This file will give you the idea what is software project planning, what are its steps and procedures. this document also give you the idea abut software project monitoring.
Lisa is the project manager updating her project's risk register. She should include a level of detail in the risk responses that corresponds to the priority ranking of each risk. This will allow for an appropriate level of planning for high priority risks without overplanning for lower priority risks.
Jenny uncovered new risk events during quantitative analysis. She should enter these new risks into the risk register so they can be properly monitored and addressed.
The risk management plan will define who will share information on project risks with stakeholders, as it is responsible for communicating how risks will be identified, analyzed, and monitored throughout the project lifecycle.
Ranga's 51 hot topics to remember for Risk Management Professional (RMP) examrrangraj
1. The document provides 51 topics to remember for the Risk Management Professional (RMP) exam, covering risk management processes, techniques, and concepts.
2. Key areas covered include contingency planning, risk assessment methods like assumption testing and FMEA, risk scoring and ranking, project cost estimation including contingency reserves, and theories around human motivation and management.
3. The exam is expected to include situational questions, as well as questions on risk simulation techniques like Monte Carlo simulation.
The document contains 23 multiple choice questions about risk management processes and terminology. It tests knowledge around identifying and prioritizing risks, qualitative and quantitative risk analysis techniques, the risk management plan, risk register, and the process of controlling risks. Key outputs of controlling risks identified are work performance information and OPA updates. Qualitative risk analysis prioritizes risks for further quantitative analysis.
This document provides an overview of project risk management processes and techniques. It discusses the six key processes: (1) plan risk management, (2) identify risks, (3) perform qualitative risk analysis, (4) perform quantitative risk analysis, (5) plan risk responses, and (6) monitor and control risks. For each process, it describes important inputs, tools and techniques, and outputs to consider when managing project risks. The goal of risk management is to proactively identify and mitigate risks that could negatively impact a project.
PMP, PMBOK (R) 5th Edition,
CH: 11: Project Risk Management
--> Represents one of two biggest chapters, of the PMBOK
==> Too much useful, for the people who have concern in the project management field, & the risk management field as well
The document describes a risk related to construction site thefts that has been identified during interviews. Although the risk of theft from the project site is considered low, the risk is recorded on a watchlist so it can be monitored over time to ensure the probability and impact remain low. Risks with low ratings are included on a watchlist for future monitoring.
The document provides an overview of how to develop a logical framework or "logframe" for a project, which is a management tool that clearly outlines the key components, expected outcomes, and how success will be measured. It explains the different elements of a logframe matrix including goals, objectives, outputs, activities, indicators, and assumptions. Finally, it provides guidance on how to write good objectives and outlines the characteristics of effective indicators for monitoring and evaluating a project.
Risk identification should be based on agreed-upon definitions, clearly describe risks, and link risks to project objectives. Avoidance is the most appropriate response when there is no reasonable response to a highly probable threat with high impact. Updating various project documents is the best next step after completing quantitative risk analysis.
The document provides examples of risk management questions and answers. It includes questions related to calculating Cost Performance Index, probability-impact matrix, customer satisfaction as a risk, qualitative risk analysis tools, risk responses such as mitigation, transference and acceptance, and other risk management processes and techniques.
The document contains a full length mock test with 23 multiple choice questions related to project management concepts based on the PMBOK 5th edition. The questions cover topics like integrated change control, corrective vs preventive actions, communication management, cost of quality calculation, critical path identification, and organizational structures.
The document contains a practice exam for the PMI Risk Management Professional (PMI-RMP) certification. It includes 33 multiple choice questions related to risk management processes, tools, and techniques. Correct answers are provided for each question. The practice exam covers topics like risk identification, qualitative and quantitative risk analysis, risk response planning, and risk monitoring and control.
This document provides guidelines for successfully deploying risk management software. It discusses the importance of collaboration between the client and vendor project teams. Key factors that contribute to success include establishing clear communication plans, addressing risks and issues, and managing the project schedule, costs and scope. The document also covers defining and measuring critical success factors, establishing organizational hierarchies and reporting structures, focusing on data mapping and integrity, and managing workloads and change. The overall theme is that structure and flexibility are both important for risk management software deployments to be efficient and successful.
There are many lists describing the reasons for project failure. That’s easy to do.
Assuring the success of an IT project is much harder. This success starts with assessing the capabilities of the project delivery process and participants
Risk 0-risk-guide book for pmi-rmp by amer elbazMohamed Saeed
This document provides an overview of project risk management. It defines project risk management as including processes for risk management planning, identification, analysis, response planning, and controlling risk on a project. The objectives are to increase the likelihood and impact of positive events and decrease the likelihood and impact of negative events. It describes the six key processes: plan risk management, identify risks, perform qualitative risk analysis, perform quantitative risk analysis, plan risk responses, and control risks. It also discusses individual project risks versus overall project risk, stakeholder risk attitudes, and the iterative nature of project risk management.
NCV 4 Project Management Hands-On Support Slide Show - Module5Future Managers
This slide show complements the Learner Guide NCV 4 Project Management Hands-On Training by Bert Eksteen, published by Future Managers. For more information visit our website www.futuremanagers.net
The document discusses various topics related to software development including challenges, opportunities, and best practices. Some key points:
1. Software development involves many phases from requirements analysis to testing to maintenance. It is important to involve users, establish clear standards, and divide projects into well-defined phases and activities.
