Water Distribution System Analysis and Design Using Epanet
Water Distribution System Analysis and Design Using Epanet
Allen M. Lowe
[email protected]
Objective
2
Design Criteria
Criteria Value
1. Demand Factor 0.3 – 2.0
2. Max. Allowable Head loss 10 m/km
3. Min. Allowable Head loss 0.5 m/km
4. Max. Allowable Pressure 70 m or 100 psi
5. Min. Allowable Pressure 7 m or 10 psi
6. Max. Allowable Velocity 3 m/sec
7. Min. Allowable Velocity 0.4 m/sec
8. Max. difference in ground 50 m
Elevation in a pressure zone
3
What Can Epanet Do?
4
Table of Contents
DAY 1
Computer Simulation
Pressure
Basic Hydraulic Principles
* Law of Conservation of Mass
* Law of Conservation of Energy
Main Principles of Network Analysis
* Continuity
* Energy Conservation
* Bernoulli’s Principle and Equation
Head Loss Equations
* Manning’s Equation
* Darcy-Weisbach Equation
* Hazen-Williams Equation
Exercises
Population and Water Demand Projections
- Water Demand Pattern
DAY 2
What is EPANET?
Capabilities of EPANET
Software
* Project Defaults
* Workspace
* Map Options Dialog
* Times Options Dialog
Physical Components of a Water Distribution System
* Reservoir
* Tanks
* Junctions
* Pipes
* Pumps
* Valves
Network Analysis and Design Procedure
Water Distribution Network Examples
Workshop
DAY 3
Computation of Total Pipe Cost Using Excel and .inp file of Epanet
Storage Requirements
Net Present Worth Cost
Presentation and Discussion of Results
5
Computer Simulation
The model assumes that water can only enter or leave from nodes
and that water cannot leak from links. Average Day Demand
(ADD) allocation is typically entered in the base demand of each
junction, which represents the ADD proportion of the service
connections near that junction.
6
In a typical water distribution system, water is normally drawn from
the network via service connections. Water is also drawn out of the
system via leaks in the pipelines. However, in modeling the water
distribution system, water is idealized to be drawn only from nodes,
the water drawn from all service connections and the leaks in the
pipes near a node area are lumped to that nearest node.
500
Demand Cubic Meters
400
300
200
100
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
7 Hour
When EPANET calculates the flow rates, velocity and headloss in
each link and pressures and head at each node for a steady state
pipe network system it is called a steady state analysis. This
analysis computes the pipe flow rates and the node hydraulic
grade line elevations (HGL) so that the conservation of energy and
mass are satisfied for any snapshot of the system.
2.5
1.5
Factor
0.5
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Series1 0.3 0.3 0.3 0.4 0.6 1.2 2 1.6 1.2 1.2 1.3 1.4 1.3 1.2 1.1 1 1.1 1.2 1.3 1.1 0.9 0.9 0.7 0.4
Hour
8
Three steps should be used to produce accurate simulation
models: Calibration, Verification, Validation.
9
Pressure
10
Pressure = height * specific weight
The SI (metric) unit for pressure is the pascal (Pa), equal to one
newton per square meter (N/m2). Non-SI (US) uses the pounds
per square inch (psi) and bars.
11
Basic Hydraulics Principles
Q = 1A1V1 = 1A2V2
where:
Q = the volumetric flow rate
A = the cross sectional area of flow
V = the mean velocity
density of the fluid
12
Q2 = 10 L/s Q1 = 10 L/s
D2 = 150 mm D1 = 75 mm
A2 = πD2/4 A1 = πD2/4
= 3.1416 * (.150 *.150) / 4 = 3.1416 * (.075 *.075) / 4
= 0.017672 m2 = 0.004418 m2
Q2 = V2 * A2 Q1 = V1 * A1
V2 = Q2 / A2 V1 = Q1 / A1
= 0.010 / 0.017672 = 0.010 / 0.004418
= 0.566 m/sec = 2.264 m/sec
Q2 = Q1
D2 / D1 = 2
A2 / A1 = 4
V1 / V2 = 4
13
Main Principles of Network Analysis
∑Inlet = ∑outlet
14
Main Principles of Network Analysis
15
Bernoulli’s Principle
This states that in a steady flow the sum of all forms of mechanical
energy in a fluid along a streamline is the same at all points on
that streamline. This requires that the sum of kinetic energy and
potential energy remain constant.
