledge skills and competencies as a
Training
• Training: Training can be regarded as the acquisition of knowledge, skills, and competencies as a
result of teaching and course taking. Irrespective of contemporary project management
framework followed, change management training, can be seen as an overall advantage (value)
since the knowledge gained is not only specific but necessary to identify, plan and validate
changes, tackle risks in a structured and documented manner.
Figure 19: Training’s Risk Attributes
C O
• Successful Change Management: Change management mostly observed and
Change Risk Overall Assessment
• Successful Change Management: Change management mostly observed and
utilised as an integrated process within project management, is a rational process for
exploring decision and behaviour alternatives in an attempt to realign the course of
“derailed” deliverables due to change and ensure project success.
Figure 20: Change Risk Attributes
S
Depending on the scope and deliverables of a project, CRAM’s nodes and related risk attributes hierarchy per level can be changed so as to accomm
CRAM as a novel model approach has the capacity to define the internal dynamics of change management within
project management eliciting also risk cause-and-effect relationships.
Summary
11
Depending on the scope and deliverables of a project, CRAM’s nodes and related risk attributes hierarchy
per level can be changed so as to accommodate more of fewer criteria.
Depending on the scope and deliverables of a project, CRAM’s nodes and related risk attributes hierarchy
per level can be changed so as to accommodate more of fewer criteria.
project management eliciting also risk cause and effect relationships.11
22
A functional hierarchy is constructed so as to decompose the complex system in smaller criteria or attributes in a
logical and simpler way.
CRAM allows users to describe a problem as they see it, refine the complexity and structure a hierarchy of attributes.CRAM allows users to describe a problem as they see it, refine the complexity and structure a hierarchy of attributes.33
44
The only restriction on the hierarchic arrangement of elements is that any element in one level must be capable ofThe only restriction on the hierarchic arrangement of elements is that any element in one level must be capable of
g p y
A hierarchical ‘tree like’ graphical model representation can be easily interpreted being capable of representing
probabilistic relationships among a set of variables and associated attributes,55
Can be applied to variety of industries / projects irrespective of size and complexity.Can be applied to variety of industries / projects irrespective of size and complexity.
y g y
being related to some elements in the next higher level, which serves as a criterion for assessing the relative impact
of elements in the level below.
.
y g y
being related to some elements in the next higher level, which serves as a criterion for assessing the relative impact
of elements in the level below.
.
66
77
“I do not believe you can do today’s job with
yesterday’s methods and be in business tomorrow”
Nelson Jackson
Building the Professional of 2020: An Approach toBuilding the Professional of 2020: An Approach to
Business Change Process Integration
Thank You!
Questions?
info@changemodel.net
harris.apstolopoulos@gmail.com
Research conducted at City University London

More Related Content

What's hot (20)

PPTX
Keeping the Same Rule
Mohammed Awad
 
PPTX
Logistic regression
YashwantGahlot1
 
PDF
Data Analyst - Interview Guide
Venkata Reddy Konasani
 
PDF
Data Science - Part X - Time Series Forecasting
Derek Kane
 
PPTX
Chem unit 1 presentation
bobcatchemistry
 
PDF
Atlason et al, 2003 WSC_Subgradient Approximation
Michael Beyer
 
PDF
Parameter Optimisation for Automated Feature Point Detection
Dario Panada
 
PPT
Chapter 14
Tuul Tuul
 
PDF
Six sigma
MallikarjunRaoPanaba
 
PDF
[M3A4] Data Analysis and Interpretation Specialization
Andrea Rubio
 
PDF
Implimenting_HJM
Abukar Ali, CQF
 
PPTX
Content extraction via tag ratios
Jhih-Ming Chen
 
DOC
352735326 rsh-qam11-tif-05-doc
Firas Husseini
 
PDF
Parameter estimation
RAVI PRASAD K.J.
 