2. Developing software presents inherent challenges like changing requirements, managing frequent changes, and ensuring compatibility with existing systems. Adopting a problem-solving approach and justifying systems as investments can help address some challenges.
3. Opportunities in software development include making the process more cost-effective, improving quality, and capturing important domain knowledge. New approaches like model-driven development also offer benefits if properly
The document provides guidelines for project risk management based on the six risk management processes from the PMBOK Guide. It discusses identifying risks, performing qualitative and quantitative risk analysis, planning risk responses, and controlling risks. An example application to a PMP certification course project is provided to demonstrate practical use of identifying risks, creating a risk register, and customizing a risk breakdown structure for the project.
The document summarizes key points from a session on risk management:
1. The session discussed tools and techniques for risk response planning, including strategies for negative risks and contingent response planning.
2. It provided examples of different types of risks like secondary risks that can arise from implementing a risk response plan.
3. Residual risks that remain after risk responses have been implemented were also explained.
The document discusses key questions to consider for effectively planning and managing a software project. It covers having a work breakdown structure and schedule, clearly defined scope and requirements, adequate resourcing and staffing plans, addressing risks, and ensuring flexibility to adapt the plans based on changes and lessons learned. Managing external dependencies, quality assurance, and gaining user input are also emphasized.
This document contains a full-length mock test with 23 multiple choice questions related to project management concepts from the PMBOK Guide 5th edition. For each question, there is one correct answer choice provided. The test covers topics such as project closing, risk management, procurement management, stakeholder engagement, and organizational structures. The purpose of the test is to evaluate understanding of key project management processes and terminology.
Risk 8- pm study question risk managementMohamed Saeed
This document contains questions and answers related to risk management from PM Study. It discusses topics like risk identification, qualitative and quantitative risk analysis, risk response planning, and risk monitoring and control. The questions cover tools and techniques used in the risk management processes along with examples of their application in project scenarios.
The document discusses risk management in software projects. It describes methods for identifying risks such as using a risk checklist of common risks. It also provides questions to assess overall project risk and discusses estimating the likelihood and impact of risks. Risks are documented in a risk table including categories, probability, impact, and mitigation plans. Developing strategies to avoid, monitor, and manage risks is key to risk management.
Project planning is essential for software projects. It involves estimating the work, resources, and time required. Key planning activities include defining problems and requirements, developing solution strategies, and planning development processes. Requirements planning is especially important - it helps eliminate defects by gaining user involvement, understanding critical needs, and considering non-functional requirements. Empirical studies show most firms plan feasibility and costs, though risk management practices vary. Thorough early planning is needed to estimate schedules, efforts, people and resources needed for a project's success.
The document discusses project scope definition and management. It states that project scope involves identifying and describing all work needed to produce the project's product in sufficient detail so the team understands their tasks and reasonably foreseeable work is included. It also discusses defining the scope of the project and product, developing a project scope statement, identifying deliverables, and using a "Green Car" example to illustrate scope concepts.
5 The Logical Framework - a short course for NGOsTony
A series of modules on project cycle, planning and the logical framework, aimed at team leaders of international NGOs in developing countries.
There is a handout to go with this module, a Logframe with blanks. http://www.slideshare.net/Makewa/exercise-watsan-logframe-with-blanks
Srae2014 - Construction Projects Risks from the Perspective of Project Manage...Safak EBESEK
Construction Projects Risks from the Perspective of Project Management
Özlem Tüz, PhD & Safak EBESEK, PhD.C
The 23rd SRA-Europe conference 16-18 June 2014 in Istanbul, Turkey
Hosted by Istanbul Technical University
The document discusses project risk management and outlines the key steps: plan risk management, identify risks and opportunities, perform qualitative and quantitative risk analysis, plan risk responses, implement responses, and monitor risks. It defines risks as uncertain future events that could negatively impact objectives and opportunities as uncertain future events that could positively impact objectives. The risk assessment process determines the probability of a risk occurring and its potential impact. A risk matrix is provided as an example to assess risks based on probability and impact. The goal of risk management is to reduce risks and exploit opportunities to increase the likelihood of project success.
This document discusses software project management. It begins by introducing software project management and noting that it aims to deliver software on time, on budget, and satisfying requirements. It then discusses that software project management differs from other types of management due to software being intangible, processes being new, and rapid technology changes. The document outlines management activities like planning, scheduling, estimating costs, and monitoring progress. It discusses the responsibilities and skills of a project manager in leading the work effort. Finally, it discusses planning activities like defining objectives, estimating size, costs and duration, scheduling resources, and identifying risks. It also discusses documenting plans in a Software Project Management Plan.
1. Software project management involves planning, organizing, and controlling software development activities using scientific principles and techniques. It includes functions like scoping, planning, scheduling, and controlling.
2. Effective software project management focuses on people, product, process, and the project. It is important to manage stakeholders, recruit and train practitioners, define requirements and scope, select appropriate processes, and plan and track the project.
3. Project scheduling involves decomposing work into tasks, estimating efforts, identifying dependencies, and allocating tasks to time periods using tools like Gantt charts, PERT, and CPM to track progress against the schedule. Managing risks is also important for project success.
The document provides examples of risk management questions and answers. It includes questions related to calculating Cost Performance Index, probability-impact matrix, customer satisfaction as a risk, qualitative risk analysis tools, risk responses such as mitigation, transference and acceptance, and other risk management processes and techniques.
