Project Budget
Team: Reckless 7
Institute of Information Technology
University of Dhaka
25 November, 2016
1
Contents
1. Project Budget Management ........................................................................2
2. Defining The Budget ......................................................................................3
2.1 Resource Requirements .............................................................................4
2.2 Budget Estimate.........................................................................................4
2.3 Budget Development .................................................................................5
2.4 Budget Approval.........................................................................................6
3. Executing the Budget .....................................................................................6
3.1 Budget Baseline..........................................................................................6
3.2 Publish Budget ...........................................................................................6
3.3 Budget Execution .......................................................................................7
4. Budget Control...............................................................................................7
4.1 Budget Reporting .......................................................................................7
4.2 Earned Value Management........................................................................8
4.3 Budget Analysis..........................................................................................8
5. Budget Update...............................................................................................9
5.1 Budget Changes .........................................................................................9
5.2 Corrective Actions....................................................................................10
5.3 Communicate Changes.............................................................................10
2
1. Project Budget Management
A project budget is the total sum of money allocated for the particular purpose of the
project for a specific period of time. The goal of budget management is to control
project costs within the approved budget and deliver the expected project goals.
Our definition of a successful project is one that meets four success criteria: that the
project’s scope is delivered on schedule, it is delivered within budget and, once
delivered, it meets the quality expectations of the sponsor and stakeholders.
The focus of this chapter is on managing and controlling the project budget
throughout the entire project life cycle while relating budget control to the other
success criteria.
Budget management consists of a series of tasks and steps designed to help manage
the costs of the project, the steps are:
 Defining the Budget
 Executing the Budget
 Controlling the Budget
 Updating the Budget
Inputs: Inputs for the project budget management include the following
documents or sources of information:
 WBS
 Project contract or initial budget
 Resource requirements
 Resource cost estimates
 Activity duration estimates
 Historical information
 Market conditions
 Sponsor and organization policies
Outputs: The project team will use the above information to develop three
important documents for the project:
 Cost estimates by activity
 the Project Budget
 the Budget Variance Report
3
Inputs Process Outputs
 WBS
 Resource
requirements
 Cost estimates
 Schedule
 Historical information
 Market condition
 Policies
 Plan - Define and estimate
the resource requirements
and develop budget
 Do – Obtain approval, and
publish budget, authorize
expenses
 Check –Budget control and
performance analysis
 Adapt – Update budget, set
corrective
actions
 Project Budget
Baseline
 Budget variance
report
 Budget updates
Budgeting serves as a control mechanism where actual costs can be compared with
and measured against the budget. The budget is often a fairly set parameter in the
execution of the project. When a schedule begins to slip, cost is proportionally
affected. When project costs begin to escalate, the project manager should revisit
the Project Plan to determine whether scope, budget, or schedule needs adjusting.
To develop the budget, the applicable cost factors associated with project tasks are
identified. The development of costs for each task should be simple and direct and
consist of personal resource, material, and other direct costs. Cost of performing a
task is directly related to the personnel assigned to the task, the duration of the task,
and the cost of any non-personal items required by the task.
2. Defining the Budget
The project manager is responsible to estimate the budget required to complete
project activities. The Project Manager should allocate all costs to project activities,
and all aspects of the project, including the cost of internal and external human
resources, equipment, travel, materials and supplies, should be incorporated. The
budget should be much more detailed and more accurate than it was on the project
proposal
The Project Manager can use manual or automated tools to generate the budget
estimate. The budgeting tools may be simple spreadsheets or complex budget
estimating tool. For historical purposes, and to enable the budget to be refined, the
Project Manager should always maintain notes on how this budget was derived. Cost
4
estimating checklists help to ensure that all preliminary budgeting information is
known and all bases are covered. The Project Manager must also include in the
budget the cost of both the human resources and the equipment and materials
required to perform the work. The method by which staff and products will be
acquired for the project will directly affect the budgeting process.
As the budget estimate is being developed, additional tasks may be identified
because the work is being further defined. It may be necessary to update the WBS
and the project schedule to include the activities identified during budget estimating,
such as equipment, materials, and other non-human resources.
2.1 Resource Requirements
Resource requirements involve determining what resources (people, equipment,
services, and material) and the quantities of those resources are required to
complete the project.
The projects’ WBS, scope statement, historical information, resource information,
and policies are inputs used to determine the resources for the project. The main
output is a list of resources requirements that provides the basis for budget
estimating and budget controls, and provide valuable information to the project
resource management process.
Human resources/Project Staffing
The project will develop a list of the human resource requirements detailing the
expertise level, areas of experience in designing, programming, testing. This
information will be used in the Resource management process to develop the project
team for Researchcolab.com project.
Equipment and Material resources
Equipment includes all the specialized tools needed by the project, from logistic
support to Laptop, desktop, premises and utility.
2.2 Budget Estimate
Once all project requirements have been documented, the next step is to determine
the costs of each requirement which will result in the creation of the project budget.
5
A cost estimate, which is the process to approximate the costs that the project will
spend to get or use the project resources.
Work hour breakdown
As with developing a project schedule, documenting assumptions made while
developing the project budget is critical to the success of the project. Without clear
documentation of these assumptions, tracking the budget is not only difficult but
risky
2.3 Budget Development
The project budget is used to communicate what amounts will spent on categories of
resources within a given time period.
Total persons working 7
Work hour per person per day 1
Total working days 60
Total work hours per person 60
Work hours in total 420