DOCX
Regression with Time Series Data
Rizano Ahdiat R
 
PPTX
Interval estimation for proportions
Aditya Mahagaonkar
 
PDF
Principal Component Analysis and Clustering
Usha Vijay
 
PPTX
Topic 15 correlation spss
Sizwan Ahammed
 
PPTX
LINEAR PROGRAMMING Assignment help
john mayer
 
Keeping the Same Rule
Mohammed Awad
 
Logistic regression
YashwantGahlot1
 
Data Analyst - Interview Guide
Venkata Reddy Konasani
 
Data Science - Part X - Time Series Forecasting
Derek Kane
 
Chem unit 1 presentation
bobcatchemistry
 
Atlason et al, 2003 WSC_Subgradient Approximation
Michael Beyer
 
Parameter Optimisation for Automated Feature Point Detection
Dario Panada
 
Chapter 14
Tuul Tuul
 
[M3A4] Data Analysis and Interpretation Specialization
Andrea Rubio
 
Implimenting_HJM
Abukar Ali, CQF
 
Content extraction via tag ratios
Jhih-Ming Chen
 
352735326 rsh-qam11-tif-05-doc
Firas Husseini
 
Parameter estimation
RAVI PRASAD K.J.
 
Regression with Time Series Data
Rizano Ahdiat R
 
Interval estimation for proportions
Aditya Mahagaonkar
 
Principal Component Analysis and Clustering
Usha Vijay
 
Topic 15 correlation spss
Sizwan Ahammed
 
LINEAR PROGRAMMING Assignment help
john mayer
 

Viewers also liked (20)

PPTX
Dsm as theory building
ClarkTony
 
PDF
Křivánek - kpii - 13 - naratologie
Luboš Křivánek
 
PPTX
Presentasi bahasa indonesia
Prilli Meli Agustina
 
PDF
How to remove_sality
Gustav Kato
 
PDF
Delivering Professional IT Services: Change, an Underestimated Value
Dr Harris Apostolopoulos EMBA, PfMP, PgMP, PMP, IPMO-E
 
PPTX
Manajemen waktu
Prilli Meli Agustina
 
PPTX
Present progressive jessika
Jessi Custodio
 
PDF
Model Driven Business Engineering for Change Management and Adaptation
Dr Harris Apostolopoulos EMBA, PfMP, PgMP, PMP, IPMO-E
 
PPTX
Seni budaya musik jazz
Prilli Meli Agustina
 
PPTX
EUPATI patient expert training course and its relevance for patient involvement
EUPATI
 
PDF
Rsa encryption
Gustav Kato
 
PPTX
Good practices in patient involvement in HTA
EUPATI
 
PPTX
Sejarah,definisi akuntansi menurut ahli,profesi akuntansi
Prilli Meli Agustina
 
PPS
4 la comunicacion
joliegirl_83
 
PPTX
Patients' involvement in ethics committees. A view from Austria.
EUPATI
 
PPT
Depletion of fossil fuels
Carlosperkles
 
PPT
Theory building lecture-3
University of Balochistan
 
PPTX
Theory and Research
Brigham Young University
 
PPT
Theory building (brm)
university of peshawar
 
PPTX
Gsm based irrigation control
Satyam Tiwari
 
Dsm as theory building
ClarkTony
 
Křivánek - kpii - 13 - naratologie
Luboš Křivánek
 
Presentasi bahasa indonesia
Prilli Meli Agustina
 
How to remove_sality
Gustav Kato
 
Delivering Professional IT Services: Change, an Underestimated Value
Dr Harris Apostolopoulos EMBA, PfMP, PgMP, PMP, IPMO-E
 
Manajemen waktu
Prilli Meli Agustina
 
Present progressive jessika
Jessi Custodio
 
Model Driven Business Engineering for Change Management and Adaptation
Dr Harris Apostolopoulos EMBA, PfMP, PgMP, PMP, IPMO-E
 
Seni budaya musik jazz
Prilli Meli Agustina
 
EUPATI patient expert training course and its relevance for patient involvement
EUPATI
 
Rsa encryption
Gustav Kato
 
Good practices in patient involvement in HTA
EUPATI
 
Sejarah,definisi akuntansi menurut ahli,profesi akuntansi
Prilli Meli Agustina
 
4 la comunicacion
joliegirl_83
 
Patients' involvement in ethics committees. A view from Austria.
EUPATI
 
Depletion of fossil fuels
Carlosperkles
 
Theory building lecture-3
University of Balochistan
 
Theory and Research
Brigham Young University
 
Theory building (brm)
university of peshawar
 
Gsm based irrigation control
Satyam Tiwari
 
Ad

Similar to Building the Professional of 2020: An Approach to Business Change Process Integration ( (20)