The document contains a full length mock test with 23 multiple choice questions related to project management concepts based on the PMBOK 5th edition. The questions cover topics like integrated change control, corrective vs preventive actions, communication management, cost of quality calculation, critical path identification, and organizational structures.
The document contains a practice exam for the PMI Risk Management Professional (PMI-RMP) certification. It includes 33 multiple choice questions related to risk management processes, tools, and techniques. Correct answers are provided for each question. The practice exam covers topics like risk identification, qualitative and quantitative risk analysis, risk response planning, and risk monitoring and control.
This document provides guidelines for successfully deploying risk management software. It discusses the importance of collaboration between the client and vendor project teams. Key factors that contribute to success include establishing clear communication plans, addressing risks and issues, and managing the project schedule, costs and scope. The document also covers defining and measuring critical success factors, establishing organizational hierarchies and reporting structures, focusing on data mapping and integrity, and managing workloads and change. The overall theme is that structure and flexibility are both important for risk management software deployments to be efficient and successful.
There are many lists describing the reasons for project failure. That’s easy to do.
Assuring the success of an IT project is much harder. This success starts with assessing the capabilities of the project delivery process and participants
Risk 0-risk-guide book for pmi-rmp by amer elbazMohamed Saeed
This document provides an overview of project risk management. It defines project risk management as including processes for risk management planning, identification, analysis, response planning, and controlling risk on a project. The objectives are to increase the likelihood and impact of positive events and decrease the likelihood and impact of negative events. It describes the six key processes: plan risk management, identify risks, perform qualitative risk analysis, perform quantitative risk analysis, plan risk responses, and control risks. It also discusses individual project risks versus overall project risk, stakeholder risk attitudes, and the iterative nature of project risk management.
NCV 4 Project Management Hands-On Support Slide Show - Module5Future Managers
This slide show complements the Learner Guide NCV 4 Project Management Hands-On Training by Bert Eksteen, published by Future Managers. For more information visit our website www.futuremanagers.net
The document discusses various topics related to software development including challenges, opportunities, and best practices. Some key points:
1. Software development involves many phases from requirements analysis to testing to maintenance. It is important to involve users, establish clear standards, and divide projects into well-defined phases and activities.
2. Developing software presents inherent challenges like changing requirements, managing frequent changes, and ensuring compatibility with existing systems. Adopting a problem-solving approach and justifying systems as investments can help address some challenges.
3. Opportunities in software development include making the process more cost-effective, improving quality, and capturing important domain knowledge. New approaches like model-driven development also offer benefits if properly
The document provides guidelines for project risk management based on the six risk management processes from the PMBOK Guide. It discusses identifying risks, performing qualitative and quantitative risk analysis, planning risk responses, and controlling risks. An example application to a PMP certification course project is provided to demonstrate practical use of identifying risks, creating a risk register, and customizing a risk breakdown structure for the project.
The document summarizes key points from a session on risk management:
1. The session discussed tools and techniques for risk response planning, including strategies for negative risks and contingent response planning.
2. It provided examples of different types of risks like secondary risks that can arise from implementing a risk response plan.
3. Residual risks that remain after risk responses have been implemented were also explained.
The document discusses key questions to consider for effectively planning and managing a software project. It covers having a work breakdown structure and schedule, clearly defined scope and requirements, adequate resourcing and staffing plans, addressing risks, and ensuring flexibility to adapt the plans based on changes and lessons learned. Managing external dependencies, quality assurance, and gaining user input are also emphasized.
This document contains a full-length mock test with 23 multiple choice questions related to project management concepts from the PMBOK Guide 5th edition. For each question, there is one correct answer choice provided. The test covers topics such as project closing, risk management, procurement management, stakeholder engagement, and organizational structures. The purpose of the test is to evaluate understanding of key project management processes and terminology.
Risk 8- pm study question risk managementMohamed Saeed
This document contains questions and answers related to risk management from PM Study. It discusses topics like risk identification, qualitative and quantitative risk analysis, risk response planning, and risk monitoring and control. The questions cover tools and techniques used in the risk management processes along with examples of their application in project scenarios.
The document discusses risk management in software projects. It describes methods for identifying risks such as using a risk checklist of common risks. It also provides questions to assess overall project risk and discusses estimating the likelihood and impact of risks. Risks are documented in a risk table including categories, probability, impact, and mitigation plans. Developing strategies to avoid, monitor, and manage risks is key to risk management.
Project planning is essential for software projects. It involves estimating the work, resources, and time required. Key planning activities include defining problems and requirements, developing solution strategies, and planning development processes. Requirements planning is especially important - it helps eliminate defects by gaining user involvement, understanding critical needs, and considering non-functional requirements. Empirical studies show most firms plan feasibility and costs, though risk management practices vary. Thorough early planning is needed to estimate schedules, efforts, people and resources needed for a project's success.
The document discusses project scope definition and management. It states that project scope involves identifying and describing all work needed to produce the project's product in sufficient detail so the team understands their tasks and reasonably foreseeable work is included. It also discusses defining the scope of the project and product, developing a project scope statement, identifying deliverables, and using a "Green Car" example to illustrate scope concepts.