Type Sector Breakdown Frequency Amount (BDT)
Opex
Project staffing
Total work hours 420
Daily 63,000/= BDT
Cost per person per
hour
150/= BDT
Logistic
Transport 1,000/= BDT
Ongoing 11,500/= BDT
Report Printing 1,500/= BDT
Web hosting 9,000/= BDT
Utility
Internet bills (7
person, 2 months)
7,000/= BDT
Ongoing 7,000/=
Miscellaneous Ongoing 2,000/=
Capex
Laptop Laptop computers 7 Pcs One time 2,80,000/=
Desktop Desktop computers 3 Pcs One time 1,20,000/=
6
2.4 Budget Approval
The final steps in estimating the budget is to get approval. The completed project
budget should be reviewed by the project team and be reviewed by the project
sponsor. Once the project budget has been completed the next steps is to get
approval for the project budget, this occurs at three times during the project
lifecycle- during project negotiations with the sponsor which lead to the contact
budget, during the planning phase of the project when the project budget is
developed in more detail, following the project’s chart of accounts, and becomes the
baseline budget.
Approval of the project budget can result in negotiations between the project team
and the sponsor, depending on the size of the budget these negotiations can take
some time before the budget is approved and a contract is signed.
3. Executing the Budget
In this section we will describe the budget in project execution.
3.1 Budget Baseline
Once the project budget has been reviewed and approved the next step is to create a
budget baseline, the baseline is a time-phased budget that project managers use to
measure and monitor budget performance. The budget baseline will be used to
control the budget using the Earned Value calculations to determine how the project
is performing according to the progress made
3.2 Publish Budget
The approved budget needs to be communicated to all people that will use it to
monitor, control and make decisions based on the information of the budget. The list
of people comes from the team/stakeholder communication mentioned in the
project communication management plan.
Premises Ongoing 2,40,000/=
Total anticipated costs 7,23,500 /=
7
3.3 Budget Execution
Executing the budget is the action of authorizing the expenses approved on the
project budget, the project manager then initiates to carry the activities that lead to
form project team, purchase of equipment, materials and services, all according to a
project procurement plan developed during the project planning. This step occurs
after the budget has been approved and the project authorized to start its activities
according to the project plan.
4. Budget Control
Monitoring and controlling the project budget ensures that only the appropriate
project changes are included in the budget baseline, that information about
authorized changes are communicated and corrective actions are taken by project
manager. The action of budget control is also a process of managing the budget.
Budget management is the process by which costs or expenses incurred on the
project are formally identified, approved and paid. Purchase order forms are
completed for each set of related project expenses such as staffing, equipment and
materials costs. Depending on the authorization level the purchase order forms are
approved and recorded by the project manager for tracking, sponsor reporting and
auditing purposes.
4.1 Budget Reporting
The typical report contains a list of all budget accounts (COA) and columns that list
the budget baseline, the cumulative expenses to date, the balance to date and the
burn ration or how the budget is spend according to the yearly budget plan. Below is
an example of a budget report:
 Expense Reports, reports provide the expenses to date by account, project
name and
funding code.
 Variance Reports, show the difference between what has been expensed and
the
approved budget, the balance for each account.
8
 Burn Ratio Reports, shows the rate at which the project is using the budget
according
to the original plan, a quick method to see if the project budget is on track.
4.2 Earned Value Management
Performance of the project will be measured using Earned Value Management. The
following four Earned Value metrics is used to measure to projects cost performance:
 Schedule Variance (SV)
 Cost Variance (CV)
 Schedule Performance Index (SPI)
 Cost Performance Index (CPI)
If the Schedule Performance Index or Cost Performance Index has a variance of
between 0.1 and 0.2 the Project Manager must report the reason for the exception.
If the SPI or CPI has a variance of greater than 0.2 the Project Manager must report
the reason for the exception and provide management a detailed corrective plan to
bring the projects performance back to acceptable levels.
Performance Measure Yellow Red
Schedule Performance Index (SPI) Between 0.9 and 0.8
or Between 1.1 and
1.2
Less Than 0.8 or
Greater than 1.2
Cost Performance Index (CPI) Between 0.9 and 0.8
or Between 1.1 and
1.2
Less Than 0.8 or
Greater than 1.2
4.3 Budget Analysis
Identify the causes for the deviations from plan. Major deviations from the budget
baseline need to be analysed to determine what caused the difference so that steps
can be taken to prevent the situation from happening again in the future, or with
similar projects.
9
 Forecasting
Earned Value enables the project manager to forecast the probable final cost and
schedule results on the project. With Earned Value, the project does not have to wait
until it is almost complete to know that it has a cost problem. Earned Value gives a
project manager an “early warning” signal in time to take corrective action, in time to
influence the final results by taking corrective actions.
The Control Thresholds for this project is a CPI or SPI of less than 0.8 or greater than
1.2. If the project reaches one of these Control Thresholds a Cost Variance
Corrective Action Plan is required. The Project Manager will present the Project
Sponsor with options for corrective actions within five business days from when the
cost variance is first reported. Within three business days from when the Project
Sponsor selects a corrective action option, the Project Manager will present the
Project Sponsor with a formal Cost Variance Corrective Action Plan. The Cost
Variance Corrective Action Plan will detail the actions necessary to bring the project
back within budget and the means by which the effectiveness of the actions in the
plan will be measured.
5. Budget Update
Budget update for ResearchColab project is described bellow.
5.1 Budget Changes
Updates to the budget come from approved changes to the budget. For most
projects changes to the budget need to be approved by the sponsor, in some
instances the sponsor can give the project a small percentage that the project can
use to cover small budget modifications
It is important that the project manager understands the sponsor contract clauses
and monitors, with special attention the accounts or budget items that have
restrictions. Not doing so may result in losses to the project.
10
5.2 Corrective Actions
If the project is under or over budget of the defined limit then the project manager
needs to take corrective actions to bring the budget back on track, these actions may
include trade-offs that will need to be discussed with sponsor, trade-off include
reducing the scope or lowering the quality. Corrective actions may include the use of
alternative options to produce the similar output using different inputs, the project
manager will implement the corrective actions and monitor their performance to see
if they are effective in reducing the project expenses and help bring the project back
on track. Corrective actions need to be consulted with the project team so that
changes are implemented.
5.3 Communicate Changes
Changes to the budget need to be communicated and incorporated on the system
that track change control. Communicating the changes of the budget to the team
member that will use the information helps reduce the chances that work will be
done on activities that have been either cancelled or postponed.
Ad

