0% found this document useful (0 votes)
2K views

Critical Path Method (CPM) in Project Management

The document discusses the Critical Path Method (CPM) for project scheduling. CPM identifies the longest path of activities in a project's network diagram as the critical path, which determines the shortest time possible to complete the project. The critical path has no float or slack time, so its activities must finish on schedule or the whole project will be delayed. Calculating early and late start/finish dates allows identifying float periods to track a project's status and make contingency plans.

Uploaded by

dndudc
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2K views

Critical Path Method (CPM) in Project Management

The document discusses the Critical Path Method (CPM) for project scheduling. CPM identifies the longest path of activities in a project's network diagram as the critical path, which determines the shortest time possible to complete the project. The critical path has no float or slack time, so its activities must finish on schedule or the whole project will be delayed. Calculating early and late start/finish dates allows identifying float periods to track a project's status and make contingency plans.

Uploaded by

dndudc
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 11

Critical Path Method (CPM) in Project Management

If you have been into project management, you must have heard about the Critical Path Method
(CPM), which is a project modeling technique developed by Morgan R. Walker and James E.
Kelly in late 1950 (Wikipedia).

The critical path method (CPM) is extensively used by project planners worldwide for developing
the project schedule in types of projects; e.g. IT, research, construction, etc.

This method is a basis of the project schedule and is discussed very broadly in the PMBOK
Guide. You can expect to see more than two to three questions in your PMP exam from this
topic.

In this blog post, I will discuss the critical path with a real world example, identifying the critical
path in a network diagram, and calculate the float for each path.

Once you become familiar with it, I will walk you through every step required for calculating
Early Start, Early Finish with forward pass, and then calculating Late Start, Late Finish with
backward pass.

Make sure you understand each step described in this blog post correctly, otherwise you might
face some difficulties while dealing with these calculations. However, if you feel you need any
clarification, you are free to reach out to me any time through the comments section.

Critical Path

If you look at any network diagram, you will notice many paths originating from a point and
ending at some point. Every path will have some duration, and the path with the longest
duration is known as the critical path.

The critical path can be defined in many ways, such as:

The critical path is the longest path in the network diagram, or


The critical path is shortest duration in which the project can be completed.

Dont you think these two definitions are different, or just opposite to each other?

No, in fact, both definitions are trying to convey same message. They might seem to be
opposite to you because the first definition is talking about the longest path and the second
definition is talking about the shortest duration. However, they both are the same.

Lets say, you got a project to build three buildings in one location. The first building is the
largest building, the second building is medium sized building, and the third building is the
smallest building.
You develop the network diagram which consists of three paths; each path resembles each
building. You calculate the duration for each path.

For the first building, the duration is 31 months, for the second building it will take 18 months,
and the third building will require 13 months to complete.

The first path is for the largest building, the second path is for the medium sized building, and
the third path is for the smallest building.

Now, review the above diagram.

Did you notice that the path for the first building is biggest in all three? It is thirteen months
bigger than the second path, and 18 months bigger than the third path.

This means that if you start working on the first building, you can wait 13 months to start work
on the second building, because you can complete second building in 18 months.

Likewise, you will have an 18 month wait time to start working on the third building, because it
will take only 13 months to complete. This means that even if you start working on the third
building after 18 months from the project start date, you can complete it on time.

This waiting period is known as float or slack. So, which one is the critical path in this network
diagram of three paths?

Of course, it is the longest path on the network diagram, because you cannot complete your
project before constructing the first building. Although you can complete the other two buildings
quickly, until you complete the first building, your project cannot be considered as completed.

Hence, the critical path is the longest path on the network diagram.
Now, tell me that what is the shortest duration in which you can complete the project?

Sure enough, it is 31 months, because you cannot complete your project before 31 months, and
this is the duration of the critical path.

Hence, the critical path is the shortest duration in which you can complete the project.

So, you see, both definitions are the same.

We can conclude that the critical path is the sequence of activities from start to end, and it has
the largest duration among all paths in a network diagram.