Bernoulli’s Equation
where:
16
For an ideal fluid,
17
Energy Grade Line(EGL) = Total Head
EGL = Pressure Head + Elevation Head + Velocity Head
10 PSI = 7 m of water
18
Changing pipe diameter and abrupt expansion
19
Head Loss Equations
Manning’s Equation
Darcy-Weisbach Equation
Hazen-Williams Equation
Manning’s Equation
hf = (nVL)
(1.49Rh2/3)
where
hf = Head loss (feet)
L = Pipe length (feet)
Rh = Hydraulic Radius = Area/Wetted Perimeter (feet)
V = Velocity (ft/sec)
n = Manning’s friction coefficient
20
Darcy-Weisbach Equation
where:
21
Hazen-Williams Equation
V = kCR0.63S0.54
where:
V = kCR0.63S0.54
V = kC(πd/4)0.63 * (hf/L)0.54
22
Hazen-Williams Equation
HL = 4.727328 LQ1.852
C1.852D4.8704
where:
Hazen-Williams Equation
Convert US to SI
K(SI) = 0.029689678
HL = 0.0297LQ1.852
C1.852D4.8704
where:
23
Hazen-Williams Equation
HL = 4.727 LQ1.852
C1.852D4.8704
where:
HL = 0.0297LQ1.852
C1.852D4.8704
where:
Q = ((HL* C1.852D4.8704 )
(0.0297 L))1/1.852
where:
HL = Head loss (meters)
L = Pipe Length (kilometers)
Q = Flow (Liters/sec)
D = Pipe Diameter (meters)
C = Roughness Coefficient (Hazen-Williams C-factor)
24
25
26
Equivalent coefficients for Hazen-Williams, Darcy-Weisbach and
Chezy Manning to have a headloss of 10 m/km.
Head
Diam Friction Velocity Loss
(mm) HWC D-W Factor C-M L/S m/s m/km
38 110 0.43 0.04365 0.01089 0.469 0.41 10.0
50 110 0.49 0.04064 0.01100 0.965 0.49 10.0
75 110 0.572 0.03657 0.01116 2.804 0.63 10.0
100 120 0.323 0.02852 0.01034 6.519 0.83 10.0
150 130 0.168 0.02187 0.00969 20.513 1.16 10.0
200 130 0.1735 0.02029 0.00979 43.713 1.39 10.0
250 130 0.1756 0.01915 0.00987 78.608 1.60 10.0
300 130 0.1758 0.01826 0.00993 126.97 1.80 10.0
350 130 0.175 0.01754 0.00999 190.44 1.98 10.0
400 130 0.1736 0.01643 0.01004 368.79 2.32 10.0
450 130 0.1718 0.01599 0.01008 486.54 2.48 10.0
500 130 0.1698 0.01345 0.01012 673.22 2.83 10.0
550 140 0.0675 0.01315 0.00943 846.32 2.99 10.0
600 140 0.066 0.01297 0.00946 994.5 3.00 10.0
650 140 0.067 0.01281 0.00952 1153.4 3.00 9.1
700 140 0.0685 0.01267 0.00958 1324 3.00 8.4
27
Hazen-Williams C-Factor
28
Given:
HL = 0.0297LQ1.852
C1.852D4.8704
HL = 0.0297 * 1 * (3)1.852
1201.852(0.100)4.8704
HL = 2.38 m
P = 20 – 2.38 = 17.62 m
29
Given:
HL = 0.0297LQ1.852
C1.852D4.8704
HL = ? m
P = 10 – ? = ? m
30
As you double the C-value, the head loss is reduced by 3.6 times.
31
As you double the pipe diameter, the carrying capacity increases
by 6.2 times, whereas the area only increases by 4 times.
32
Pipe Diameters (PVC)
for 10 m/km Headloss
50 110 0.97
75 110 2.80
100 120 6.52
150 130 20.50
200 130 43.69
250 130 78.57
300 130 126.90
350 130 190.34
400 130 270.42
450 140 396.96
500 140 523.70
33
Pipe Diameters (PVC)
for 5 m/km Headloss
50 110 0.66
75 110 1.91
100 120 4.44
150 130 14.00
200 130 29.85
250 130 53.71
300 130 86.80
350 130 130.24
400 130 185.09
450 140 271.79
500 140 358.66
34
Branch
Network
35
36
37
38
Exercises
39
40
41
42
43
44
Population and Water Demand Projections
http://psa.gov.ph
http://122.54.214.222 – Household/Population from 1990 to 2015.
45
46
47
48
Annual Growth Rate (r) = (Pn/Pa)1/n – 1
Example:
Population (2010) = 234,733
Population (2000) = 209,491
r = (234,733/209,491)1/10 – 1
r = (1.1205)0.1 – 1 = 0.011442 = 1.1442%
The PSA also issues projected growth rates for the different
municipalities and cities.