More Related Content

What's hot (20)

Chap 6 Developing A Project Plan
Chap 6 Developing A Project PlanChap 6 Developing A Project Plan
Chap 6 Developing A Project Plan
project management
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
Reetesh Gupta
 
Chap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management planChap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management plan
Anand Bobade
 
Types of project
Types of projectTypes of project
Types of project
akshay jain
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project management
Jared C. Powell
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project management
Jared C. Powell
 
Lecture 1. general introduction to project management
Lecture 1. general introduction to project management Lecture 1. general introduction to project management
Lecture 1. general introduction to project management
Dania Abdel-aziz
 
Project control
Project controlProject control
Project control
monisha pattnaik
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
Ajeesh Mk
 
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Tùng Trần Thanh
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management -
dyaksa hanindito
 
Project Costs, Budgeting and Appraisal
Project Costs, Budgeting and AppraisalProject Costs, Budgeting and Appraisal
Project Costs, Budgeting and Appraisal
Jude Iheanacho
 
Project human resources management
Project human resources managementProject human resources management
Project human resources management
Firmansyah Ashari
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project management
Shadina Shah
 
Project Cost & Schedule Integration Lessons Learnt
Project Cost & Schedule Integration Lessons LearntProject Cost & Schedule Integration Lessons Learnt
Project Cost & Schedule Integration Lessons Learnt
PMA Consultants
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
Agus Suhanto
 
Project Monitoring And Controlling
Project Monitoring And ControllingProject Monitoring And Controlling
Project Monitoring And Controlling
Tom Milner
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
mohamed elashri
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
Ahmed Rami Elsherif, PMP, ITBMC
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1
Anand Bobade
 
Chap 6 Developing A Project Plan
Chap 6 Developing A Project PlanChap 6 Developing A Project Plan
Chap 6 Developing A Project Plan
project management
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
Reetesh Gupta
 
Chap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management planChap 4.2 Develop Project Management plan
Chap 4.2 Develop Project Management plan
Anand Bobade
 
Types of project
Types of projectTypes of project
Types of project
akshay jain
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project management
Jared C. Powell
 
5 phases of project management
5 phases of project management5 phases of project management
5 phases of project management
Jared C. Powell
 
Lecture 1. general introduction to project management
Lecture 1. general introduction to project management Lecture 1. general introduction to project management
Lecture 1. general introduction to project management
Dania Abdel-aziz
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
Ajeesh Mk
 
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Tùng Trần Thanh
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management -
dyaksa hanindito
 
Project Costs, Budgeting and Appraisal
Project Costs, Budgeting and AppraisalProject Costs, Budgeting and Appraisal
Project Costs, Budgeting and Appraisal
Jude Iheanacho
 
Project human resources management
Project human resources managementProject human resources management
Project human resources management
Firmansyah Ashari
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project management
Shadina Shah
 
Project Cost & Schedule Integration Lessons Learnt
Project Cost & Schedule Integration Lessons LearntProject Cost & Schedule Integration Lessons Learnt
Project Cost & Schedule Integration Lessons Learnt
PMA Consultants
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
Agus Suhanto
 
Project Monitoring And Controlling
Project Monitoring And ControllingProject Monitoring And Controlling
Project Monitoring And Controlling
Tom Milner
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1
Anand Bobade
 

Similar to Software Project Management: Budget (20)

Construction company business plan
Construction company business planConstruction company business plan
Construction company business plan
farouq umar
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3
POOJA UDAYAN
 
Chapter Five project budget management.pptx
Chapter Five project budget management.pptxChapter Five project budget management.pptx
Chapter Five project budget management.pptx
SewaleAbate1
 
5.Chapter Five.pptx
5.Chapter Five.pptx5.Chapter Five.pptx
5.Chapter Five.pptx
AberraBeri
 
Project Management Life Cycle
Project Management Life CycleProject Management Life Cycle
Project Management Life Cycle
Reema
 
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET Journal
 
abate and h.pptx
abate and h.pptxabate and h.pptx
abate and h.pptx
BetshaTizazu1
 
The simplified project management process it-toolkits
The simplified project management process   it-toolkitsThe simplified project management process   it-toolkits
The simplified project management process it-toolkits
IT-Toolkits.org
 
construction-project-management-ppt-india-ppt.pptx
construction-project-management-ppt-india-ppt.pptxconstruction-project-management-ppt-india-ppt.pptx
construction-project-management-ppt-india-ppt.pptx
PR Engineering Dept,Govt.of Andhra Pradesh
 
Aaqib
AaqibAaqib
Aaqib
Aaqib Ismail
 
Good scheduling practice
Good scheduling practiceGood scheduling practice
Good scheduling practice
krunalchem
 
Project typed
Project typedProject typed
Project typed
Rahul
 
Communication 1
Communication 1Communication 1
Communication 1
Ujjwal Joshi
 
Project planning
Project planningProject planning
Project planning
Sutha Vincent
 
Mmi entrepreneurship 6
Mmi entrepreneurship 6Mmi entrepreneurship 6
Mmi entrepreneurship 6
gatecomro
 
Latest Microsoft Project 2013 for civil work planning.docx
Latest Microsoft Project 2013 for civil work planning.docxLatest Microsoft Project 2013 for civil work planning.docx
Latest Microsoft Project 2013 for civil work planning.docx
DejeneTsegaye6
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
SHAZEBALIKHAN1
 
software (1).pptx
software (1).pptxsoftware (1).pptx
software (1).pptx
ayanadamtew
 
Proposed project plan template
Proposed project plan templateProposed project plan template
Proposed project plan template
Michelle Joja
 
Microsoft Project 2013 training manual for civil engineering.docx
Microsoft Project 2013 training manual for civil engineering.docxMicrosoft Project 2013 training manual for civil engineering.docx
Microsoft Project 2013 training manual for civil engineering.docx
DejeneTsegaye6
 
Construction company business plan
Construction company business planConstruction company business plan
Construction company business plan
farouq umar
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3
POOJA UDAYAN
 
Chapter Five project budget management.pptx
Chapter Five project budget management.pptxChapter Five project budget management.pptx
Chapter Five project budget management.pptx
SewaleAbate1
 
5.Chapter Five.pptx
5.Chapter Five.pptx5.Chapter Five.pptx
5.Chapter Five.pptx
AberraBeri
 
Project Management Life Cycle
Project Management Life CycleProject Management Life Cycle
Project Management Life Cycle
Reema
 
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET Journal
 
The simplified project management process it-toolkits
The simplified project management process   it-toolkitsThe simplified project management process   it-toolkits
The simplified project management process it-toolkits
IT-Toolkits.org
 
Good scheduling practice
Good scheduling practiceGood scheduling practice
Good scheduling practice
krunalchem
 
Project typed
Project typedProject typed
Project typed
Rahul
 
Mmi entrepreneurship 6
Mmi entrepreneurship 6Mmi entrepreneurship 6
Mmi entrepreneurship 6
gatecomro
 
Latest Microsoft Project 2013 for civil work planning.docx
Latest Microsoft Project 2013 for civil work planning.docxLatest Microsoft Project 2013 for civil work planning.docx
Latest Microsoft Project 2013 for civil work planning.docx
DejeneTsegaye6
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
SHAZEBALIKHAN1
 
software (1).pptx
software (1).pptxsoftware (1).pptx
software (1).pptx
ayanadamtew
 
