Modefied Format
Modefied Format
ON
SUBMITTED BY
ABC
ID: 0000000000
INTERNSHIP REPORT
ON
POWER GENERATION, TRANSMISSION AND PROTECTION SYSTEM
EQUIPMENTS OF ASHUGANJ POWER STATION COMPANY LIMITED
SUBMITTED BY
ABC (ID: 00000000000)
SUBMITTED TO
APPROVED BY
ACADEMIC ADVISOR
XYZ
HEAD OF DEPARTMENT
XYZ
2
Department of Technical Education, University of
Sargodha
Approval Letter
Acknowledgement
Executive Summary
Training Schedule
The following table contains my training schedule in XYZ Company Limited. My internship
started on 00 December, 2017 and ended on 11 May, 2018.
Date Division Time Instructor
26-12-11 Eng. XYZ (Operation)
Power Plant Training Center 8am to 5pm
27-12-11
Operation
to 8am to 5pm
28-12-11
29-12-11
Instrumentation and Control
to 8am to 5pm
(I&C)
01-01-12
6
Department of Electrical and Electronic Engineering, East West University
List of Abbreviations
CT = Current Transformer
PT = Potential Transformer
CB = Circuit Breaker
MW = Mega Watt
LPT = Low pressure turbine
IPT = Intermediate pressure turbine
HPT = High pressure turbine
ONAN = Oil Natural Air Natural, without pumps and fans
ONAF = Oil Natural Air Forced, without pumps for oil, with fans for air
7
Department of Electrical and Electronic Engineering, East West University
TABLE OF CONTENTS
Introduction.........................................................................................................................................................12
Company Objective.............................................................................................................................................13
Generation Details...............................................................................................................................................13
Financial Performance........................................................................................................................................14
Air collection........................................................................................................................................................16
Forced draft fan........................................................................................................................................................16
Air pre-heater...........................................................................................................................................................17
Flow transmitter.......................................................................................................................................................17
Fuel gas.................................................................................................................................................................17
Line gas control valve..............................................................................................................................................17
Gas flow meter.........................................................................................................................................................17
Gas heater................................................................................................................................................................18
Water collection...................................................................................................................................................18
Pump 18
Water purifying basin..............................................................................................................................................18
Water filter house....................................................................................................................................................18
De-hydronization process........................................................................................................................................19
Boiler.....................................................................................................................................................................19
Water tube boiler.....................................................................................................................................................19
Ignition 20
Burner 20
Boiler drum..............................................................................................................................................................21
Safety valve.............................................................................................................................................................21
Pressure gauge.........................................................................................................................................................21
Boiler efficiency......................................................................................................................................................21
Stack 22
Turbine...................................................................................................................................................................22
Sections of steam turbine.........................................................................................................................................22
Operation and maintenance.....................................................................................................................................23
Introduction of CCPP...........................................................................................................................................24
Economizer.............................................................................................................................................................28
Damper...................................................................................................................................................................28
CHAPTER - 4 SUBSTATION................................................................................................................................30
Introduction of substation.....................................................................................................................................30
Equipment of Substation.......................................................................................................................................30
Bus Bars...................................................................................................................................................................30
C.T (Current Transformer)......................................................................................................................................31
P.T (Potential transformer)......................................................................................................................................31
Transformer..............................................................................................................................................................32
Insulator...................................................................................................................................................................33
Isolator 33
Lightning Arresters..................................................................................................................................................33
Sub-station Auxiliary Supply..................................................................................................................................34
Circuit Breaker......................................................................................................................................................35
SF6 circuit breaker...................................................................................................................................................36
Oil Circuit Breaker..................................................................................................................................................36
Relay.......................................................................................................................................................................37
Electrical Relay.......................................................................................................................................................37
Electronics Overload Relay.....................................................................................................................................37
Buchholz relay.........................................................................................................................................................37
CHAPTER - 5 GENERATOR................................................................................................................................38
Introduction to Generator....................................................................................................................................38
AC generator..........................................................................................................................................................38
Generator Synchronization..................................................................................................................................39
Generator Protection............................................................................................................................................39
Over current protection............................................................................................................................................39
Stator Winding Protection.......................................................................................................................................40
Over current with under voltages.............................................................................................................................40
Over Speed Protection.............................................................................................................................................41
Negative Sequence Protection.................................................................................................................................41
Reverse Power Protection........................................................................................................................................42
Under Frequency Protection....................................................................................................................................43
Minimum impedance and Distance protection.......................................................................................................43
Stator ground fault protection..................................................................................................................................44
Back-up earth fault protection.................................................................................................................................44
Combustion Control..............................................................................................................................................49