Using the projected growth rates, the population for each year can
be obtained using the formula:
Pn = Pa (1 + r)n
where:
49
Average Day Demand – The total annual quantity of water
production divided by 365. Residential + Gov’t + Commercial
(Industrial) Demands + Unaccounted for Water.
Peaking Factor = 1.0
Population Ratio
< 30,000 1.3:1
30,000-200,000 1.25:1
over 200,000 1.2:1
50
Water District data on production and consumption
http://www.lwua.gov.ph
http://122.54.214.222
51
Typical Water District Demand Pattern
Demand Pattern
500
Demand Cubic Meters
400
300
200
100
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Hour
2.5
2
Factor
1.5
1
0.5
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Series1 0.3 0.3 0.3 0.4 0.6 1.2 2 1.6 1.2 1.2 1.3 1.4 1.3 1.2 1.1 1 1.1 1.2 1.3 1.1 0.9 0.9 0.7 0.4
Hour
3
2.5
2
Factor
1.5
1
0.5
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Series1 0.3 0.3 0.3 0.4 0.6 1.2 2.5 1.5 1.2 1 1.2 1.3 1.3 1.2 1.1 1 1.1 1.2 1.3 1.1 0.9 0.9 0.7 0.4
Hour
52
53
Hydraulic Modeling Software
WaterCAD/WaterGEMS by Bentley
InfoWater by ESRI
HydrauliCAD
Hydronet
H2OMap Water
KYPipe
WATSYS
Epanet
54
Modeling of Water
Distribution Systems
Using EPANET
55
What is EPANET
56
Capabilities of EPANET
57
EPANET’s Workspace
58
Project Preferences
Bold Fonts
Uses bold fonts in all newly created windows.
59
Confirm Deletions
Displays a confirmation dialog box before deleting any object.
Temporary Directory
Name of the directory (folder) where EPANET writes its temporary
files.
Use the spin edit boxes to select the number of decimal places to
use when displaying computed results for the parameter.
60
Project Defaults
61
The Properties page of the Project Defaults dialog form sets
default property values for newly created nodes and links. These
properties include:
Flow Units
Units in which nodal demands and link flow rates are expressed.
Choosing liters or cubic meters causes all other units to be SI
metric, otherwise US customary units apply. Use caution when
changing flow units as it might affect all other data supplied to the
project.
Headloss Formula
Formula used to compute headloss as a function of flow rate in a
pipe. Choices are:
62
Hazen-Williams
Darcy-Weisbach
Chezy-Manning
Specific Gravity
Ratio of the density of the fluid being modeled to that of water at 4
deg. C (unitless).
Relative Viscosity
Kinematic viscosity of the fluid being modeled relative to the
viscosity of water at 20 deg. C (1.0 centistokes or 0.94 sq ft/day).
Maximum Trials
Maximum number of trials used to solve the nonlinear equations
that govern network hydraulics at a given point in time. Suggested
value is 200.
Accuracy
Convergence criterion used to signal that a solution has been
found to the nonlinear equations that govern network hydraulics.
Trials end when the sum of all flow changes divided by the sum of
all link flows is less than this number.
Suggested value is 0.001.
If Unbalanced
Action to take if a hydraulic solution is not found within the
maximum number of trials. Choices are STOP to stop the
simulation at this point or CONTINUE to use another 10 trials, with
no link status changes allowed, in an attempt to achieve
convergence.
Default Pattern
63
ID label of a time pattern to be applied to demands at those
junctions where no time pattern is specified. If no such time
pattern exists then demands will not vary at these locations.
Demand Multiplier
Multiplier applied to all baseline demands to make total system
consumption vary up or down by a fixed amount. E.g., 2.0 doubles
all demands, 0.5 halves them, and 1.0 leaves them as is.
Emitter Exponent
Power to which pressure is raised when computing the flow
through an emitter device. The textbook value for nozzles and
sprinklers is 0.5. This may not apply to pipe leakage.
Status Report
Amount of status information to report after a simulation is made.
Choices are
64
65
Menu Bar
The Menu Bar located across the top of the EPANET workspace
contains a collection of menus used to control the program. These
include:
File Menu
Edit Menu
View Menu
Project Menu
Report Menu
Window Menu
Help Menu
File Menu
The File Menu contains commands for opening and saving data
files and for printing:
Command Description
New Creates a new EPANET project
Open Opens an existing project
Save Saves the current project
Save As Saves the current project under a different
name
Import Imports network data or map from a file
Export Exports network data or map to a file
Page Setup Sets page margins, headers, and footers for
printing
Print Preview Previews a printout of the current view
Print Prints the current view
Preferences Sets program preferences
Exit Exits EPANET
Edit Menu
66
The Edit Menu contains commands for editing and copying.