PDF
Analytical Hierarchy Process Approach An Application Of Engineering Education
Bria Davis
 
DOCX
With the consideration of the recurring theme and ideas of .docx
madlynplamondon
 
PDF
How to do ahp analysis in excel
J.Roberto S.F
 
PPT
AHP2 - Copy.pptgsghqshwsvhsvhwvhwhwhvwvvwvhxwh
AliRaza761916
 
PPTX
Decision Making Using The Analytic Hierarchy Process
Vaibhav Gaikwad
 
PDF
Project104_Group173_Draft_Proposal
Sarp Uzel
 
PPTX
AHP fundamentals
mgarciamelon
 
PPT
Ahp
fijojose
 
PPT
Introduction to AHP Method - Examples and Introduction
JulioDias42
 
PPT
AHP_Report_EM-206.ppt
GeorgeGomez31
 
PPT
PPT-UEU-Sistem-Pendukung-Keputusan-Pertemuan-9.ppt
AndiRahadianWijayaST
 
PDF
Multi Criteria Decision Making Methodology on Selection of a Student for All ...
ijtsrd
 
PPTX
Evaluation of alternative policy options.pptx
TaniaUrmee
 
PDF
5 analytic hierarchy_process
FEG
 
PDF
analytic hierarchy_process
FEG
 
PPTX
ANALYTIC HIERARCHY PROCESS (AHP)
Nam N.N Tran M.Eng, PMP
 
PDF
Analytic Hierarchy Process AHP
adcom2015
 
PDF
Poonam 20ahluwalia-131008015758-phpapp02
PMI_IREP_TP
 
PDF
Poonam ahluwalia
PMI2011
 
PDF
Ahp calculations
Lakshna Suresh
 
Analytical Hierarchy Process Approach An Application Of Engineering Education
Bria Davis
 
With the consideration of the recurring theme and ideas of .docx
madlynplamondon
 
How to do ahp analysis in excel
J.Roberto S.F
 
AHP2 - Copy.pptgsghqshwsvhsvhwvhwhwhvwvvwvhxwh
AliRaza761916
 
Decision Making Using The Analytic Hierarchy Process
Vaibhav Gaikwad
 
Project104_Group173_Draft_Proposal
Sarp Uzel
 
AHP fundamentals
mgarciamelon
 
Introduction to AHP Method - Examples and Introduction
JulioDias42
 
AHP_Report_EM-206.ppt
GeorgeGomez31
 
PPT-UEU-Sistem-Pendukung-Keputusan-Pertemuan-9.ppt
AndiRahadianWijayaST
 
Multi Criteria Decision Making Methodology on Selection of a Student for All ...
ijtsrd
 
Evaluation of alternative policy options.pptx
TaniaUrmee
 
5 analytic hierarchy_process
FEG
 
analytic hierarchy_process
FEG
 
ANALYTIC HIERARCHY PROCESS (AHP)
Nam N.N Tran M.Eng, PMP
 
Analytic Hierarchy Process AHP
adcom2015
 
Poonam 20ahluwalia-131008015758-phpapp02
PMI_IREP_TP
 
Poonam ahluwalia
PMI2011
 
Ahp calculations
Lakshna Suresh
 
Ad

More from Dr Harris Apostolopoulos EMBA, PfMP, PgMP, PMP, IPMO-E (6)

PDF
EPMO: Putting the pieces together as true game changer!
Dr Harris Apostolopoulos EMBA, PfMP, PgMP, PMP, IPMO-E
 
PDF
Change Management: Enforcing the Transitional Integration towards Projects’ S...
Dr Harris Apostolopoulos EMBA, PfMP, PgMP, PMP, IPMO-E
 
PDF
Taking a step forward: Agile PMO: Trends and Challenges
Dr Harris Apostolopoulos EMBA, PfMP, PgMP, PMP, IPMO-E
 
PDF
Building the Professional of 2020: An Approach to Business Change Process Int...
Dr Harris Apostolopoulos EMBA, PfMP, PgMP, PMP, IPMO-E
 
PDF
Measuring Change Risk for Organisational Decision Making Through a Hierarchic...
Dr Harris Apostolopoulos EMBA, PfMP, PgMP, PMP, IPMO-E
 