Proposed project plan template
Proposed project plan templateProposed project plan template
Proposed project plan template
Michelle Joja
 
Microsoft Project 2013 training manual for civil engineering.docx
Microsoft Project 2013 training manual for civil engineering.docxMicrosoft Project 2013 training manual for civil engineering.docx
Microsoft Project 2013 training manual for civil engineering.docx
DejeneTsegaye6
 
Ad

More from Minhas Kamal (20)

Digital Image Processing
Digital Image ProcessingDigital Image Processing
Digital Image Processing
Minhas Kamal
 
Deep Learning - Exploring The Magical World of Neural Network
Deep Learning - Exploring The Magical World of Neural NetworkDeep Learning - Exploring The Magical World of Neural Network
Deep Learning - Exploring The Magical World of Neural Network
Minhas Kamal
 
Machine Learning - Entering into The Wonderful Galaxy of Machine Learning
Machine Learning - Entering into The Wonderful Galaxy of Machine LearningMachine Learning - Entering into The Wonderful Galaxy of Machine Learning
Machine Learning - Entering into The Wonderful Galaxy of Machine Learning
Minhas Kamal
 
Artificial Intelligence - Staring at The Grand Universe of AI (1)
Artificial Intelligence - Staring at The Grand Universe of AI (1)Artificial Intelligence - Staring at The Grand Universe of AI (1)
Artificial Intelligence - Staring at The Grand Universe of AI (1)
Minhas Kamal
 
Final Project Report- Bengali Braille to Text Translator
Final Project Report- Bengali Braille to Text TranslatorFinal Project Report- Bengali Braille to Text Translator
Final Project Report- Bengali Braille to Text Translator
Minhas Kamal
 
Abstract- Bengali Braille to Text Translator
Abstract- Bengali Braille to Text TranslatorAbstract- Bengali Braille to Text Translator
Abstract- Bengali Braille to Text Translator
Minhas Kamal
 
Software Project Management: Testing Document
Software Project Management: Testing DocumentSoftware Project Management: Testing Document
Software Project Management: Testing Document
Minhas Kamal
 
Software Project Management: Change Control
Software Project Management: Change ControlSoftware Project Management: Change Control
Software Project Management: Change Control
Minhas Kamal
 
Software Project Management: Release Notes
Software Project Management: Release NotesSoftware Project Management: Release Notes
Software Project Management: Release Notes
Minhas Kamal
 
Software Project Management: Configuration Management
Software Project Management: Configuration ManagementSoftware Project Management: Configuration Management
Software Project Management: Configuration Management
Minhas Kamal
 
Software Project Management: Risk Management
Software Project Management: Risk ManagementSoftware Project Management: Risk Management
Software Project Management: Risk Management
Minhas Kamal
 
Software Project Management: Software Architecture
Software Project Management: Software ArchitectureSoftware Project Management: Software Architecture
Software Project Management: Software Architecture
Minhas Kamal
 
Software Project Management: Software Requirement Specification
Software Project Management: Software Requirement SpecificationSoftware Project Management: Software Requirement Specification
Software Project Management: Software Requirement Specification
Minhas Kamal
 
Software Project Management: Business Case
Software Project Management: Business CaseSoftware Project Management: Business Case
Software Project Management: Business Case
Minhas Kamal
 
Software Project Management: Project Initiation
Software Project Management: Project InitiationSoftware Project Management: Project Initiation
Software Project Management: Project Initiation
Minhas Kamal
 
Software Project Management: Project Charter
Software Project Management: Project CharterSoftware Project Management: Project Charter
Software Project Management: Project Charter
Minhas Kamal
 
Software Project Management Presentation Final
Software Project Management Presentation FinalSoftware Project Management Presentation Final
Software Project Management Presentation Final
Minhas Kamal
 
Software Requirements Specification on Bengali Braille to Text Translator
Software Requirements Specification on Bengali Braille to Text TranslatorSoftware Requirements Specification on Bengali Braille to Text Translator
Software Requirements Specification on Bengali Braille to Text Translator
Minhas Kamal
 
Project Proposal: Bengali Braille to Text Translation
Project Proposal: Bengali Braille to Text TranslationProject Proposal: Bengali Braille to Text Translation
Project Proposal: Bengali Braille to Text Translation
Minhas Kamal
 
Software Project Proposal: Bengali Braille to Text Translation
Software Project Proposal: Bengali Braille to Text TranslationSoftware Project Proposal: Bengali Braille to Text Translation
Software Project Proposal: Bengali Braille to Text Translation
Minhas Kamal
 
Digital Image Processing
Digital Image ProcessingDigital Image Processing
Digital Image Processing
Minhas Kamal
 
Deep Learning - Exploring The Magical World of Neural Network
Deep Learning - Exploring The Magical World of Neural NetworkDeep Learning - Exploring The Magical World of Neural Network
Deep Learning - Exploring The Magical World of Neural Network
Minhas Kamal
 
Machine Learning - Entering into The Wonderful Galaxy of Machine Learning
Machine Learning - Entering into The Wonderful Galaxy of Machine LearningMachine Learning - Entering into The Wonderful Galaxy of Machine Learning
Machine Learning - Entering into The Wonderful Galaxy of Machine Learning
Minhas Kamal
 
Artificial Intelligence - Staring at The Grand Universe of AI (1)
Artificial Intelligence - Staring at The Grand Universe of AI (1)Artificial Intelligence - Staring at The Grand Universe of AI (1)
Artificial Intelligence - Staring at The Grand Universe of AI (1)
Minhas Kamal
 
Final Project Report- Bengali Braille to Text Translator
Final Project Report- Bengali Braille to Text TranslatorFinal Project Report- Bengali Braille to Text Translator
Final Project Report- Bengali Braille to Text Translator
Minhas Kamal
 
Abstract- Bengali Braille to Text Translator
Abstract- Bengali Braille to Text TranslatorAbstract- Bengali Braille to Text Translator
Abstract- Bengali Braille to Text Translator
Minhas Kamal
 
Software Project Management: Testing Document
Software Project Management: Testing DocumentSoftware Project Management: Testing Document
Software Project Management: Testing Document
Minhas Kamal
 
Software Project Management: Change Control
Software Project Management: Change ControlSoftware Project Management: Change Control
Software Project Management: Change Control
Minhas Kamal
 
Software Project Management: Release Notes
Software Project Management: Release NotesSoftware Project Management: Release Notes
Software Project Management: Release Notes
Minhas Kamal
 
