The document provides a detailed description of the proposed Nicaragua Canal Project, including:
- The canal would span 275.5 km from the Pacific to Caribbean coasts of Nicaragua, crossing Lake Nicaragua.
- Key facilities include two locks, ports, dredge disposal areas, excavated material placement areas, a dam, dikes, and breakwaters.
- Associated infrastructure includes roads, bridges, power lines, quarries, cement plants, and improvements to existing ports.
- Construction is planned over 5-7 years and will require extensive earthworks, dredging, and materials transport. Operations will require ship transit management and maintenance dredging.