PDF
Delivering Professional IT Services; Mind the gap of Cultural Risks
Dr Harris Apostolopoulos EMBA, PfMP, PgMP, PMP, IPMO-E
 
EPMO: Putting the pieces together as true game changer!
Dr Harris Apostolopoulos EMBA, PfMP, PgMP, PMP, IPMO-E
 
Change Management: Enforcing the Transitional Integration towards Projects’ S...
Dr Harris Apostolopoulos EMBA, PfMP, PgMP, PMP, IPMO-E
 
Taking a step forward: Agile PMO: Trends and Challenges
Dr Harris Apostolopoulos EMBA, PfMP, PgMP, PMP, IPMO-E
 
Building the Professional of 2020: An Approach to Business Change Process Int...
Dr Harris Apostolopoulos EMBA, PfMP, PgMP, PMP, IPMO-E
 
Measuring Change Risk for Organisational Decision Making Through a Hierarchic...
Dr Harris Apostolopoulos EMBA, PfMP, PgMP, PMP, IPMO-E
 
Delivering Professional IT Services; Mind the gap of Cultural Risks
Dr Harris Apostolopoulos EMBA, PfMP, PgMP, PMP, IPMO-E
 

Recently uploaded (20)

PDF
Labirintos morais: um estudo sobre ética
Ivomar Schuler da Costa
 
DOCX
Process Confirmation and Product Tracecability Project Report.docx
himanshupersevering
 
PPT
Fire Extinguishers Suppression Systems.ppt
sumanthramlakkan
 
PDF
CISSP Domain 3: Security Architecture and Engineering
VICTOR MAESTRE RAMIREZ
 
PDF
Can an Inspection Test Plan be modified during a project?
Writegenic AI
 
PDF
ANIn Bengaluru 2025 | Workshop- Innovate For Business Agility: Idea Generatio...
AgileNetwork
 
PDF
CISSP Domain 1: Security and Risk Management
VICTOR MAESTRE RAMIREZ
 
PPTX
Grounding_Hypotheses_Presentation_Updated.pptx
truefollower1
 
PDF
Is an Information Security Policy Necessary for Small Businesses?
Writegenic AI
 
PPT
leadership types and creativity in management.ppt
SubrataPaul74
 
PPT
Fire Extinguisher Training powerpoint .ppt
sumanthramlakkan
 
PPTX
Emergency Preparedness and Response.pptx
sumanthramlakkan
 
PPTX
Ideation and Product Innovation: Solving Problems
Dr NIkhill Alok Jha
 
PDF
SpatzAI Micro-conflict Resolution Toolkit
Desmond Sherlock
 
PDF
Pokemon Leadership Lessons_2025WhitePaper.pdf
katjadm
 
PDF
CISSP Domain 4: Communication and Network Security
VICTOR MAESTRE RAMIREZ
 
PPT
Fire Safety Main powerpoint for training .ppt
sumanthramlakkan
 
PDF
SpatzAI Micro-conflict Resolution Toolkit
Desmond Sherlock
 
PDF
Criminology_and_Security_Studies_Syllabus.pdf
MOHAMED HERSI FARAH
 
Labirintos morais: um estudo sobre ética
Ivomar Schuler da Costa
 
Process Confirmation and Product Tracecability Project Report.docx
himanshupersevering
 
Fire Extinguishers Suppression Systems.ppt
sumanthramlakkan
 
CISSP Domain 3: Security Architecture and Engineering
VICTOR MAESTRE RAMIREZ
 
Can an Inspection Test Plan be modified during a project?
Writegenic AI
 
ANIn Bengaluru 2025 | Workshop- Innovate For Business Agility: Idea Generatio...
AgileNetwork
 
CISSP Domain 1: Security and Risk Management
VICTOR MAESTRE RAMIREZ
 
Grounding_Hypotheses_Presentation_Updated.pptx
truefollower1
 
Is an Information Security Policy Necessary for Small Businesses?
Writegenic AI
 
leadership types and creativity in management.ppt
SubrataPaul74
 
Fire Extinguisher Training powerpoint .ppt
sumanthramlakkan
 
Emergency Preparedness and Response.pptx
sumanthramlakkan
 
Ideation and Product Innovation: Solving Problems
Dr NIkhill Alok Jha
 
SpatzAI Micro-conflict Resolution Toolkit
Desmond Sherlock
 
Pokemon Leadership Lessons_2025WhitePaper.pdf
katjadm
 
CISSP Domain 4: Communication and Network Security
VICTOR MAESTRE RAMIREZ
 
Fire Safety Main powerpoint for training .ppt
sumanthramlakkan
 
SpatzAI Micro-conflict Resolution Toolkit
Desmond Sherlock
 
Criminology_and_Security_Studies_Syllabus.pdf
MOHAMED HERSI FARAH
 

Building the Professional of 2020: An Approach to Business Change Process Integration (