In ideal conditions, a network diagram should have only one critical path. However, if the
network diagram has more than one critical path, you will be in a difficult situation because in
this case you will have to manage more than one path in parallel.

As we know, the critical path has the largest duration, and its duration is known as the duration
of the project. Since activities on a critical path have no float or slack, no activity can be allowed
to be delayed. If this happens, the project will be delayed.

In case of delays, you can use schedule compression tool, such as fast tracking or schedule
crashing, to bring the project on track.

You must always update the network diagram if there is any change to it so that you can have a
better understanding of activities and predict the float, project completion dates, etc.

Benefits of the critical path method

The following are a few benefits of the critical path method:

It shows the graphical view of the project.


It discovers and makes dependencies visible.
It helps in project planning, scheduling, and controlling.
It helps in contingency planning.
It shows the critical path, and identifies critical activities requiring special attention.
It helps you assign the float to activities and flexibility to float activities.
It shows you where you need to take action to bring project back on track.

Although the critical path is very useful tool in project planning, it also has some limitations and
drawbacks.

Limitations/drawbacks of the critical path method

The critical path method is an optimal planning tool, which always assumes that all
resources are available for the project at all time.
It does not consider resource dependencies.
There are chances of mis-using float or slack.
Less attention on non-critical activities, though sometimes they may also become critical
activities.
Projects based on the critical path often fail to be completed within the approved time
duration.

To overcome these shortcomings of the critical path, the critical chain model was developed. In
the critical chain method, while developing the network diagram, resource constraints are also
taken into consideration.

Visit: Critical Chain Method in Project Management

Procedure for finding the critical path in a network diagram

The following is the procedure to find the critical path on a network diagram:

Draw the network diagram.


Identify all paths in the network diagram.
Find the duration of each path.
The path with the largest duration is the critical path.

Lets see the above procedure in action.

Example

Based on the below network diagram, identify the total paths, critical path, and float for each
path.

The above network diagram has five paths; the paths and their duration are as follows:

1. Start -> A -> B -> C-> End, duration: 31 days.


2. Start ->D -> E ->F -> End, duration: 18 days.

3. Start -> D -> B -> C -> End, duration: 26 days.

4. Start -> G ->H ->I -> End, duration: 13 days.

5. Start -> G -> E ->F -> End, duration: 16 days.

Since the duration of the first path is largest, it is the critical path. The float on critical path is
zero.

The float for the second path Start ->D -> E ->F -> End = duration of the critical path duration
of the path Start ->D -> E ->F -> End

= 31 18 = 13

Hence, the float for the second path is 13 days.

Likewise, we can calculate the float for other paths as well.

Float for the third path = 31 26 = 5 days.

Float for the fourth path = 31 13 = 18 days.

Float for the fifth path = 31 16 = 15 days.

Calculate Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF)

As we have identified the critical path, and duration of other paths, time to move on more
advanced calculations such as Early Start, Early Finish, Late Start, and Late Finish.

Calculating Early Start (ES) and Early Finish (EF)

To calculate the Early Start and Early Finish dates, we use forward pass; i.e. we will start from
the beginning and proceed to the end.

Early Start (ES) for the first activity on any path will be 1, because no activity can be started
before the first day of starting the project.

Formula used for calculate Early Start and Early Finish dates.

Early Start of the activity = Early Finish of predecessor activity + 1


Early Finish of activity = activity duration + Early Start of activity 1

Early Start and Early Finish Dates for the path Start -> A -> B -> C -> End
Early Start of activity A = 1 (Since this is the first activity of the path)

Early Finish of activity A = ES of activity A + activity duration 1

= 1 + 10 1 = 10

Early Start of activity B = EF of predecessor activity + 1

= 10 +1 = 11

Early Finish of activity B = ES of activity B + activity duration 1

= 11 + 12 1 = 22

Early Start of activity C = EF of predecessor activity + 1

= 22 +1 = 23

Early Finish of activity C = ES of activity C + activity duration 1

= 23 + 9 1 = 31

Early Start and Early Finish Dates for the path Start -> D -> E -> F -> End
Early Start of activity D = 1 (Since this is the first activity of the path)

Early Finish of activity D = 1 + 5 1 = 5

Early Start of activity E = EF of predecessor activity + 1

Now there is a trick. Since the Activity E has two predecessor activities, which one will you
select? You will select the activity with the greater Early Finish date. Early Finish of activity D is
5, and Early Finish of activity G is 3 (we will calculate it later).