5 The Logical Framework - a short course for NGOsTony
A series of modules on project cycle, planning and the logical framework, aimed at team leaders of international NGOs in developing countries.
There is a handout to go with this module, a Logframe with blanks. http://www.slideshare.net/Makewa/exercise-watsan-logframe-with-blanks
Srae2014 - Construction Projects Risks from the Perspective of Project Manage...Safak EBESEK
Construction Projects Risks from the Perspective of Project Management
Özlem Tüz, PhD & Safak EBESEK, PhD.C
The 23rd SRA-Europe conference 16-18 June 2014 in Istanbul, Turkey
Hosted by Istanbul Technical University
The document discusses project risk management and outlines the key steps: plan risk management, identify risks and opportunities, perform qualitative and quantitative risk analysis, plan risk responses, implement responses, and monitor risks. It defines risks as uncertain future events that could negatively impact objectives and opportunities as uncertain future events that could positively impact objectives. The risk assessment process determines the probability of a risk occurring and its potential impact. A risk matrix is provided as an example to assess risks based on probability and impact. The goal of risk management is to reduce risks and exploit opportunities to increase the likelihood of project success.
This document discusses software project management. It begins by introducing software project management and noting that it aims to deliver software on time, on budget, and satisfying requirements. It then discusses that software project management differs from other types of management due to software being intangible, processes being new, and rapid technology changes. The document outlines management activities like planning, scheduling, estimating costs, and monitoring progress. It discusses the responsibilities and skills of a project manager in leading the work effort. Finally, it discusses planning activities like defining objectives, estimating size, costs and duration, scheduling resources, and identifying risks. It also discusses documenting plans in a Software Project Management Plan.
1. Software project management involves planning, organizing, and controlling software development activities using scientific principles and techniques. It includes functions like scoping, planning, scheduling, and controlling.
2. Effective software project management focuses on people, product, process, and the project. It is important to manage stakeholders, recruit and train practitioners, define requirements and scope, select appropriate processes, and plan and track the project.
3. Project scheduling involves decomposing work into tasks, estimating efforts, identifying dependencies, and allocating tasks to time periods using tools like Gantt charts, PERT, and CPM to track progress against the schedule. Managing risks is also important for project success.
The document discusses project planning in software engineering. It defines project planning and its importance. It describes the project manager's responsibilities which include project planning, reporting, risk management, and people management. It discusses challenges in software project planning. The RUP process for project planning is then outlined which involves creating artifacts like the business case and software development plan. Risk management is also a key part of project planning.
The document discusses various approaches to project management including PMBOK, PRINCE2, and Six Sigma. It provides details on:
1) The five process groups and ten knowledge areas that PMBOK recognizes as typical for almost all projects.
2) The key aspects that PRINCE2 emphasizes such as organizing/planning before starting work and controlling a project once started.
3) How Six Sigma uses green belts and black belts for projects and that these typically last 4 months, with management control through goals rather than formal project management.
This document discusses software project planning and management. It covers topics like planning for both plan-driven and agile development, project scheduling, estimation techniques, and managing risks. It defines key aspects of project management like establishing a project plan, scheduling tasks, identifying and addressing risks, and managing people and teams. Estimation techniques discussed include experience-based and algorithmic modeling approaches. The document emphasizes the importance of project planning, tracking progress against plans, and adjusting plans based on new information or changes in risks and priorities.
Software Project Management | An Overview of the Software Project ManagementAhsan Rahim
Management is the process of getting things done through others, it is the process of coordinating people & other resources to achieve the goals of the organization. A project is a set of related tasks that are coordinated to achieve a specific objective in a given time limit. A project is well-defined task, which is a collection of several operations done in order to achieve a goal. Software is the program & all associated documentation & configuration data which is needed to make these programs operate correctly.
A Software Project is the complete procedure of software development from requirement gathering to testing & maintenance, carried out according to the execution methodologies, in a specified period of time to achieve intended software product.
Project Scope Statement
<Project Name>
<Student Name>
<Date>Introduction
Provide a one to two paragraph high level executive summary of the project, expanding on the summary provided in the project charter…Project Purpose and Justification
Provide a one to two paragraph summary of the purpose and justification of the project, expanding on the justification provided in the project charter…Scope Description
Describe all currently known characteristics of the project’s product or service. All details may not be known at the onset of the project and this may be progressively elaborated as the project moves forward. This section should contain descriptions of what is included in the product or service as well as the desired outcome of the project…High Level Requirements
Describe the currently known high-level capabilities of the solution to be met by successful completion of the project…Boundaries
Identify what should be included in the solution as well as what should not be included…Strategy
Describe the strategy/approach the project team will use in executing the project. Is this to be a “traditional” staged project, or will it require adaptive planning and control such as rolling wave or Agile Development? If traditional, what are the development/deployment stages? If rolling wave, how will you roll the wave? How will you manage change?Deliverables
Describe the currently known high-level products or outputs that solution is intended to provide…
Acceptance Criteria
Describe the measurable criteria which must be met for the solution to be considered complete and accepted by management…Constraints
Describe the limitations that the project faces due to funding, scheduling/time, technology, or resources…Assumptions
Describe the factors affecting the project that are believed to be true but that have not verified to be true…Risk Analysis and Mitigation Strategy
Describe any currently known high level risks for the project and associated mitigation strategies…Cost Estimate
Provide an estimate of the funding which will be needed to successfully complete the project, utilizing the table below…
Expense
Estimated Budget
Expended to Date
Estimate to Complete
Variance
Labor
Internal
External
Software
Hardware
Other
Total
PAGE
2
Name:
Exam 1
Congratulations. You have just been hired as the new CEO for Handback Industries. You were excited until you started and within first the few days, the director of HR came into your office and indicated that the employees were threatening to strike and go to the media if things were not fixed immediately. Since you were successful in your Statistics course taken during the Summer of 2013, you decide that you will assist the HR Director with her analysis.