Command Description
Copy To Copies the currently active view (map, report,
graph or table) to the clipboard or to file
Select Object Allows selection of an object on the map
Select Vertex Allows selection of link vertices on the map
Select Region Allows selection of an outlined region on the
map
Select All Makes the outlined region the entire viewable
map area
Group Edit Edits a property for the group of objects that
fall within the outlined region of the map
View Menu
Command Description
Dimensions Dimensions the map
Backdrop Allows a backdrop map to be viewed
Pan Pans across the map
Zoom In Zooms in on the map
Zoom Out Zooms out on the map
Full Extent Redraws the map at full extent
Find Locates a specific item on the map
Query Searches for items on the map that meet
specific criteria
Overview Map Toggles the Overview Map on/off
Legends Controls the display of map legends
Toolbars Toggles the toolbars on/off
Options Sets map appearance options
Project Menu
67
Command Description
Summary Provides a summary description of the
project's characteristics
Defaults Edits a project's default properties
Calibration Data Registers files containing calibration data with
the project
Analysis Options Edits analysis options
Run Analysis Runs a simulation
Report Menu
Command Description
Status Reports changes in the status of links over
time
Energy Reports the energy consumed by each pump
Calibration Reports differences between simulated and
measured values
Reaction Reports average reaction rates throughout the
network
Full Creates a full report of computed results for all nodes and links
in all time periods which is saved to a plain
text file
Graph Creates time series, profile, frequency, and
contour plots of selected parameters
Table Creates a tabular display of selected node
and link quantities
Options Controls the display style of a report, graph, or
table
Window Menu
68
Command Description
Arrange Rearranges all child windows to fit within the
main window
Close All Closes all open windows (except the Map and
Browser)
Window List Lists all open windows; selected window
currently has focus
Help Menu
Command Description
Help Topics Displays the Help system's Help Topics dialog
box
Units Lists the units of measurement for all
EPANET parameters
Tutorial Presents a short tutorial introducing the user
to EPANET
About Lists information about the version of
EPANET being used
69
Physical Components in a Water Distribution System
70
Reservoirs
The primary input properties for a reservoir are its hydraulic head
(equal to the water surface elevation if the reservoir is not under
pressure) and its initial quality for water quality analysis.
71
Tanks
72
Maximum
Initial
Diameter
Minimum
Elevation
73
Junctions
Junctions are points in the network where links join together and
where water enters or leaves the network. The basic input data
required for junctions are:
74
Pipes
Pipes are links that convey water from one point in the network to
another. EPANET assumes that all pipes are full at all times. Flow
direction is from the end at higher hydraulic head (internal energy
per weight of water) to that at lower head. The principal hydraulic
input parameters for pipes are:
75
Pumps
Pumps are links that impart energy to a fluid thereby raising its
hydraulic head. The principal input parameters for a pump are its
start and end nodes and its pump curve (the combination of heads
and flows that the pump can produce). In lieu of a pump curve, the
pump could be represented as a constant energy device, one that
supplies a constant amount of energy (horsepower if US or
kilowatts if SI) to the fluid for all combinations of flow and head.
76
Pump Curve
Head is the head gain imparted to the water by the pump and is
plotted on the vertical (Y) axis of the curve in feet (meters). Flow
rate is plotted on the horizontal (X) axis.
Single-Point Curve
Three-Point Curve
Multi-Point Curve
77
Single-Point Pump Curve
78
Three-Point Pump Curve
79
Multi-Point Pump Curve
80
Water Horsepower (WHP) = Q * TDH / 3960
where:
Q = Flow (gpm)
TDH = Total Dynamic Head (feet)
where:
Q = Flow (Liters/sec)
TDH = Total Dynamic Head (meters)
kW = 0.746 * HP
Power Factor is the ratio of the real power that is used to do work
and the apparent power that is supplied to the circuit.
81
Pumps (cont’d)
The principal output parameters are flow and head gain. Flow
through a pump is unidirectional and EPANET will not allow a
pump to operate outside the range of its pump curve. If system
conditions require more head than the pump can produce,
EPANET shuts the pump off. If more than the maximum flow is
required, EPANET extrapolates the pump curve to the required
flow, even if this produces a negative head. In both cases a
warning message will be issued.
82
Valves are links that limit the pressure or flow at a specific point in
the network.
The computed outputs for a valve are flow rate and headloss.