Therefore, we will select the Early Finish of activity D to find the Early Start of activity E.

Early Start of activity E = EF of predecessor activity + 1

=5+1=6

Early Finish of activity E = 6 + 7 1 = 12

Early Start of activity F = 12 + 1 = 13

Early Finish of activity F = 13 + 6 -1 = 18

Early Start and Early Finish Dates for the path Start -> G -> H -> I -> End
Early Start of activity G = 1 (Since this is the first activity of the path)

Early Finish of activity G = 1 + 3 1 = 3

Early Start of activity H = 3 + 1 = 4

Early Finish of activity H = 4 + 4 1 = 7

Early Start of activity I = 7 +1 = 8

Early Finish of activity I = 8 + 6 1 = 13

Calculating Late Start (LS) and Late Finish (LF)

We have calculated Early Start and Early Finish dates of all activities. Now it is time to calculate
the Late Start and Late Finish dates.

Late Finish of last activity in any path will be the same as the Last Finish of the last activity on
the critical path, because you cannot continue any activity once the project is completed.

Formula used for Late Start and Late Finish dates:

Late Start of Activity = Late Finish of activity activity duration + 1


Late Finish of Activity = Late Start of successor activity 1

To calculate the Late Start and Late Finish, we use backward pass; i.e. we will start from the
last activity and move back towards the first activity.

Late Start and Late Finish Dates for the path Start -> A -> B -> C -> End
On a critical path, Early Start, and Early Finish dates will be the same as Late Start and Late
Finish dates.

Late Start and Late Finish Dates for the path Start -> D -> E -> F -> End

Late Finish of activity F = 31 (because you cannot allow any activity to cross the project
completion date)

Late Start of activity F = LF of activity F activity duration + 1

= 31 6 +1 = 26
Late Finish of activity E = LS of successor activity 1

= LS of activity F 1

= 26 1 = 25

Late Start of Activity E = LF of activity E activity duration + 1

= 25 7 + 1 = 19

Late Finish of activity D = LS of successor activity 1

If you look at the network diagram, you will notice that activity D has two successor activities, B
and E. So, which activity will you select?

You will select the activity with the lower Late Start date. Here, Late Start of activity B is 11, and
Late Start of activity E is 19.

Therefore, you will select activity B which has the lower Late Start date.

Hence,

Late Finish of activity D = LS of activity B 1

= 11 1 = 10

Late Start of Activity D = LF of activity D activity duration + 1

= 10 5 + 1 = 6

Late Start and Late Finish Dates for the path Start -> G -> H -> I -> End
Late Finish of activity I = 31 (because you cannot allow any activity to cross the project
completion date)

Late Start of activity I = 31 6 + 1 = 26

Late Finish of activity H = 26 1 = 25

Late Start of activity H = 25 4 + 1 = 22

Late Finish of Activity G = 19 1= 18 (we will choose the late start of activity E not activity H,
because the Late Start of activity E is lower than the Late Start of activity H)

Late Start of activity G = 18 3 + 1

= 16

Calculate the Free Float

I have already written a detailed blog post explaining the total float and free float, therefore, Im
not going to describe it now; rather, I will directly show you its calculation.

I strongly recommend you read my blog post on total float and free float to get a better
understanding.

Formula for the Free Float:

Free Float = ES of next activity EF of current activity 1

In our network diagram, only two activities can have the Free Float, activity D and activity G,
because only these two activities have more than one successor activities.

Free Float for activity D = ES of activity B EF of activity D 1

= 11 5 1

=5

Free Float of activity G = ES of E EF of G 1

=631

=2

NEXT: PRIMAVERA P6 PROJECT CONTROLS

You might also like