  • 1. Building the Professional of 2020: An A h t B i ChApproach to Business Change Process Integration Change Risk Assessment Model: Results Discussion & AnalysisChange Risk Assessment Model: Results Discussion & Analysis Harris Apostolopoulos BEng(Hons), MSc, MBA, PhDc City University London 31 May 2013
  • 2. CRAM (Change Risk Assessment Model) is a novel model About CRAM (Change Risk Assessment Model) is a novel model approach which can significantly contribute to the missing formality of business models especially in the change(s) risk assessment area. Project Management has long established the need for risk management techniques to be utilised in the succinct definition of associated risks in projects and agreement on countervailingassociated risks in projects and agreement on countervailing actions as an aim to reduce scope creep, increase the probability of on-time and in-budget delivery. U t ll d h dl f i d l itUncontrolled changes, regardless of size and complexity, can certainly pose as risks, of any magnitude, to projects and affect project success or even an organisation’s coherence.
  • 3. CCRAM’s Processes • CRAM is composed of three interrelated processes (steps) which are continually recorded and monitored. CRAM’s processes accomplish specific risk objectives (identification, assessment, monitor & control) which are applied to projects or at a greater extend to business environments with a view to facilitate and control change. Risk IdentificationRisk Identification Risk Monitoring &  Control Risk Assessment Figure 1: CRAM’s Triple Processes
  • 4. CCRAM’s Hierarchy • CRAM hierarchical tree consists of one (1) core (root) node, eight (8) parent nodes, five (5) child nodes and its respective sixty one (61) attributes Forrespective sixty-one (61) attributes. For example, ‘Communication’ parent node consists of seven (7) risk attributes (sub-factors). • Depending on the scope and deliverables of a project, CRAM’s nodes and related risk attributes hierarchy per level can change so as to accommodate more of fewer criteria. Figure 2: CRAM’s Hierarchy Tree
  • 6. A dAgenda Significance11 22 CRAM Overview22 33 Analysis of ResultsAnalysis of Results 44 Open Discussion 55 Summary
  • 7. Analytical Hierarchy Process (AHP) • Analytic Hierarchy Process (AHP) is an established and structured hierarchical pairwise• Analytic Hierarchy Process (AHP) is an established and structured hierarchical pairwise process for making complex decisions that helps users sort out the "best" decision for their challenge. • Sets priorities being a systematic method for comparing a list of objectives leading to a• Sets priorities being a systematic method for comparing a list of objectives leading to a decision; utilising pairwise comparisons; eigenvalues and eigenvector.
  • 8. Weighting Scale • In order to able to quantify the respondents replies a relative weights mapping scale is• In order to able to quantify the respondents replies, a relative weights mapping scale is used, for example:
  • 9. Weighting Scale (cont.) • A typical pair wise comparison matrix is seen below (diagonal is always completed by• A typical pair wise comparison matrix is seen below (diagonal is always completed by 1’s): • When comparing the elements together the smaller one to be compared is consideredWhen comparing the elements together, the smaller one to be compared is considered to be the unit and the larger one is assessed to be so many times more than that it, using the intensity of feeling and translating it to the numerical value.
  • 10. Weighting Scale (cont.) A t i l i i i t i i b l (di l i l l t d b• A typical pair wise comparison matrix is seen below (diagonal is always completed by 1’s): • When comparing the elements together, the smaller one to be compared is considered to be the unit and the larger one is assessed to be so many times more than that it, using the intensity of feeling and translating it to the numerical value.
  • 11. AHP Calculations 1 Let Aij equals the intensity of relative importance between criterion i and criterion j1. Let Aij equals the intensity of relative importance between criterion i and criterion j , as defined in previous with: 2. Compute , the sum of each column of A 3 Normalize A by dividing each element Aij in the comparison matrix A by Aj3. Normalize A by dividing each element Aij in the comparison matrix A by Aj 4. Compute the weight of criterion i Step 3 :(normalisation), actually permits meaningful comparison among elements. Step4:yields the percentage of overall relative priorities, or preferences. or preferences).
