RESOURCE SCHEDULING OF
RESIDENTIAL PROJECT USING
PRIMAVERA
 The main aim of this project is to study the plan
of a residential building project (G+4) and
scheduling of construction activities and
budgeting by Using suitable method of Project
management techniques (CPM,PERT) with help
of primavera software.
AIM OF PROJECT
 Study the basics of primavera
 Selection of project and preparation of typical plan for (G+4)
Residential building.
 Estimation of quantities
 Preparation of activity layout and calculating duration of each
activity.
 Scheduling the activities
 Preparation of WBS layout.
 Budgeting the project.
 Preparation of reports &document
Schedule of project
 1. Primavera is a tool for planner, project managers and
any person needs to plan - control a project.
 2.It is a product of primavera system in since 1982-
oracle corporation -2008(p6)
 Oracle's Primavera P6 Enterprise Project Management
is the most powerful and easy-to-use solution for
globally prioritizing, planning, managing, and executing
projects, programs.
Concept of primavera
&Oracle corporation review
 p6 is specified in managing all types of projects
small, medium & large
 Methods of Working:-
Pm is using critical path method (CPM) in
calculating project duration and floats of the activities
 It has types of charts (view/display)
Gantt Bar chart
Specified & method of working
 Construction management
 Scheduling
 Tracking
 Resources
 Man-day
 Budget
 Project: Any undertaken work is called project, it requires
resources and fund to complete. We can get some out put by
doing project.
 Ex: catering, wedding planning, construction of building,
software development.
Key words& their definitions
&uses
 The components that may be measured and controlled using
planning and scheduling software
Time
Resource
Cost
Project Planning Components&
Parameters
 Thinking & documenting what needs to be done to complete the
project
 Defining Responsibilities(AR,OW,CONTRACTER)
 Defining the phases (DP, EP, FP)
 Calculating Activity duration
 Adding the logic links between activities
 Assigning resources and cost to activities
 Define calendars
 Create a work break down structure
 Preparing work schedules
 Developing an acceptable budget
 Provide a base line which progresses is measured
Planning the project by means
 Ensuring the project is being executed according to
the plan measuring performance
 Compare the projects progress with the original plan
 Suggesting correction action when needed
 Inform the team about progress
 Identifying the improvement of performance of team
 Forecast Problems
Monitoring and controlling means:-
 The time span between the start and competition of
project. Represents the project
 life cycle which varies from few months to few years
The life cycle of project can be broadly divided into the
following:-
Project life cycle (Plc.)
 a) Formation stage / inception stage
. Feasibility studies
.Invest appraisal(budget)
.project definition
 b) Mobilization / preparation Stage
.Project Preliminary plan
.Design & drawing
.Specification and tendering(contract finalization)
.resource Mobilization
 C) Construction stage / Execution stage
. Planning & controlling execution
.Inducting Resources
.Construction
.Final handing over to the client
Project updating cycle
cre
ppt for primevera
ppt for primevera
ppt for primevera
ppt for primevera
ppt for primevera
ppt for primevera
THE PROGRAM CAN BE SEE IN
PRIMAVERA SOFTWARE IN
PRACTICALY

More Related Content

PDF
Primavera P6 manual
Abbas Tahir
 
PPTX
Introduction To Primavera (P6)
Sandip Kumar Verma
 
PPTX
Primavara
danabl
 
PDF
PM using P6
Hakeem-Ur- Rehman
 
PPT
Primavera Training P6
Suresh G Sankarankutty
 
PDF
Primavera - Tutorial
Rajeev Sharma
 
PDF
Pdf primavera tutorial
Ketut Swandana
 
PDF
Primavera p6 advanced project planning
Amit Kumar Senapati, PMP®
 
Primavera P6 manual
Abbas Tahir
 
Introduction To Primavera (P6)
Sandip Kumar Verma
 
Primavara
danabl
 
PM using P6
Hakeem-Ur- Rehman
 
Primavera Training P6
Suresh G Sankarankutty
 
Primavera - Tutorial
Rajeev Sharma
 
Pdf primavera tutorial
Ketut Swandana
 
Primavera p6 advanced project planning
Amit Kumar Senapati, PMP®
 

What's hot (20)