Problem 1 - The employees have indicated that 95% of employees in one of the departments are receiving higher salaries than any other department because their supervisor parties with them each weekend. Some employee ...
This document provides information about a software project management course taught by Jing Zhang. It includes details about the instructor, course content, textbook, assessment, and a project paper assignment. Students will learn about the key aspects of software project management, including defining the scope, understanding factors the project manager must consider, elaborating the planning, supervision, and control required. The course covers principles of software project management and factors that influence their success or failure.
Project Plan Development - A FlackVentures Training ExampleKate Pynn
Project planning is the construction of a dynamic agreement across diverse functional groups involved in a project. This agreement specifies:
Goals and deliverables of the project
What is being developed
Major activities that will be performed to achieve those goals
The assumptions that were made
Major risks, as they become known
Unit 2 -Software-Development (Programming Logic and Techniques)Nabin Dhakal
Program development is the process of creating software applications to solve problems or meet specific user requirements. This intricate process involves various stages, from identifying a problem to delivering and maintaining the software. To ensure success, developers follow a structured Program Development Life Cycle (PDLC). Along the way, they leverage tools like algorithms, flowcharts, pseudocode, and decision-making frameworks.
Quality software project managementi need deep explanation for thi.pdfalokkesh
Quality software project management
i need deep explanation for this figure
Solution
Answer :-
Software Project Management :
A project is well-defined task, which is a collection of several operations done in order to
achieve a goal (for example, software development and delivery). A Project can be characterized
as:
1) Every project may has a unique and distinct goal.
2) Project is not routine activity or day-to-day operations.
3) Project comes with a start time and end time.
4) Project ends when its goal is achieved hence it is a temporary phase in the lifetime of an
organization.
5) Project needs adequate resources in terms of time, manpower, finance, material and
knowledge-bank.
Software Project :
A Software Project is the complete procedure of software development from requirement
gathering to testing and maintenance, carried out according to the execution methodologies, in a
specified period of time to achieve intended software product.
Need of software project management :
Software is said to be an intangible product. Software development is a kind of all new stream in
world business and there’s very little experience in building software products.
Software Project Manager :
A software project manager is a person who undertakes the responsibility of executing the
software project. Software project manager is thoroughly aware of all the phases of SDLC that
the software would go through. Project manager may never directly involve in producing the end
product but he controls and manages the activities involved in production.
Managing People :
1) Act as project leader
2) Liaison with stakeholders
3) Managing human resources
4) Setting up reporting hierarchy etc.
Managing Project :
1) Defining and setting up project scope .
2) Managing project management activities .
3)Monitoring progress and performance
4) Risk analysis at every phase .
5) Take necessary step to avoid or come out of problems .
6) Act as project spokesperson .
Software Management Activities :
Software project management comprises of a number of activities, which contains planning of
project, deciding scope of software product, estimation of cost in various terms, scheduling of
tasks and events, and resource management. Project management activities may include:
1) Project Planning
2) Scope Management
3) Project Estimation
Project Planning :
Software project planning is task, which is performed before the production of software actually
starts. It is there for the software production but involves no concrete activity that has any
direction connection with software production; rather it is a set of multiple processes, which
facilitates software production.
Scope Management :
It defines the scope of project; this includes all the activities, process need to be done in order to
make a deliverable software product. Scope management is essential because it creates
boundaries of the project by clearly defining what would be done in the project and what would
not be done. This makes.
The document summarizes a half-day workshop on project management. The workshop covers understanding business needs and justifying projects, the project life cycle, developing a project charter, managing scope, schedule and budget using the triple constraints, planning and executing projects, communication plans, closing projects, and continuous improvement.
This document discusses managing computing projects. It defines what a project and software project are, and explains the need for software project management. It describes triple constraints for software projects involving quality, cost, and schedule. Key software project management activities are outlined, including planning, scope management, estimation, scheduling, resource management, risk management, execution and monitoring. Common project management tools like Gantt charts, PERT charts, and resource histograms are also summarized.
Computer Network tutorial provides basic and advanced concepts of Data Communication & Networks (DCN). Our Computer Networking Tutorial is designed for beginners and professionals.
Our Computer Network tutorial includes all topics of Computer Network such as introduction, features, types of computer network, architecture, hardware, software, internet, intranet, website, LAN, WAN, etc.
What is Computer Network?
A computer network is a set of devices connected through links. A node can be computer, printer, or any other device capable of sending or receiving the data. The links connecting the nodes are known as communication channels.
Computer Network uses distributed processing in which task is divided among several computers. Instead, a single computer handles an entire task, each separate computer handles a subset.
Following are the advantages of Distributed processing:
Security: It provides limited interaction that a user can have with the entire system. For example, a bank allows the users to access their own accounts through an ATM without allowing them to access the bank's entire database.