  • 12. AHP Calculations Example The numbers in the table represent the relative importance between the criteria ForThe numbers in the table represent the relative importance between the criteria. For instance, the relative importance of criterion. For example: the relative importance of criterion 1 versus criterion 3 is 5 and between criterion 3 and criterion 1 it is 1/5. This indicates that criterion 1 is strongly important compared with criterion3 The numbers in the weights column show the relative weightscompared with criterion3. The numbers in the weights column show the relative weights of the corresponding criteria. To evaluate the credibility of the estimated weights, Saaty (1980, 1983) proposed an eigenvector which is considered a theoretically and practically proven methodeigenvector which is considered a theoretically and practically proven method for evaluating the credibility of the weights.
  • 13. Credibility of Weights – Eigenvectors 1 Calculate the maximum eigenvalue λ of the pair-wise comparison matrix A;1. Calculate the maximum eigenvalue λmax of the pair-wise comparison matrix A; After computing the nth root of the products of the values in each row, λmax can be found as follows. The priority vector is the nth root divided by the sum of the nth root values. λmax = Sum of Priority Row Priority Row = (sum of the row value) x Priority vector 2. Compute the consistency index (C.I.) defined by Saaty as: If a matrix [A] which represents the pairwise comparisons elements is absolutely consistent then it should be equal to the the matrix which denotes the ratios of theconsistent, then it should be equal to the the matrix which denotes the ratios of the weights matrix [W]. In effect if A = W , then λmax = n The weights (w1...n) which can be obtained by using the eigenvectors, should be positive and normalized, in effect satisfy the reciprocity property.
  • 14. Credibility of Weights – Eigenvectors (cont.) N id d th t th i b l t i t th λ i ff t thi l l fNow, provided that there is no absolute consistency then, λmax > n, in effect this level of inconsistency has to be measured. For this reason Saaty, defined the consistency ratio (CR). 3 C l l t th i t ti (C R )3. Calculate the consistency ratio (C.R.) C R = C. I/R.I h th d i d (R I ) f diff t b bt i d fwhere the random index (R.I.) for different n can be obtained from:
  • 15. Random Index (RI) Random Index (RI) is the average of (CI) for random matrices using the Saaty scaleRandom Index (RI) is the average of (CI) for random matrices using the Saaty scale. 500 random reciprocal n x n matrices were generated for n = 3 to n = 15 using the 1 to 9 scale. CR in a sense is normalised as a value as it is divided by the arithmetic mean of random consistency indexes (RI)random consistency indexes (RI).
  • 16. Consistency Ratio (CR) After a lot of experiments Alonso & Lamata (2006) concluded to the following calculationAfter a lot of experiments Alonso & Lamata (2006) concluded to the following calculation of consistency ratio (CR) as better results can be obtained: The maximum eigenvalue, based on Saaty, can be determined by raising each random matrix to increasing powers and normalizing the result until the process converged. The consistency index was then computed on each matrix for n = 1 through n = 15consistency index was then computed on each matrix for n = 1 through n = 15. As a rule of thumb, a value of C.R. ≤ 0.1 is typically considered acceptable. In other word inconsistency is permitted in AHP as long as it does not exceed the ratio ofIn other word inconsistency is permitted in AHP as long as it does not exceed the ratio of 0.1. Nevertheless, AHP is flexible enough that can trace the inconsistent elements and reform the matrix where required; taking into account that changes in the hierarchy or judgements may lead to changes in the outcome. If CR equals 0 then that means that the judgments are perfectly consistent..
  • 17. Further Examples (Consolidated) k = 3 (number of participants)k = 3 (number of participants) n = 3 (number of criteria), with respective pairwise values as seen below:
  • 18. Further Examples (cont.) For the consolidated matrix taking as an example the pairwise comparison of nFor the consolidated matrix, taking as an example the pairwise comparison of n1,2 (shaded light gray) then: All remaining elements of the consolidated matrix as calculated with the use of geometric mean formula. So:So:
  • 19. Respondent’s Background Figure 3: PM Methodology Use Figure 4: PM Experience
  • 20. ( )Respondent’s Background (cont.) Figure 5: PM Team Members Figure 6: Current Industry
  • 21. • Leadership: Project success is accounted in many ways to strong leadership and commitment to Leadership • Leadership: Project success is accounted in many ways to strong leadership and commitment to project scope and objectives. Active leadership remains important throughout the entire project lifecycle, with the application of skills and determinacy to succeed. Therefore, efficient resource management is necessary to complete each task in its predefined priority. Senior management’s accountability is key to effective decision making in the context of ‘firm but fair’ handling, to inspire and lead the project team in achieving high performance levels and overall high adaptation rate to proposed and authorised changes. Figure 7: Leadership's Risk Attributes Process