PPTX
Primavera presentation
Nithin Dev
 
PDF
construction project planing
SANJEEV Wazir
 
PDF
Primavera p6 18.8 planning and scheduling guide r3
Matiwos Tsegaye
 
PPTX
PRIMAVERA P6 manual.pptx
GracePentinio1
 
PPTX
Construction project management
Senthil Kannan
 
PDF
Primavera P6 Notes for Beginners
SivaSubramanian Sakthivel
 
PPTX
Construction planning - Construction Technology and Project Management
srinivas2036
 
PDF
Construction Project Management
Rajat Nainwal
 
PPT
Primavera Project Management
Kashiff Naveed
 
PPT
Construction scheduling & Cost control
Guhan M
 
PPTX
tcc primavera
Jaspreet singh
 
PPTX
Microsoft Project
university of education,Lahore
 
PDF
Project scheduling and resource levelling_Construction Management
A Makwana
 
PDF
Construction Project management
Anupama holla
 
PPTX
PROJECT SCHEDULE
Ajeesh Mk
 
PPT
Project Management: NETWORK ANALYSIS - CPM and PERT
S.Vijaya Bhaskar
 
PPT
3. construction planning. construction project management
Kabilan Kabi
 
PPTX
Project cost control
Sourabh Modgil
 
PPTX
Construction Cost Control
Sunayana Miglani
 
PPTX
Construction planning & management
Manit Agarwal
 
Primavera presentation
Nithin Dev
 
construction project planing
SANJEEV Wazir
 
Primavera p6 18.8 planning and scheduling guide r3
Matiwos Tsegaye
 
PRIMAVERA P6 manual.pptx
GracePentinio1
 
Construction project management
Senthil Kannan
 
Primavera P6 Notes for Beginners
SivaSubramanian Sakthivel
 
Construction planning - Construction Technology and Project Management
srinivas2036
 
Construction Project Management
Rajat Nainwal
 
Primavera Project Management
Kashiff Naveed
 
Construction scheduling & Cost control
Guhan M
 
tcc primavera
Jaspreet singh
 
Project scheduling and resource levelling_Construction Management
A Makwana
 
Construction Project management
Anupama holla
 
PROJECT SCHEDULE
Ajeesh Mk
 
Project Management: NETWORK ANALYSIS - CPM and PERT
S.Vijaya Bhaskar
 
3. construction planning. construction project management
Kabilan Kabi
 
Project cost control
Sourabh Modgil
 
Construction Cost Control
Sunayana Miglani
 
Construction planning & management
Manit Agarwal
 
Ad

Similar to ppt for primevera (20)

PDF
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
IRJET Journal
 
PPTX
Scheduling of a five story residential apartment project
kaishwarya3
 
PDF
BATCH 4 REVIEW.pdf by civil engineering in pulivendula
acherlap
 
PDF
TESTED PDF REPORT.pdf
BharatGoyal55
 
PDF
Review on Planning and Scheduling of Construction Project by Management Tool ...
ijtsrd
 
PDF
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...
IRJET Journal
 
PDF
IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET Journal
 
PDF
Primavera p3 [compatibility mode]
Rahul
 
PPTX
PPT_Primavera_P6_Training_of_Presentation
mgayathiri1807
 
PDF
Primavera P6
Piyush Bagade
 
PDF
Www.7aramy kotob.tk-planning.scheduling.using.primavera
Yasser Nassr
 
PDF
Planning and Scheduling Construction Projects using Primavera Software A Case...
ijtsrd
 
PPTX
Project Scheduling
William Brooks
 
PPTX
Project Scheduling
William Brooks
 
PPTX
Project Scheduling
William Brooks
 
PPTX
Project Scheduling
William Brooks
 
PDF
H1303024956
IOSR Journals
 
PDF
Enterprise Project Management using Primavera P6 EPPM
IRJET Journal
 
PDF
Project Scheduling of a High-rise Building using Primavera P6
IRJET Journal
 
PPTX
Project Scheduling
William Brooks
 
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
IRJET Journal
 
Scheduling of a five story residential apartment project
kaishwarya3
 
BATCH 4 REVIEW.pdf by civil engineering in pulivendula
acherlap
 
TESTED PDF REPORT.pdf
BharatGoyal55
 
Review on Planning and Scheduling of Construction Project by Management Tool ...
ijtsrd
 