83
• partially opened (i.e., active) to maintain its pressure setting on
its upstream side when the downstream pressure is below this
value
• fully open if the downstream pressure is above the setting
• closed if the pressure on the downstream side exceeds that on
the upstream side (i.e., reverse flow is not allowed).
84
Throttle Control Valve - TCVs simulate a partially closed valve by
adjusting the minor head loss coefficient of the valve. A
relationship between the degree to which a valve is closed and
the resulting head loss coefficient is usually available from the
valve manufacturer.
85
Using Google Earth Pro as Backdrop Images in Epanet
86
• Click the restore down button on the right hand corner window.
Close the sidebar and toolbar.
Try to save the image by clicking File/Save/Save Image.
Uncheck all options in Map Options.
Change resolution to the maximum resolution, 4800x4800,
by dragging the right side of the window to the left or right
until the resolution is 4800x4800. Do not save yet.
• Position the placemark to the left of the screen, just barely
touching the left side of the window by dragging the window
to the left. The icon should now be in the middle half and
left of the window.
87
• Add the second placemark
• Name it as sam02 for sample SA
• Drag the placemark window to the left so that the
new icon is shown
• Click on the new icon and drag to the right side of the
window just barely touching the side
• Right click the first icon and click properties.
Copy the latitude value by selecting the latitude value
and pressing Control-C. Close the window.
• Right click the second placemark and click properties.
Replace latitude values in the top and in the view
section
by pasting the copied latitude using control-V
• Change range to 2000 to represent 2000 meters altitude
eye level
• Heading = 0, Tilt = 0
88
• Add the third placemark
• Name it as sam03 for sample SA
• Drag the placemark window to the left so that the
new icon is shown
• Click on the new icon and drag to the bottom side of the
window just above the barely touching digital mark
• Right click the first icon and click properties.
Copy the longitude value by selecting the longitude
value
and pressing Control-C. Close the window.
• Right click the third placemark and click properties.
Replace longitude values in the top and in the view
section
by pasting the copied latitude using control-V
• Change range to 2000 to represent 2000 meters altitude
eye level
• Heading = 0, Tilt = 0
89
• You may also want to save your placemarks so it can be
transported to another computer.
• Right click on the folder that you created and click
Save Place As. Enter your filename.
90
• Before saving, uncheck the placemark in the sidebar,
so that the icon is not copied in the image.
Save your images by clicking save image.
Input the filename = placemark name.
If the image is not showing any progress of clearing up or
moving to the other section, close Google Earth Pro and
start again by finding your placemark by double clicking it.
Resave again.
91
How to Use FSViewer to Stitch Together Saved Images
92
How to get a properly scaled background map image in
EPANET
93
3. Add the background map image you just saved to the project
(View menu – Backdrop – Load…).
94
6. If the pipe length as determined by EPANET’s Auto-Length
function does not match the length according to the map scale
do the following steps.
95
8. To re-scale the map, go to View – Dimensions… The default x
and y coordinates for the lower left corner should be (0, 0) and
for the upper right corner should be (10000, 10000). Multiply
both coordinates of the upper right corner by your re-scaling
factor. In the example from above, the new coordinates would
be (803.02, 803.02). Do not use Auto-Size, otherwise the
background will move its position and the scaling will also be
modified.
9. Try another pipe along the map scale and verify that Auto-
Length determines the correct length.
10. Save the file with the correct name of your project to reflect
the corrected scaled backdrop.
96
Network Analysis and Design Procedure Using EPANET
Add the nodes first, starting with tanks, then wells (as
reservoirs), then junctions.
97
time otherwise use the WELL pattern which is a basically a
multiplier of 1.
98
of service connections by clicking Projects/Compute
Demands and changing the parameters. Base Demand,
if negative is the average production rate of a source.
Demand Pattern can be left blank if the default pattern is
set to PHIL.pat or SUBD.pat. The base demand are
multiplied by the pattern's collection of multipliers to
allow it to vary over time.
50 mm to 75 mm (PVC)– 110
100 mm (steel) – 110
100 mm (pvc) – 120
150 mm and larger (steel) – 120
150 mm and larger (pvc) – 130
99
for headlosses and C-values. In case of unavailable
data, subtract 10-20 from C-values of new pipes.
100
system and not merely to show where your valves are
located. Say a PRV in a mountainous area to reduce
pressure in the system.
Design Criteria
Criteria Value
1. Demand Factor 0.3 – 2.5
2. Max. Allowable Head loss 10 m/km
3. Min. Allowable Head loss 0.5 m/km
4. Max. Allowable Pressure 70 m
5. Min. Allowable Pressure 7m
6. Max. Allowable Velocity 3 m/sec
7. Min. Allowable Velocity 0.4 m/sec
8. Max. difference in ground 50 m
Elevation in a pressure zone
101
Run the model by pressing the run button. If the run is
successful a faucet icon will appear at the bottom of the screen
and if there are any errors a warning message will show with the
corresponding error. If you edit the properties of the network after
a successful run has been made the faucet icon changes to a
broken faucet indicating that the current computed results no
longer apply to the modified network.