  • 22. C • Communication: Refers to the exchange of ideas or information among stakeholders e g project Communication • Communication: Refers to the exchange of ideas or information among stakeholders e.g. project manager, team members, board of directors, which are related to change and associated risks. The more complex the organisational structure or the proposed changes, the more communication channels have to be engaged. Effective communication is a bi-directional activity which has to be controlled and monitored. Communication is an important business environment factor incorporating cultural values) as project’s success is highly dependent on communication. Figure 8: Communication's Risk Attributes
  • 23. C • Culture: Collection (but not limited to) of beliefs attitudes core values ways of acting and Culture • Culture: Collection (but not limited to) of beliefs, attitudes, core values, ways of acting and thinking shared among members or organisations. Culture can impact the way of business conduction, decision making process, communication attitude and in effect influence project success. A supportive, knowledge sharing organisational culture can be enough ‘risk taking’ so as to match complicated project’s scope and objectives with success. A risk averse business culture might be problematic against accepting proposed changes which in turn, might cause problems to over decision making, communication and leadership of the project. Figure 9: Culture's Risk Attributes
  • 24. • Resistance: Change is a time consuming (transitional) and risky process often resisted by Resistance • Resistance: Change is a time consuming (transitional) and risky process, often resisted by employees. If changes are not communicated in the right way, then team members might feel threatened and undervalued. Because change actually ‘changes’ the way things used to operate in projects, resistance is frequently observed as a phenomenon which might jeopardise project’s success. Feeling anxious which is associated to anticipated changes is more or less normal, nevertheless the project processes have to run as planned. Figure 10: Resistance's Risk Attributes
  • 25. • Requirements: Conditions often dictated by the project’s user which the deliverables Requirements • Requirements: Conditions often dictated by the project s user which the deliverables of the project should meet. Any non conformance to customer’s requirements may lead to partially or full unacceptance of the project’s deliverables. Change requirements have to be documented and closely monitored from start till end of the projectproject. Figure 11: Requirement's Risk Attributes
  • 26. ( Monitoring • Monitoring: The change process monitoring should be continuous (but have an end at some point), involving benchmarking, milestones establishment, Key Performance Indicators (KPIs) and proper feedback. The end at some point, may become unnecessary for a reason e.g. if the change becomes obsolete and does not serve any purpose anymore. Figure 12: Monitoring's Risk Attributes
  • 27. / • Flexibility (Adaptation): Refers to the ability to affect changes and to the level which are Flexibility / Adaptation • Flexibility (Adaptation): Refers to the ability to affect changes, and to the level which are adaptable to the project scope. Flexibility is also related to the level of quick response to change. For example, there are cases where time is limited and quick decision making is required. Since not all organisations are adaptable to changes the responsiveness to change is an overall added value. Changes process flexibility results from ability to embed changes in project management policies and procedures; sometimes proactively in response to anticipated changes in the project life cycle. Figure 13: Flexibility's Risk Attributes
  • 28. • Project Management Team (PMT): Project team members who are directly involved Project Management Team • Project Management Team (PMT): Project team members who are directly involved in project management activities, processes and in effect ‘execute’ the project within defined scope and objectives. Figure 14: PMT’s Risk Attributes
  • 29. f Performance: Based on the achievement of preset metrics such as KPI’s (Key Performance • Performance: Based on the achievement of preset metrics such as KPI’s (Key Performance Indicators), Balanced Score Cards, KSFs, (Key Success Factors), 360, SLAs (Service Level Agreements); assessing measurement and trends to effect processes improvement and goals. Figure 15: Performance’s Risk Attributes
  • 30. • Motivation: Motivation can inspire and encourage individuals (create value) or Motivation • Motivation: Motivation can inspire and encourage individuals (create value) or groups of people who constitute the project management team to cope with the changes strategy and increase their overall performance. If motivation is weak then this might have serious effects on the project constraints which consequently might lead to project failure Effectively motivation can be seen also as a driver forlead to project failure. Effectively, motivation can be seen also as a driver for successful project management. Figure 16: Motivation’s Risk Attributes