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...
IRJET Journal
 
IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET Journal
 
Primavera p3 [compatibility mode]
Rahul
 
PPT_Primavera_P6_Training_of_Presentation
mgayathiri1807
 
Primavera P6
Piyush Bagade
 
Www.7aramy kotob.tk-planning.scheduling.using.primavera
Yasser Nassr
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
ijtsrd
 
Project Scheduling
William Brooks
 
Project Scheduling
William Brooks
 
Project Scheduling
William Brooks
 
Project Scheduling
William Brooks
 
H1303024956
IOSR Journals
 
Enterprise Project Management using Primavera P6 EPPM
IRJET Journal
 
Project Scheduling of a High-rise Building using Primavera P6
IRJET Journal
 
Project Scheduling
William Brooks
 
Ad

ppt for primevera

  • 1. RESOURCE SCHEDULING OF RESIDENTIAL PROJECT USING PRIMAVERA
  • 2.  The main aim of this project is to study the plan of a residential building project (G+4) and scheduling of construction activities and budgeting by Using suitable method of Project management techniques (CPM,PERT) with help of primavera software. AIM OF PROJECT
  • 3.  Study the basics of primavera  Selection of project and preparation of typical plan for (G+4) Residential building.  Estimation of quantities  Preparation of activity layout and calculating duration of each activity.  Scheduling the activities  Preparation of WBS layout.  Budgeting the project.  Preparation of reports &document Schedule of project
  • 4.  1. Primavera is a tool for planner, project managers and any person needs to plan - control a project.  2.It is a product of primavera system in since 1982- oracle corporation -2008(p6)  Oracle's Primavera P6 Enterprise Project Management is the most powerful and easy-to-use solution for globally prioritizing, planning, managing, and executing projects, programs. Concept of primavera &Oracle corporation review
  • 5.  p6 is specified in managing all types of projects small, medium & large  Methods of Working:- Pm is using critical path method (CPM) in calculating project duration and floats of the activities  It has types of charts (view/display) Gantt Bar chart Specified & method of working
  • 6.  Construction management  Scheduling  Tracking  Resources  Man-day  Budget  Project: Any undertaken work is called project, it requires resources and fund to complete. We can get some out put by doing project.  Ex: catering, wedding planning, construction of building, software development. Key words& their definitions &uses
  • 7.  The components that may be measured and controlled using planning and scheduling software Time Resource Cost Project Planning Components& Parameters
  • 8.  Thinking & documenting what needs to be done to complete the project  Defining Responsibilities(AR,OW,CONTRACTER)  Defining the phases (DP, EP, FP)  Calculating Activity duration  Adding the logic links between activities  Assigning resources and cost to activities  Define calendars  Create a work break down structure  Preparing work schedules  Developing an acceptable budget  Provide a base line which progresses is measured Planning the project by means
  • 9.  Ensuring the project is being executed according to the plan measuring performance  Compare the projects progress with the original plan  Suggesting correction action when needed  Inform the team about progress  Identifying the improvement of performance of team  Forecast Problems Monitoring and controlling means:-
  • 10.  The time span between the start and competition of project. Represents the project  life cycle which varies from few months to few years The life cycle of project can be broadly divided into the following:- Project life cycle (Plc.)
  • 11.  a) Formation stage / inception stage . Feasibility studies .Invest appraisal(budget) .project definition  b) Mobilization / preparation Stage .Project Preliminary plan .Design & drawing .Specification and tendering(contract finalization) .resource Mobilization  C) Construction stage / Execution stage . Planning & controlling execution .Inducting Resources .Construction .Final handing over to the client
  • 13. cre
  • 20. THE PROGRAM CAN BE SEE IN PRIMAVERA SOFTWARE IN PRACTICALY