Using the design criteria, check that all parameters are met,
especially pressure and unit headlosses. Change all the diameters
and HWCs of pipes (except existing pipes) which do not meet the
maximum allowable unit headloss and maximum velocity in the
pipes. Put bigger diameter if it exceeds maximum unit headloss or
maximum velocity and put smaller diameter if unit headlosses or
velocities are too small. Use the flow diameter, which is the
required diameter to deliver the flow which will give a headloss
equal to the set maximum headloss, to guide you in changing the
diameter. This is repeated until all parameters meet the design
criteria.
102
Water Distribution Network Examples
103
Service Connection Sizing
A demand equal
to 20 liters per
minute cannot be
delivered by a ½”
service pipe.
There is negative
pressure at the
end of only 10m
line assuming 10
m initial pressure
at the beginning.
What is the
carrying
capacity?
104
Service Connection Sizing
A demand equal
to 20 liters per
minute can be
delivered by a
3/4” service pipe.
There is still 8.47
m pressure
assuming 10 m
initial pressure at
the beginning.
105
106
Given:
What will be the flow in the pipe if Horsepower rating of the pump
is equal to 2 HP? What will be the flow if the pipes are reduced to
75mm?
107
Solution:
108
109
Page 1 1/24/2014 1:14:46 PM
**********************************************************************
* E P A N E T *
* Hydraulic and Water Quality *
* Analysis for Pipe Networks *
* Version 2.0 *
**********************************************************************
Energy Usage:
----------------------------------------------------------------------
Usage Avg. Kw-hr Avg. Peak Cost
Pump Factor Effic. /m3 Kw Kw /day
----------------------------------------------------------------------
PS-1 100.00 75.00 0.09 2.19 2.19 524.80
----------------------------------------------------------------------
Demand Charge: 0.00
Total Cost: 524.80
Node Results:
----------------------------------------------------------------------
Node Demand Head Pressure Quality
ID LPS m m
----------------------------------------------------------------------
1 0.00 28.67 28.67 0.00
2 0.00 28.94 28.94 0.00
Res-1 -6.99 5.00 0.00 0.00 Reservoir
Tank-1 6.99 28.00 3.00 0.00 Tank
Link Results:
----------------------------------------------------------------------
Link Flow VelocityUnit Headloss Status
ID LPS m/s m/km
----------------------------------------------------------------------
1 6.99 0.89 13.38 Open
2 6.99 0.89 13.38 Open
PS-1 6.99 0.00 -23.94 Open Pump
110
111
112
113
Page 1 1/5/2014 9:13:15 AM
**********************************************************************
* E P A N E T *
* Hydraulic and Water Quality *
* Analysis for Pipe Networks *
* Version 2.0 *
**********************************************************************
114
Page 2
Link - Node Table: (continued)
----------------------------------------------------------------------
Link Start End Length Diameter
ID Node Node m mm
----------------------------------------------------------------------
40 29 33 122.60 100
41 33 34 32.75 100
42 28 30 108.46 100
43 30 34 122.66 100
44 28 31 56.07 100
45 31 32 61.43 100
46 32 35 122.79 100
47 35 36 83.56 100
48 27 37 148.85 50
49 39 37 119.60 75
50 36 39 32.92 75
51 37 38 30.45 75
52 38 40 127.32 50
53 40 42 35.19 50
54 38 41 43.95 75
55 41 48 29.82 75
56 42 48 68.87 50
57 48 43 45.72 75
58 43 44 216.67 50
59 44 45 174.05 50
60 46 45 84.88 50
61 46 49 61.34 50
62 34 35 32.08 150
64 53 46 115.21 75
65 52 53 329.01 75
66 51 52 108.44 75
67 50 51 101.03 75
68 47 50 83.51 75
69 Tank-1 2 25.56 200
1 4 54 5.17 150