Software Project Management: Configuration Management
Software Project Management: Configuration ManagementSoftware Project Management: Configuration Management
Software Project Management: Configuration Management
Minhas Kamal
 
Software Project Management: Risk Management
Software Project Management: Risk ManagementSoftware Project Management: Risk Management
Software Project Management: Risk Management
Minhas Kamal
 
Software Project Management: Software Architecture
Software Project Management: Software ArchitectureSoftware Project Management: Software Architecture
Software Project Management: Software Architecture
Minhas Kamal
 
Software Project Management: Software Requirement Specification
Software Project Management: Software Requirement SpecificationSoftware Project Management: Software Requirement Specification
Software Project Management: Software Requirement Specification
Minhas Kamal
 
Software Project Management: Business Case
Software Project Management: Business CaseSoftware Project Management: Business Case
Software Project Management: Business Case
Minhas Kamal
 
Software Project Management: Project Initiation
Software Project Management: Project InitiationSoftware Project Management: Project Initiation
Software Project Management: Project Initiation
Minhas Kamal
 
Software Project Management: Project Charter
Software Project Management: Project CharterSoftware Project Management: Project Charter
Software Project Management: Project Charter
Minhas Kamal
 
Software Project Management Presentation Final
Software Project Management Presentation FinalSoftware Project Management Presentation Final
Software Project Management Presentation Final
Minhas Kamal
 
Software Requirements Specification on Bengali Braille to Text Translator
Software Requirements Specification on Bengali Braille to Text TranslatorSoftware Requirements Specification on Bengali Braille to Text Translator
Software Requirements Specification on Bengali Braille to Text Translator
Minhas Kamal
 
Project Proposal: Bengali Braille to Text Translation
Project Proposal: Bengali Braille to Text TranslationProject Proposal: Bengali Braille to Text Translation
Project Proposal: Bengali Braille to Text Translation
Minhas Kamal
 
Software Project Proposal: Bengali Braille to Text Translation
Software Project Proposal: Bengali Braille to Text TranslationSoftware Project Proposal: Bengali Braille to Text Translation
Software Project Proposal: Bengali Braille to Text Translation
Minhas Kamal
 
Ad

Recently uploaded (20)

How can one start with crypto wallet development.pptx
How can one start with crypto wallet development.pptxHow can one start with crypto wallet development.pptx
How can one start with crypto wallet development.pptx
laravinson24
 
Not So Common Memory Leaks in Java Webinar
Not So Common Memory Leaks in Java WebinarNot So Common Memory Leaks in Java Webinar
Not So Common Memory Leaks in Java Webinar
Tier1 app
 
Adobe Lightroom Classic Crack FREE Latest link 2025
Adobe Lightroom Classic Crack FREE Latest link 2025Adobe Lightroom Classic Crack FREE Latest link 2025
Adobe Lightroom Classic Crack FREE Latest link 2025
kashifyounis067
 
Automation Techniques in RPA - UiPath Certificate
Automation Techniques in RPA - UiPath CertificateAutomation Techniques in RPA - UiPath Certificate
Automation Techniques in RPA - UiPath Certificate
VICTOR MAESTRE RAMIREZ
 
Download Wondershare Filmora Crack [2025] With Latest
Download Wondershare Filmora Crack [2025] With LatestDownload Wondershare Filmora Crack [2025] With Latest
Download Wondershare Filmora Crack [2025] With Latest
tahirabibi60507
 
TestMigrationsInPy: A Dataset of Test Migrations from Unittest to Pytest (MSR...
TestMigrationsInPy: A Dataset of Test Migrations from Unittest to Pytest (MSR...TestMigrationsInPy: A Dataset of Test Migrations from Unittest to Pytest (MSR...
TestMigrationsInPy: A Dataset of Test Migrations from Unittest to Pytest (MSR...
Andre Hora
 
Adobe Illustrator Crack FREE Download 2025 Latest Version
Adobe Illustrator Crack FREE Download 2025 Latest VersionAdobe Illustrator Crack FREE Download 2025 Latest Version
Adobe Illustrator Crack FREE Download 2025 Latest Version
kashifyounis067
 
How to Optimize Your AWS Environment for Improved Cloud Performance
How to Optimize Your AWS Environment for Improved Cloud PerformanceHow to Optimize Your AWS Environment for Improved Cloud Performance
How to Optimize Your AWS Environment for Improved Cloud Performance
ThousandEyes
 
Expand your AI adoption with AgentExchange
Expand your AI adoption with AgentExchangeExpand your AI adoption with AgentExchange
Expand your AI adoption with AgentExchange
Fexle Services Pvt. Ltd.
 
Explaining GitHub Actions Failures with Large Language Models Challenges, In...
Explaining GitHub Actions Failures with Large Language Models Challenges, In...Explaining GitHub Actions Failures with Large Language Models Challenges, In...
Explaining GitHub Actions Failures with Large Language Models Challenges, In...
ssuserb14185
 
Get & Download Wondershare Filmora Crack Latest [2025]
Get & Download Wondershare Filmora Crack Latest [2025]Get & Download Wondershare Filmora Crack Latest [2025]
Get & Download Wondershare Filmora Crack Latest [2025]
saniaaftab72555
 
Landscape of Requirements Engineering for/by AI through Literature Review
Landscape of Requirements Engineering for/by AI through Literature ReviewLandscape of Requirements Engineering for/by AI through Literature Review
Landscape of Requirements Engineering for/by AI through Literature Review
Hironori Washizaki
 
Secure Test Infrastructure: The Backbone of Trustworthy Software Development
Secure Test Infrastructure: The Backbone of Trustworthy Software DevelopmentSecure Test Infrastructure: The Backbone of Trustworthy Software Development
Secure Test Infrastructure: The Backbone of Trustworthy Software Development
Shubham Joshi
 
Exploring Code Comprehension in Scientific Programming: Preliminary Insight...
Exploring Code Comprehension  in Scientific Programming:  Preliminary Insight...Exploring Code Comprehension  in Scientific Programming:  Preliminary Insight...
Exploring Code Comprehension in Scientific Programming: Preliminary Insight...
University of Hawai‘i at Mānoa
 
Requirements in Engineering AI- Enabled Systems: Open Problems and Safe AI Sy...
Requirements in Engineering AI- Enabled Systems: Open Problems and Safe AI Sy...Requirements in Engineering AI- Enabled Systems: Open Problems and Safe AI Sy...
Requirements in Engineering AI- Enabled Systems: Open Problems and Safe AI Sy...
Lionel Briand
 