Faster problem solving: Multiple computers can solve the problem faster than a single machine working alone.
Security through redundancy: Multiple computers running the same program at the same time can
The document discusses the Logical Framework Approach (LFA), a systematic planning procedure used for project management. It describes the history and key features of the Logical Framework Matrix, including its hierarchy of objectives from activities to goal. The matrix maps the logical relationships between project components and defines objectives, indicators, assumptions and risks. It is a tool used for planning, monitoring and evaluating projects.
The document discusses various aspects of software project management including the management scope, people, product, process, and project. It also covers the W5HH principle for defining key project characteristics including why the system is being developed, what will be done, when it will be done, who is responsible, where people are located, how the job will be done technically and authoritatively, and how many resources are needed. Finally, it discusses software metrics for measuring aspects like size, quality, and productivity.
This document provides an overview of key concepts and methods for evaluating programs, including:
1. SWOT analysis, the steps in program evaluation, milestone charts, Gantt charts, PERT, critical path method, Bennett's hierarchy of evaluation, and the logical framework approach.
2. It describes each method at a high level - for example, that SWOT analysis identifies strengths, weaknesses, opportunities, and threats, and that the critical path method uses mathematical calculations to schedule project activities.
3. Bennett's hierarchy presents a logic model for educational programs with 7 steps from inputs to end results, showing how the program causes changes in knowledge and practice.
The document provides details of a proposed project to create a new Excel spreadsheet software. It includes a project proposal, charter, requirements, costs, and work breakdown structure. The goal is to develop a software that allows more efficient production tracking and reduces costs and errors. The estimated budget is $30,000 and timeline is 12 months, including 2 months of testing. Progress will be tracked and risks like insufficient resources or delays will be monitored closely.
pulse ppt.pptx Types of pulse , characteristics of pulse , Alteration of pulsesushreesangita003
what is pulse ?
Purpose
physiology and Regulation of pulse
Characteristics of pulse
factors affecting pulse
Sites of pulse
Alteration of pulse
for BSC Nursing 1st semester
for Gnm Nursing 1st year
Students .
vitalsign
A measles outbreak originating in West Texas has been linked to confirmed cases in New Mexico, with additional cases reported in Oklahoma and Kansas. The current case count is 795 from Texas, New Mexico, Oklahoma, and Kansas. 95 individuals have required hospitalization, and 3 deaths, 2 children in Texas and one adult in New Mexico. These fatalities mark the first measles-related deaths in the United States since 2015 and the first pediatric measles death since 2003.
The YSPH Virtual Medical Operations Center Briefs (VMOC) were created as a service-learning project by faculty and graduate students at the Yale School of Public Health in response to the 2010 Haiti Earthquake. Each year, the VMOC Briefs are produced by students enrolled in Environmental Health Science Course 581 - Public Health Emergencies: Disaster Planning and Response. These briefs compile diverse information sources – including status reports, maps, news articles, and web content– into a single, easily digestible document that can be widely shared and used interactively. Key features of this report include:
- Comprehensive Overview: Provides situation updates, maps, relevant news, and web resources.
- Accessibility: Designed for easy reading, wide distribution, and interactive use.
- Collaboration: The “unlocked" format enables other responders to share, copy, and adapt seamlessly. The students learn by doing, quickly discovering how and where to find critical information and presenting it in an easily understood manner.
GDGLSPGCOER - Git and GitHub Workshop.pptxazeenhodekar
This presentation covers the fundamentals of Git and version control in a practical, beginner-friendly way. Learn key commands, the Git data model, commit workflows, and how to collaborate effectively using Git — all explained with visuals, examples, and relatable humor.
Geography Sem II Unit 1C Correlation of Geography with other school subjectsProfDrShaikhImran
The correlation of school subjects refers to the interconnectedness and mutual reinforcement between different academic disciplines. This concept highlights how knowledge and skills in one subject can support, enhance, or overlap with learning in another. Recognizing these correlations helps in creating a more holistic and meaningful educational experience.
How to Set warnings for invoicing specific customers in odooCeline George
Odoo 16 offers a powerful platform for managing sales documents and invoicing efficiently. One of its standout features is the ability to set warnings and block messages for specific customers during the invoicing process.
Exploring Substances:
Acidic, Basic, and
Neutral
Welcome to the fascinating world of acids and bases! Join siblings Ashwin and
Keerthi as they explore the colorful world of substances at their school's
National Science Day fair. Their adventure begins with a mysterious white paper
that reveals hidden messages when sprayed with a special liquid.
In this presentation, we'll discover how different substances can be classified as
acidic, basic, or neutral. We'll explore natural indicators like litmus, red rose
extract, and turmeric that help us identify these substances through color
changes. We'll also learn about neutralization reactions and their applications in
our daily lives.
by sandeep swamy
As of Mid to April Ending, I am building a new Reiki-Yoga Series. No worries, they are free workshops. So far, I have 3 presentations so its a gradual process. If interested visit: https://www.slideshare.net/YogaPrincess
https://ldmchapels.weebly.com
Blessings and Happy Spring. We are hitting Mid Season.
Odoo Inventory Rules and Routes v17 - Odoo SlidesCeline George
Odoo's inventory management system is highly flexible and powerful, allowing businesses to efficiently manage their stock operations through the use of Rules and Routes.