  • 31. • Appraisal: Assessing the performance of employees against agreed change targets Appraisal • Appraisal: Assessing the performance of employees against agreed change targets and consequently to project’s deliverables. Appraisals are better conducted on a systematic, periodic basis. In such a way individual’s job performance and productivity will be assessed in relation to certain pre-established criteria and organisational project change objectivesorganisational project change objectives. Figure 17: Appraisal’s Risk Attributes
  • 32. • Rewards: Tangible and/or intangible benefits given or received in recompense for worthy Rewards • Rewards: Tangible and/or intangible benefits given or received in recompense for worthy behaviour, for example after the successful result of change/s have been acknowledged. In many cases rewards may lead to internal team member’s competition which up to a point may be considered healthy. People who will place change effort on their priorities list, and especially those who will succeed change goals can be rewarded with benefits. The reward, if any, should not be an incentive for competition among team members rather than for effective cooperation and goals and performance accomplishments. Figure 18: Reward’s Risk Attributes
  • 33. • Training: Training can be regarded as the acquisition of knowledge skills and competencies as a Training • Training: Training can be regarded as the acquisition of knowledge, skills, and competencies as a result of teaching and course taking. Irrespective of contemporary project management framework followed, change management training, can be seen as an overall advantage (value) since the knowledge gained is not only specific but necessary to identify, plan and validate changes, tackle risks in a structured and documented manner. Figure 19: Training’s Risk Attributes
  • 34. C O • Successful Change Management: Change management mostly observed and Change Risk Overall Assessment • Successful Change Management: Change management mostly observed and utilised as an integrated process within project management, is a rational process for exploring decision and behaviour alternatives in an attempt to realign the course of “derailed” deliverables due to change and ensure project success. Figure 20: Change Risk Attributes
  • 35. S Depending on the scope and deliverables of a project, CRAM’s nodes and related risk attributes hierarchy per level can be changed so as to accomm CRAM as a novel model approach has the capacity to define the internal dynamics of change management within project management eliciting also risk cause-and-effect relationships. Summary 11 Depending on the scope and deliverables of a project, CRAM’s nodes and related risk attributes hierarchy per level can be changed so as to accommodate more of fewer criteria. Depending on the scope and deliverables of a project, CRAM’s nodes and related risk attributes hierarchy per level can be changed so as to accommodate more of fewer criteria. project management eliciting also risk cause and effect relationships.11 22 A functional hierarchy is constructed so as to decompose the complex system in smaller criteria or attributes in a logical and simpler way. CRAM allows users to describe a problem as they see it, refine the complexity and structure a hierarchy of attributes.CRAM allows users to describe a problem as they see it, refine the complexity and structure a hierarchy of attributes.33 44 The only restriction on the hierarchic arrangement of elements is that any element in one level must be capable ofThe only restriction on the hierarchic arrangement of elements is that any element in one level must be capable of g p y A hierarchical ‘tree like’ graphical model representation can be easily interpreted being capable of representing probabilistic relationships among a set of variables and associated attributes,55 Can be applied to variety of industries / projects irrespective of size and complexity.Can be applied to variety of industries / projects irrespective of size and complexity. y g y being related to some elements in the next higher level, which serves as a criterion for assessing the relative impact of elements in the level below. . y g y being related to some elements in the next higher level, which serves as a criterion for assessing the relative impact of elements in the level below. . 66 77
  • 36. “I do not believe you can do today’s job with yesterday’s methods and be in business tomorrow” Nelson Jackson Building the Professional of 2020: An Approach toBuilding the Professional of 2020: An Approach to Business Change Process Integration Thank You! Questions? [email protected] [email protected] Research conducted at City University London