Interactive odoo dashboards for sales, CRM , Inventory, Invoice, Purchase, Pr...
Interactive odoo dashboards for sales, CRM , Inventory, Invoice, Purchase, Pr...Interactive odoo dashboards for sales, CRM , Inventory, Invoice, Purchase, Pr...
Interactive odoo dashboards for sales, CRM , Inventory, Invoice, Purchase, Pr...
AxisTechnolabs
 
F-Secure Freedome VPN 2025 Crack Plus Activation New Version
F-Secure Freedome VPN 2025 Crack Plus Activation  New VersionF-Secure Freedome VPN 2025 Crack Plus Activation  New Version
F-Secure Freedome VPN 2025 Crack Plus Activation New Version
saimabibi60507
 
LEARN SEO AND INCREASE YOUR KNOWLDGE IN SOFTWARE INDUSTRY
LEARN SEO AND INCREASE YOUR KNOWLDGE IN SOFTWARE INDUSTRYLEARN SEO AND INCREASE YOUR KNOWLDGE IN SOFTWARE INDUSTRY
LEARN SEO AND INCREASE YOUR KNOWLDGE IN SOFTWARE INDUSTRY
NidaFarooq10
 
WinRAR Crack for Windows (100% Working 2025)
WinRAR Crack for Windows (100% Working 2025)WinRAR Crack for Windows (100% Working 2025)
WinRAR Crack for Windows (100% Working 2025)
sh607827
 
Maxon CINEMA 4D 2025 Crack FREE Download LINK
Maxon CINEMA 4D 2025 Crack FREE Download LINKMaxon CINEMA 4D 2025 Crack FREE Download LINK
Maxon CINEMA 4D 2025 Crack FREE Download LINK
younisnoman75
 
How can one start with crypto wallet development.pptx
How can one start with crypto wallet development.pptxHow can one start with crypto wallet development.pptx
How can one start with crypto wallet development.pptx
laravinson24
 
Not So Common Memory Leaks in Java Webinar
Not So Common Memory Leaks in Java WebinarNot So Common Memory Leaks in Java Webinar
Not So Common Memory Leaks in Java Webinar
Tier1 app
 
Adobe Lightroom Classic Crack FREE Latest link 2025
Adobe Lightroom Classic Crack FREE Latest link 2025Adobe Lightroom Classic Crack FREE Latest link 2025
Adobe Lightroom Classic Crack FREE Latest link 2025
kashifyounis067
 
Automation Techniques in RPA - UiPath Certificate
Automation Techniques in RPA - UiPath CertificateAutomation Techniques in RPA - UiPath Certificate
Automation Techniques in RPA - UiPath Certificate
VICTOR MAESTRE RAMIREZ
 
Download Wondershare Filmora Crack [2025] With Latest
Download Wondershare Filmora Crack [2025] With LatestDownload Wondershare Filmora Crack [2025] With Latest
Download Wondershare Filmora Crack [2025] With Latest
tahirabibi60507
 
TestMigrationsInPy: A Dataset of Test Migrations from Unittest to Pytest (MSR...
TestMigrationsInPy: A Dataset of Test Migrations from Unittest to Pytest (MSR...TestMigrationsInPy: A Dataset of Test Migrations from Unittest to Pytest (MSR...
TestMigrationsInPy: A Dataset of Test Migrations from Unittest to Pytest (MSR...
Andre Hora
 
Adobe Illustrator Crack FREE Download 2025 Latest Version
Adobe Illustrator Crack FREE Download 2025 Latest VersionAdobe Illustrator Crack FREE Download 2025 Latest Version
Adobe Illustrator Crack FREE Download 2025 Latest Version
kashifyounis067
 
How to Optimize Your AWS Environment for Improved Cloud Performance
How to Optimize Your AWS Environment for Improved Cloud PerformanceHow to Optimize Your AWS Environment for Improved Cloud Performance
How to Optimize Your AWS Environment for Improved Cloud Performance
ThousandEyes
 
Expand your AI adoption with AgentExchange
Expand your AI adoption with AgentExchangeExpand your AI adoption with AgentExchange
Expand your AI adoption with AgentExchange
Fexle Services Pvt. Ltd.
 
Explaining GitHub Actions Failures with Large Language Models Challenges, In...
Explaining GitHub Actions Failures with Large Language Models Challenges, In...Explaining GitHub Actions Failures with Large Language Models Challenges, In...
Explaining GitHub Actions Failures with Large Language Models Challenges, In...
ssuserb14185
 
Get & Download Wondershare Filmora Crack Latest [2025]
Get & Download Wondershare Filmora Crack Latest [2025]Get & Download Wondershare Filmora Crack Latest [2025]
Get & Download Wondershare Filmora Crack Latest [2025]
saniaaftab72555
 
Landscape of Requirements Engineering for/by AI through Literature Review
Landscape of Requirements Engineering for/by AI through Literature ReviewLandscape of Requirements Engineering for/by AI through Literature Review
Landscape of Requirements Engineering for/by AI through Literature Review
Hironori Washizaki
 
Secure Test Infrastructure: The Backbone of Trustworthy Software Development
Secure Test Infrastructure: The Backbone of Trustworthy Software DevelopmentSecure Test Infrastructure: The Backbone of Trustworthy Software Development
Secure Test Infrastructure: The Backbone of Trustworthy Software Development
Shubham Joshi
 
Exploring Code Comprehension in Scientific Programming: Preliminary Insight...
Exploring Code Comprehension  in Scientific Programming:  Preliminary Insight...Exploring Code Comprehension  in Scientific Programming:  Preliminary Insight...
Exploring Code Comprehension in Scientific Programming: Preliminary Insight...
University of Hawai‘i at Mānoa
 
Requirements in Engineering AI- Enabled Systems: Open Problems and Safe AI Sy...
Requirements in Engineering AI- Enabled Systems: Open Problems and Safe AI Sy...Requirements in Engineering AI- Enabled Systems: Open Problems and Safe AI Sy...
Requirements in Engineering AI- Enabled Systems: Open Problems and Safe AI Sy...
Lionel Briand
 
Interactive odoo dashboards for sales, CRM , Inventory, Invoice, Purchase, Pr...
Interactive odoo dashboards for sales, CRM , Inventory, Invoice, Purchase, Pr...Interactive odoo dashboards for sales, CRM , Inventory, Invoice, Purchase, Pr...
Interactive odoo dashboards for sales, CRM , Inventory, Invoice, Purchase, Pr...
AxisTechnolabs
 