CBSE - Grade 8 - Science - Chemistry - Metals and Non Metals - WorksheetSritoma Majumder
Introduction
All the materials around us are made up of elements. These elements can be broadly divided into two major groups:
Metals
Non-Metals
Each group has its own unique physical and chemical properties. Let's understand them one by one.
Physical Properties
1. Appearance
Metals: Shiny (lustrous). Example: gold, silver, copper.
Non-metals: Dull appearance (except iodine, which is shiny).
2. Hardness
Metals: Generally hard. Example: iron.
Non-metals: Usually soft (except diamond, a form of carbon, which is very hard).
3. State
Metals: Mostly solids at room temperature (except mercury, which is a liquid).
Non-metals: Can be solids, liquids, or gases. Example: oxygen (gas), bromine (liquid), sulphur (solid).
4. Malleability
Metals: Can be hammered into thin sheets (malleable).
Non-metals: Not malleable. They break when hammered (brittle).
5. Ductility
Metals: Can be drawn into wires (ductile).
Non-metals: Not ductile.
6. Conductivity
Metals: Good conductors of heat and electricity.
Non-metals: Poor conductors (except graphite, which is a good conductor).
7. Sonorous Nature
Metals: Produce a ringing sound when struck.
Non-metals: Do not produce sound.
Chemical Properties
1. Reaction with Oxygen
Metals react with oxygen to form metal oxides.
These metal oxides are usually basic.
Non-metals react with oxygen to form non-metallic oxides.
These oxides are usually acidic.
2. Reaction with Water
Metals:
Some react vigorously (e.g., sodium).
Some react slowly (e.g., iron).
Some do not react at all (e.g., gold, silver).
Non-metals: Generally do not react with water.
3. Reaction with Acids
Metals react with acids to produce salt and hydrogen gas.
Non-metals: Do not react with acids.
4. Reaction with Bases
Some non-metals react with bases to form salts, but this is rare.
Metals generally do not react with bases directly (except amphoteric metals like aluminum and zinc).
Displacement Reaction
More reactive metals can displace less reactive metals from their salt solutions.
Uses of Metals
Iron: Making machines, tools, and buildings.
Aluminum: Used in aircraft, utensils.
Copper: Electrical wires.
Gold and Silver: Jewelry.
Zinc: Coating iron to prevent rusting (galvanization).
Uses of Non-Metals
Oxygen: Breathing.
Nitrogen: Fertilizers.
Chlorine: Water purification.
Carbon: Fuel (coal), steel-making (coke).
Iodine: Medicines.
Alloys
An alloy is a mixture of metals or a metal with a non-metal.
Alloys have improved properties like strength, resistance to rusting.
*Metamorphosis* is a biological process where an animal undergoes a dramatic transformation from a juvenile or larval stage to a adult stage, often involving significant changes in form and structure. This process is commonly seen in insects, amphibians, and some other animals.
Multi-currency in odoo accounting and Update exchange rates automatically in ...Celine George
Most business transactions use the currencies of several countries for financial operations. For global transactions, multi-currency management is essential for enabling international trade.
INTRO TO STATISTICS
INTRO TO SPSS INTERFACE
CLEANING MULTIPLE CHOICE RESPONSE DATA WITH EXCEL
ANALYZING MULTIPLE CHOICE RESPONSE DATA
INTERPRETATION
Q & A SESSION
PRACTICAL HANDS-ON ACTIVITY
1. The company we will interview for our report well be Netsol. We will ask questions to its development
department employees named The Innovation Group. The Innovation Group delivers profit
improvement solutions for the insurance and associated industries through technology and specialized
business process outsourcing solutions.
By conducting this interview we will learn following skills:
To understand what is project planning. To understand what are project panning life cycle
phases and methods.
To understand the feasibility of a project prior to implementation.
To understand the steps in defining project objectives and scope.
To understand the concepts of the Time Value of Money and Resources.
To understand who to eliminate constraints of Time/Cost/Performance Specification and
Resources on software during monitoring.
To understand who to schedule a project
To understand who to analyze risks associated with a project
The knowledge we get from this interview we will apply it in software development sector.
Planning
The overall goal of software project planning is to establish a pragmatic strategy for controlling, tracking,
and monitoring a complex technical project.
Why?
So the end result gets done on time, with quality.
Clear objectives lead to a higher rate of project success.
By taking the time to properly plan your project’s objectives, the tasks leading toward these
objectives are easily created.
Software project planning encompasses five major activities:
Estimation:
o
Scheduling:
Estimation determines — how much money, effort, resources, and time it will take to
build a specific system or product?
2. o
Scheduling determines — how do we allocate resources along the timeline? What are
the milestones?
Risk analysis:
o
Risk analysis determines —what can go wrong? How can we avoid it? What can we do
about it?
Quality and change management planning:
o
Control strategy determines —how do we control quality? How do we control change?
Task Set for Project Planning:
Software houses perform collection of planning task to get the solution of above mentioned questions,
these tasks are:
1) Establish project scope:
a) Understand the customer’s needs
b) understand the business context
c) understand the project boundaries
d) understand the customer’s motivation
e) understand the likely paths for change
After identifying the software scope you must ask two important questios:
1) Can we build software to meet this scope?
2) Is the project feasible?
2) Determine feasibility: To get the answer of send question we make feasibility of software.
Technical feasibility is important, but business need is more important. You should not develop
such software which will technically very high but no one wants to buy it.