20 35 55 3.90 150
PS-1 Well-1 Tank-1 #N/A #N/A Pump
Energy Usage:
----------------------------------------------------------------------
Usage Avg. Kw-hr Avg. Peak Cost
Pump Factor Effic. /m3 Kw Kw /day
----------------------------------------------------------------------
PS-1 100.00 75.00 0.10 4.02 4.02 965.64
----------------------------------------------------------------------
Demand Charge: 0.00
Total Cost: 965.64
115
Page 3
Node Results:
----------------------------------------------------------------------
Node Demand Head Pressure Quality
ID LPS m m
----------------------------------------------------------------------
1 0.33 69.77 21.77 0.00
2 0.30 69.95 17.95 0.00
3 0.57 69.69 30.69 0.00
4 0.65 69.65 21.65 0.00
5 0.40 69.83 16.83 0.00
6 0.55 69.55 23.55 0.00
7 0.25 69.46 25.46 0.00
8 0.33 69.20 27.20 0.00
9 0.40 69.27 25.27 0.00
10 0.38 69.34 24.34 0.00
11 0.25 69.39 25.39 0.00
12 0.20 69.10 25.10 0.00
13 0.25 68.85 26.85 0.00
14 0.28 68.73 27.73 0.00
15 0.73 68.52 29.52 0.00
16 0.15 69.14 29.14 0.00
17 0.15 69.12 30.12 0.00
18 0.20 68.35 24.35 0.00
19 0.47 69.78 17.78 0.00
20 0.15 69.12 28.12 0.00
21 0.95 68.42 28.42 0.00
22 0.45 69.18 27.18 0.00
23 0.17 69.49 19.49 0.00
24 0.12 69.77 22.77 0.00
25 0.47 68.07 32.07 0.00
26 0.17 69.09 31.09 0.00
27 0.63 67.84 39.84 0.00
28 0.30 69.07 34.07 0.00
29 0.28 68.99 29.99 0.00
30 0.55 68.97 34.97 0.00
31 0.15 69.02 39.02 0.00
32 0.35 68.97 38.97 0.00
33 0.15 68.92 28.92 0.00
34 0.30 68.91 33.91 0.00
35 0.50 68.91 38.91 0.00
36 0.17 68.71 34.71 0.00
37 0.65 67.35 42.35 0.00
38 0.25 67.12 46.12 0.00
39 0.25 68.37 39.37 0.00
40 0.35 66.79 42.79 0.00
41 0.05 66.94 45.94 0.00
42 0.30 66.79 45.79 0.00
43 0.55 66.72 57.72 0.00
44 0.65 65.62 52.62 0.00
45 0.40 65.62 49.62 0.00
46 0.33 65.77 47.77 0.00
47 0.25 67.49 26.49 0.00
116
Page 4
Node Results: (continued)
----------------------------------------------------------------------
Node Demand Head Pressure Quality
ID LPS m m
----------------------------------------------------------------------
48 0.28 66.82 44.82 0.00
49 0.45 65.62 47.62 0.00
50 0.23 67.20 41.20 0.00
51 0.05 66.94 40.94 0.00
52 0.10 66.68 40.68 0.00
53 0.05 65.99 45.99 0.00
54 0.00 69.65 21.65 0.00
55 0.00 68.91 38.91 0.00
Well-1 -11.40 43.00 0.00 0.00 Reservoir
Tank-1 -6.47 70.00 17.00 0.00 Tank
Link Results:
----------------------------------------------------------------------
Link Flow VelocityUnit Headloss Status
ID LPS m/s m/km
----------------------------------------------------------------------
2 8.69 0.49 2.04 Open
3 8.88 0.50 2.12 Open
4 8.37 0.47 1.90 Open
5 2.06 0.26 1.18 Open
6 7.04 0.40 1.38 Open
7 2.81 0.36 2.11 Open
8 6.42 0.36 1.16 Open
9 5.82 0.33 0.97 Open
10 1.25 0.28 2.23 Open
11 0.44 0.22 2.33 Open
12 2.12 0.48 5.98 Open
13 0.55 0.28 3.50 Open
14 8.83 0.50 2.10 Open
15 10.97 0.62 3.14 Open
16 1.41 0.32 2.80 Open
17 1.31 0.30 2.45 Open
18 9.19 0.52 2.26 Open
19 1.16 0.26 1.95 Open
21 0.15 0.08 0.32 Open
22 2.47 0.56 7.92 Open
23 10.03 0.57 2.66 Open
24 7.84 0.44 1.68 Open
25 1.74 0.39 4.15 Open
26 3.96 0.50 3.98 Open
27 7.54 0.43 1.57 Open
28 1.64 0.37 3.70 Open
29 5.33 0.68 6.89 Open
30 2.98 0.38 2.35 Open
31 0.20 0.10 0.54 Open
32 0.17 0.09 0.42 Open
33 0.12 0.06 0.23 Open
117
Page 5
Link Results: (continued)
----------------------------------------------------------------------
Link Flow VelocityUnit Headloss Status
ID LPS m/s m/km
----------------------------------------------------------------------
34 1.62 0.37 3.64 Open
35 5.75 0.33 0.95 Open
36 1.15 0.26 1.92 Open
37 3.95 0.22 0.47 Open
38 1.83 0.41 4.54 Open
39 1.62 0.21 0.76 Open
40 1.35 0.17 0.54 Open