F-Secure Freedome VPN 2025 Crack Plus Activation New Version
F-Secure Freedome VPN 2025 Crack Plus Activation  New VersionF-Secure Freedome VPN 2025 Crack Plus Activation  New Version
F-Secure Freedome VPN 2025 Crack Plus Activation New Version
saimabibi60507
 
LEARN SEO AND INCREASE YOUR KNOWLDGE IN SOFTWARE INDUSTRY
LEARN SEO AND INCREASE YOUR KNOWLDGE IN SOFTWARE INDUSTRYLEARN SEO AND INCREASE YOUR KNOWLDGE IN SOFTWARE INDUSTRY
LEARN SEO AND INCREASE YOUR KNOWLDGE IN SOFTWARE INDUSTRY
NidaFarooq10
 
WinRAR Crack for Windows (100% Working 2025)
WinRAR Crack for Windows (100% Working 2025)WinRAR Crack for Windows (100% Working 2025)
WinRAR Crack for Windows (100% Working 2025)
sh607827
 
Maxon CINEMA 4D 2025 Crack FREE Download LINK
Maxon CINEMA 4D 2025 Crack FREE Download LINKMaxon CINEMA 4D 2025 Crack FREE Download LINK
Maxon CINEMA 4D 2025 Crack FREE Download LINK
younisnoman75
 