3. Software feasibility has four dimensions
a) Technology – Is the project technically feasible? Is it within the state of the art? Can
defects be reduced to a level matching the application's needs?
b) Finance – Is is financially feasible? Can development be completed at a cost that the
software organization, its client, or the market can afford?
c) Time – Will the project's time-to-market beat the competition?
d) Resources – Does the software organization have the resources needed to succeed in
doing the project?
3) Analyze risks:
In the software project plan we perform following tasks to analyze the risks:
o
o
o
o
o
o
List the potential risks
Assign a probability to each risk (1 is low, 5 is high)
Assess the severity should the risk occur (1 is low, 5 is high)
Give each risk a score (probability time’s severity)
Plan how you will prevent risks happening (or manage them if they occur).
The highest scoring risks need to be considered and planned for in more detail.
Think about the risk analysis at the start of the project in order to prevent risks from happening.
4) Define required resources
a) Determine human resources required:
o
o
o
Planners need to select the number and the kind of people skills needed to
complete the project. They need to specify the organizational position and job
specialty for each person
Small projects of a few person-months may only need one individual. Large
projects spanning many person-months or years require the location of the
person to be specified also
The number of people required can be determined only after an estimate of the
development effort
b) Define reusable software resources:
Reusable software resources consist on following:
4. o
o
o
o
Off-the-shelf components
Full-experience components
Partial-experience components
New components
c) Identify environmental resources:
o
o
A software engineering environment (SEE) consists on hardware, software, and
network resources that required in developing and testing software product.
Most software organizations have many projects that require access to the SEE
provided by the organization. Planners must identify the time window required
for hardware and software and verify that these resources will be available
5) Estimate cost and effort
a) Decompose the problem
b) Develop two or more estimates using different approaches
c) Reconcile the estimates
6) Develop a project schedule
a) Establish a meaningful task set and milestones.
b) Use scheduling tools to develop a timeline chart
c) Define schedule tracking mechanisms
d) Identifies who is responsible for conducting each task
e) Specifies the inter-task dependencies
Monitoring:
The purpose of Project Monitoring and is to provide an understanding of the project’s progress so that
appropriate corrective actions can be taken when the project’s performance deviates significantly from
the plan.
Monitoring is used to oversee progress of software and generate reports. Reporting advises the correct
people at the correct time of positive and negative events, allowing for progression or remedial action
as appropriate.
Monitor the actual values of the project planning parameters against the project plan.
Monitor commitments against those identified in the project plan.
Monitor risks against those identified in the project plan.
5. Periodically review the project's progress, performance, and issues:
o Regularly communicate status on assigned activities and work products to
relevant stakeholders.
o Identify and document significant issues and deviations from the plan.
o Document change requests and problems identified in any of the work products
and processes.
o Document the results of the reviews.
o Track change requests and problem reports to closure.
Review the accomplishments and results of the project at selected project milestones:
o Conduct reviews at meaningful points in the project’s schedule, such as the
completion of selected stages, with relevant stakeholders.
o Review the commitments, plan, status, and risks of the project.
o Identify and document significant issues and their impacts.
o Document the results of the review, action items, and decisions.
o Track action items to closure
Corrective actions are managed to closure when the project's performance or results deviate
significantly from the plan:
o Gather issues for analysis
o Analyze issues to determine need for corrective action.Corrective action is
required when the issue, if left unresolved, may prevent the project from
meeting its objectives.
3. What process are you following for the study?
The Process following for studying
Software Engineering A P R A C T I T I O N E R ’ S A P P R O A C H edition 5 chapter 5 for
planning
for monitoring we study cmmi for development version 1.2 "project monitorinl and
control (PMc) "
6. Questions for Project Planning
How long you have been working in industry?
How long you have been working in this company?
What is your job title?
Are you using any tool to manage planning? If yes, then which tool you use for managing
the planning?
Which steps you used for project planning? And what is their order?
Are resources provided for the planning software project?
If you fail in project planning who guide you?
Do you set the team road map? If Yes, then who divide the task, do you divide the task
equally or according to the capacity of employees?
Do affected groups and individuals agree their commitments related to the software
project?
Do you use the same team for all projects or do you assign different team to different
project.
How you evaluate project success?
Which software matrices you used for project cost, time and effort estimation?
For which kind of software you perform risk analysis before checking the quality of
software and after checking the quality of software? What are their benefits?
While understanding the scope of software with clients, does you makes developer
team leads part of that meeting?
Questions for monitoring
Name the activities/steps you perform for monitoring your project. What are the order
of the steps/activates?
Who perform the monitoring activities? Do you have a separate team for monitoring or
the team who developed the software?
How you create framework for monitoring?
How you perform monitoring in your project? Are you using some tool or you update
your project file manually?
In monitoring which time estimation is good one? Daily weekly or monthly?
Does the project follow a written organization policy for monitoring the software the
project?
How you deal with the delays if any occur?
7. If you are behind the schedule what will you do? You make another plan to reach the
target or stick with the old one?
which resources you are using for monitoring the project ?
Refrences
http://www.brighthubpm.com/project-planning/20136-examples-of-project-planningobjectives/
http://portal.hud.gov/hudportal/HUD?src=/program_offices/comm_planning/affordablehousin
g/training/web/checkup/monitoring/monitoringobjectives