41 1.20 0.15 0.43 Open
42 1.82 0.23 0.94 Open
43 1.27 0.16 0.49 Open
44 1.83 0.23 0.95 Open
45 1.68 0.21 0.81 Open
46 1.33 0.17 0.52 Open
47 3.00 0.38 2.37 Open
48 0.52 0.27 3.24 Open
49 2.57 0.58 8.52 Open
50 2.82 0.64 10.12 Open
51 2.45 0.55 7.77 Open
52 0.46 0.23 2.55 Open
53 0.11 0.06 0.18 Open
54 1.73 0.39 4.11 Open
55 1.68 0.38 3.90 Open
56 -0.19 0.10 0.49 Open
57 1.22 0.28 2.15 Open
58 0.67 0.34 5.10 Open
59 0.02 0.01 0.01 Open
60 0.38 0.19 1.77 Open
61 0.45 0.23 2.43 Open
62 2.17 0.12 0.16 Open
64 1.15 0.26 1.93 Open
65 1.20 0.27 2.09 Open
66 1.30 0.30 2.42 Open
67 1.35 0.31 2.60 Open
68 1.58 0.36 3.45 Open
69 17.88 0.57 1.91 Open
1 0.00 0.00 0.00 Open
20 0.00 0.00 0.00 Open
PS-1 11.40 0.00 -27.00 Open Pump
118
Workshop
119
Procedures in Designing a Distribution System
Using Google Earth and Epanet
120
junctions in between the pipe to cut the pipe to smaller length
especially if there are service connections in the pipes.
11. Autolength = on. Connect with pipes.
12. Count the nearest houses within junction and input in Service
Connections of junction. This will serve as basis for allocating
the base demand later.
13. Compute Base Demand using Projects/Compute Demands.
Change persons per connection, per capita demand and
Unaccounted-for water then press OK.
14. Input elevation of junctions taken from Google Earth.
15. Add patterns by loading from saved patterns - phil.pat,
subd.pat, well.pat, fire.pat. Rename the pattern IDs as PHIL,
SUBD, WELL and FIRE
16. Check the default pattern is either phil.pat or subd.pat from
Options/Hydraulics in the browser
17. Add Fire Hydrants and put base demands as 11 L/s and input
demand pattern as Fire. Run only with a maximum of two
hydrants at a time.
18. In Options/Times enter the Total Duration of simulation in 24
hours.
19. Enter Statistics = Maximum in Options/Times to get the
maximum values in the results when Epanet is run.
20. Run Epanet. Modify values of diameters and HWC so that
unit headlosses in pipes do not exceed 10 and not below 0.5.
Use Flow Diameter to guide you in changing the diameter.
Check pressures are acceptable. If pressures are too low,
unit headlosses may be further reduced to gain pressure or
add available head in pumps and tanks.
21. Return Statistics to None when done optimizing to get the
true values in the hydraulic results.
22. Check the results at 12:00 am - depicted as the low demand
but filling hours, 6:00 am – depicted as the peak hour, 12:00
NN as Max-Day demand + Fire Flow.
23. To print the final and most critical result – usually 6:00
depicting the peak hour, change the following in
Options/Times – Total Duration = 0, Pattern Start Time = 6:00
121
and do Report/Full and save to file the full report (.rpt). Open
the result with an editor (Notepad) and print.
24. Compute total pipeline cost using Pipe Cost.xls by first
exporting the Epanet file to inp file, opening the inp file and
selecting text starting from [PIPES] to just before [PUMPS],
copy text (Ctrl-C) and Paste (Ctrl-V) in excel file at A1. Total
pipeline cost is in K2.
122
Computation of Total Pipe Cost Using Excel and .inp file of Epanet
Use the provided pipe cost.xls to compute for the total pipe cost.
123
STORAGE REQUIREMENTS
124
STORAGE REQUIREMENTS
ALTERNATIVE ANALYSIS
b. Determine staging of source and storage facilities for all the three
alternative schemes
125
Net Present Worth Cost
Cn = Cc - Cs
Cc = C / (1 + i) n
Cs = C * (1 – (nx – n) / SL) / (1 + i) nx
where:
Cn = Ac / (1 + i) n
where:
Cn = present worth comparable cost
Ac = annual cost
i = discount rate
n = number of years between year of annual cost and base year
126