Software Project Management: Budget

  • 1. ResearchColab Project Budget Team: Reckless 7 Institute of Information Technology University of Dhaka 25 November, 2016
  • 2. 1 Contents 1. Project Budget Management ........................................................................2 2. Defining The Budget ......................................................................................3 2.1 Resource Requirements .............................................................................4 2.2 Budget Estimate.........................................................................................4 2.3 Budget Development .................................................................................5 2.4 Budget Approval.........................................................................................6 3. Executing the Budget .....................................................................................6 3.1 Budget Baseline..........................................................................................6 3.2 Publish Budget ...........................................................................................6 3.3 Budget Execution .......................................................................................7 4. Budget Control...............................................................................................7 4.1 Budget Reporting .......................................................................................7 4.2 Earned Value Management........................................................................8 4.3 Budget Analysis..........................................................................................8 5. Budget Update...............................................................................................9 5.1 Budget Changes .........................................................................................9 5.2 Corrective Actions....................................................................................10 5.3 Communicate Changes.............................................................................10
  • 3. 2 1. Project Budget Management A project budget is the total sum of money allocated for the particular purpose of the project for a specific period of time. The goal of budget management is to control project costs within the approved budget and deliver the expected project goals. Our definition of a successful project is one that meets four success criteria: that the project’s scope is delivered on schedule, it is delivered within budget and, once delivered, it meets the quality expectations of the sponsor and stakeholders. The focus of this chapter is on managing and controlling the project budget throughout the entire project life cycle while relating budget control to the other success criteria. Budget management consists of a series of tasks and steps designed to help manage the costs of the project, the steps are:  Defining the Budget  Executing the Budget  Controlling the Budget  Updating the Budget Inputs: Inputs for the project budget management include the following documents or sources of information:  WBS  Project contract or initial budget  Resource requirements  Resource cost estimates  Activity duration estimates  Historical information  Market conditions  Sponsor and organization policies Outputs: The project team will use the above information to develop three important documents for the project:  Cost estimates by activity  the Project Budget  the Budget Variance Report
  • 4. 3 Inputs Process Outputs  WBS  Resource requirements  Cost estimates  Schedule  Historical information  Market condition  Policies  Plan - Define and estimate the resource requirements and develop budget  Do – Obtain approval, and publish budget, authorize expenses  Check –Budget control and performance analysis  Adapt – Update budget, set corrective actions  Project Budget Baseline  Budget variance report  Budget updates Budgeting serves as a control mechanism where actual costs can be compared with and measured against the budget. The budget is often a fairly set parameter in the execution of the project. When a schedule begins to slip, cost is proportionally affected. When project costs begin to escalate, the project manager should revisit the Project Plan to determine whether scope, budget, or schedule needs adjusting. To develop the budget, the applicable cost factors associated with project tasks are identified. The development of costs for each task should be simple and direct and consist of personal resource, material, and other direct costs. Cost of performing a task is directly related to the personnel assigned to the task, the duration of the task, and the cost of any non-personal items required by the task. 2. Defining the Budget The project manager is responsible to estimate the budget required to complete project activities. The Project Manager should allocate all costs to project activities, and all aspects of the project, including the cost of internal and external human resources, equipment, travel, materials and supplies, should be incorporated. The budget should be much more detailed and more accurate than it was on the project proposal The Project Manager can use manual or automated tools to generate the budget estimate. The budgeting tools may be simple spreadsheets or complex budget estimating tool. For historical purposes, and to enable the budget to be refined, the Project Manager should always maintain notes on how this budget was derived. Cost
  • 5. 4 estimating checklists help to ensure that all preliminary budgeting information is known and all bases are covered. The Project Manager must also include in the budget the cost of both the human resources and the equipment and materials required to perform the work. The method by which staff and products will be acquired for the project will directly affect the budgeting process. As the budget estimate is being developed, additional tasks may be identified because the work is being further defined. It may be necessary to update the WBS and the project schedule to include the activities identified during budget estimating, such as equipment, materials, and other non-human resources. 2.1 Resource Requirements Resource requirements involve determining what resources (people, equipment, services, and material) and the quantities of those resources are required to complete the project. The projects’ WBS, scope statement, historical information, resource information, and policies are inputs used to determine the resources for the project. The main output is a list of resources requirements that provides the basis for budget estimating and budget controls, and provide valuable information to the project resource management process. Human resources/Project Staffing The project will develop a list of the human resource requirements detailing the expertise level, areas of experience in designing, programming, testing. This information will be used in the Resource management process to develop the project team for Researchcolab.com project. Equipment and Material resources Equipment includes all the specialized tools needed by the project, from logistic support to Laptop, desktop, premises and utility. 2.2 Budget Estimate Once all project requirements have been documented, the next step is to determine the costs of each requirement which will result in the creation of the project budget.
  • 6. 5 A cost estimate, which is the process to approximate the costs that the project will spend to get or use the project resources. Work hour breakdown As with developing a project schedule, documenting assumptions made while developing the project budget is critical to the success of the project. Without clear documentation of these assumptions, tracking the budget is not only difficult but risky 2.3 Budget Development The project budget is used to communicate what amounts will spent on categories of resources within a given time period. Total persons working 7 Work hour per person per day 1 Total working days 60 Total work hours per person 60 Work hours in total 420 Type Sector Breakdown Frequency Amount (BDT) Opex Project staffing Total work hours 420 Daily 63,000/= BDT Cost per person per hour 150/= BDT Logistic Transport 1,000/= BDT Ongoing 11,500/= BDT Report Printing 1,500/= BDT Web hosting 9,000/= BDT Utility Internet bills (7 person, 2 months) 7,000/= BDT Ongoing 7,000/= Miscellaneous Ongoing 2,000/= Capex Laptop Laptop computers 7 Pcs One time 2,80,000/= Desktop Desktop computers 3 Pcs One time 1,20,000/=
  • 7. 6 2.4 Budget Approval The final steps in estimating the budget is to get approval. The completed project budget should be reviewed by the project team and be reviewed by the project sponsor. Once the project budget has been completed the next steps is to get approval for the project budget, this occurs at three times during the project lifecycle- during project negotiations with the sponsor which lead to the contact budget, during the planning phase of the project when the project budget is developed in more detail, following the project’s chart of accounts, and becomes the baseline budget. Approval of the project budget can result in negotiations between the project team and the sponsor, depending on the size of the budget these negotiations can take some time before the budget is approved and a contract is signed. 3. Executing the Budget In this section we will describe the budget in project execution. 3.1 Budget Baseline Once the project budget has been reviewed and approved the next step is to create a budget baseline, the baseline is a time-phased budget that project managers use to measure and monitor budget performance. The budget baseline will be used to control the budget using the Earned Value calculations to determine how the project is performing according to the progress made 3.2 Publish Budget The approved budget needs to be communicated to all people that will use it to monitor, control and make decisions based on the information of the budget. The list of people comes from the team/stakeholder communication mentioned in the project communication management plan. Premises Ongoing 2,40,000/= Total anticipated costs 7,23,500 /=
  • 8. 7 3.3 Budget Execution Executing the budget is the action of authorizing the expenses approved on the project budget, the project manager then initiates to carry the activities that lead to form project team, purchase of equipment, materials and services, all according to a project procurement plan developed during the project planning. This step occurs after the budget has been approved and the project authorized to start its activities according to the project plan. 4. Budget Control Monitoring and controlling the project budget ensures that only the appropriate project changes are included in the budget baseline, that information about authorized changes are communicated and corrective actions are taken by project manager. The action of budget control is also a process of managing the budget. Budget management is the process by which costs or expenses incurred on the project are formally identified, approved and paid. Purchase order forms are completed for each set of related project expenses such as staffing, equipment and materials costs. Depending on the authorization level the purchase order forms are approved and recorded by the project manager for tracking, sponsor reporting and auditing purposes. 4.1 Budget Reporting The typical report contains a list of all budget accounts (COA) and columns that list the budget baseline, the cumulative expenses to date, the balance to date and the burn ration or how the budget is spend according to the yearly budget plan. Below is an example of a budget report:  Expense Reports, reports provide the expenses to date by account, project name and funding code.  Variance Reports, show the difference between what has been expensed and the approved budget, the balance for each account.
  • 9. 8  Burn Ratio Reports, shows the rate at which the project is using the budget according to the original plan, a quick method to see if the project budget is on track. 4.2 Earned Value Management Performance of the project will be measured using Earned Value Management. The following four Earned Value metrics is used to measure to projects cost performance:  Schedule Variance (SV)  Cost Variance (CV)  Schedule Performance Index (SPI)  Cost Performance Index (CPI) If the Schedule Performance Index or Cost Performance Index has a variance of between 0.1 and 0.2 the Project Manager must report the reason for the exception. If the SPI or CPI has a variance of greater than 0.2 the Project Manager must report the reason for the exception and provide management a detailed corrective plan to bring the projects performance back to acceptable levels. Performance Measure Yellow Red Schedule Performance Index (SPI) Between 0.9 and 0.8 or Between 1.1 and 1.2 Less Than 0.8 or Greater than 1.2 Cost Performance Index (CPI) Between 0.9 and 0.8 or Between 1.1 and 1.2 Less Than 0.8 or Greater than 1.2 4.3 Budget Analysis Identify the causes for the deviations from plan. Major deviations from the budget baseline need to be analysed to determine what caused the difference so that steps can be taken to prevent the situation from happening again in the future, or with similar projects.
  • 10. 9  Forecasting Earned Value enables the project manager to forecast the probable final cost and schedule results on the project. With Earned Value, the project does not have to wait until it is almost complete to know that it has a cost problem. Earned Value gives a project manager an “early warning” signal in time to take corrective action, in time to influence the final results by taking corrective actions. The Control Thresholds for this project is a CPI or SPI of less than 0.8 or greater than 1.2. If the project reaches one of these Control Thresholds a Cost Variance Corrective Action Plan is required. The Project Manager will present the Project Sponsor with options for corrective actions within five business days from when the cost variance is first reported. Within three business days from when the Project Sponsor selects a corrective action option, the Project Manager will present the Project Sponsor with a formal Cost Variance Corrective Action Plan. The Cost Variance Corrective Action Plan will detail the actions necessary to bring the project back within budget and the means by which the effectiveness of the actions in the plan will be measured. 5. Budget Update Budget update for ResearchColab project is described bellow. 5.1 Budget Changes Updates to the budget come from approved changes to the budget. For most projects changes to the budget need to be approved by the sponsor, in some instances the sponsor can give the project a small percentage that the project can use to cover small budget modifications It is important that the project manager understands the sponsor contract clauses and monitors, with special attention the accounts or budget items that have restrictions. Not doing so may result in losses to the project.
  • 11. 10 5.2 Corrective Actions If the project is under or over budget of the defined limit then the project manager needs to take corrective actions to bring the budget back on track, these actions may include trade-offs that will need to be discussed with sponsor, trade-off include reducing the scope or lowering the quality. Corrective actions may include the use of alternative options to produce the similar output using different inputs, the project manager will implement the corrective actions and monitor their performance to see if they are effective in reducing the project expenses and help bring the project back on track. Corrective actions need to be consulted with the project team so that changes are implemented. 5.3 Communicate Changes Changes to the budget need to be communicated and incorporated on the system that track change control. Communicating the changes of the budget to the team member that will use the information helps reduce the chances that work will be done on activities that have been either cancelled or postponed.