Safety Valve............................................................................................................................................................49
Pressure gauge........................................................................................................................................................50
Flame detector........................................................................................................................................................51
Junction box...........................................................................................................................................................52
Fire alarm...............................................................................................................................................................52
CHAPTER - 7 CONCLUSION..............................................................................................................................54
My achievements....................................................................................................................................................54
Problem faced........................................................................................................................................................54
Recommendations.................................................................................................................................................54
Discussion................................................................................................................................................................55
References....................................................................................................................................................................55
LIST OF TABLE
Table 1-1: Generation details of APSCL..................................................................................................................13
Table 1-2: Financial performance of APSCL...........................................................................................................14
Table 1-3: Salient feature of the 225MW future project.........................................................................................15
Table 1-4: Salient feature of the 450MW future project ........................................ Error! Bookmark not
defined.15 Table 1-5: Salient feature of the 450MW (North) future project........................................................15
131
Department of Electrical and Electronic Engineering, East West University 3
List of Figures
Figure 2-1: Forced draft fan......................................................................................................................................16
Figure 2-2: Gas flow meter.........................................................................................................................................17
Figure 2-3: Water filter house...................................................................................................................................18
Figure 2-4: Burner room with water tube boiler....................................................................................................20
Figure 2-5: Steam turbine..........................................................................................................................................22
Figure 3-1: Design diagram of CCPP in APSCL....................................................................................................24
Figure 3-2: Combustion chamber in CCPP.............................................................................................................25
Figure 3-3: Diesel engine of CCPP............................................................................................................................26
Figure 3-4: Fuel annex room in CCPP.....................................................................................................................27
Figure 3-5: Design of Steam Generation process in CCPP....................................................................................29
Figure 4-1: A typical bus bar of APSCL..................................................................................................................30
Figure 4-2: A typical CT............................................................................................................................................31
Figure 4-3: A typical PT.............................................................................................................................................31
Figure 4-4: Bushing of transformer..........................................................................................................................32
Figure 4-5: Silica gel in a cylinder.............................................................................................................................32
Figure 4-6: Insulator used in APSCL.......................................................................................................................33
Figure 4-7: Isolator used in APSCL..........................................................................................................................33
Figure 4-8: Double bus-bar arrangement.................................................................................................................34
Figure 4-9: Double bus bar transmission arrangement of APSCL.......................................................................35
Figure 4-10: SF6 circuit breaker...............................................................................................................................36
Figure 4-11: Oil circuit breaker................................................................................................................................36
Figure 5-1: Generator in APSCL..............................................................................................................................38
Figure 5-2: Over current protection.........................................................................................................................39
Figure 5-3: Stator Winding Protection.....................................................................................................................40
Figure 5-4: Over current protection.........................................................................................................................41
Figure 5-5: Negative sequence protection................................................................................................................42
Figure 5-6: Reverse power Protection use in APSCL.............................................................................................42
Figure 5-7: Minimum impedance and Distance protection...................................................................................44
Figure 5-8: Stator ground fault protection..............................................................................................................44
Figure 5-9: Earth fault protection of field circuit by potentiometer method & the relay used in APSCL........45
Figure 6-1: Total output unit measure meter...........................................................................................................46
Figure 6-2: Control unit 1 &2....................................................................................................................................46
Figure 6-3: Control unit 3 & 4...................................................................................................................................47
Figure 6-4: Combine cycle control unit.....................................................................................................................47
Figure 6-5: Feed water drum level control..............................................................................................................48
Figure 6-6: Safety valve used in APSCL...................................................................................................................49
Figure 6-7: Typical pressure gauge...........................................................................................................................50
Figure 6-8: Flame detector.........................................................................................................................................51
Figure 6-9: Junction box used in APSCL.................................................................................................................52
Figure 6-10: Fire alarm used in APSCL..................................................................................................................52
141
Department of Electrical and Electronic Engineering, East West University 4
CHAPTER - 1 Company Profile
I did my internship at XYZ Power Station Company Ltd from 26th of December 2017 to 11th
of May 2018 and this internship report is the result of those 120 days attachment with the XYZ.
Introduction
XYZ Power Station Company Ltd. (APSCL) owns the second largest power station in
Pakistan. The installed capacity by its 9 units is 777 MW and present de-rated capacity is 642
MW. Electricity generated in this power station is supplied to the national grid and distributed to
the consumers throughout the whole country. This power station plays a significant role in the
national economic development by generating more than 15% of the total demand of electricity
in the country.
Power Sector Development and reform Program of the Government of Pakistan, XYZ Power
Station Company ltd, has been incorporated under the companies Act 1994 on 28 June 2000.
All the activities of the company started formally on 01 June 2003. From that day the
overall activities of the company along with the operation, maintenance and development are
vested upon a Management Team consisting of the Managing Director, the Director (technical)
and the Director (Finance).
In this power station Natural Gas from Titas Gas Transmission and Distribution Company Ltd. is
used as fuel. Water from XYZ is used through in-take channels for steam generation and
cooling of generated steam. Used water (for cooling) is again thrown into the XYZ through
discharge channels. Huge water from the discharge channels is used for irrigation in the dry
season. Approximately 36,000 acres of land of XYZ are irrigated by this water. [3], [4]
151
Department of Electrical and Electronic Engineering, East West University 5
Company Objective
i. To carry out the business of electric power generation
ii. To supply and sell electricity to XYZ Power Development Board through National Grid.
iii. To undertake projects to increase the power generation of XYZ to meet the growing
demand of electric power in the country.
iv. To increase the net worth of the company.
Generation Details
Table 1-1: Generation details of APSCL
Particulars of Gas
Unit 01 Unit 02 Unit 03 Unit 04 Unit 05 GT 01 GT 02 ST (cc)
Operation Engine
Brown
Brown Brown Brown Brown
Boveri GEC, GEC,
Make & Boveri Boveri Boveri Boveri GEC,
190 69.6 69.6 Genbac
Capacity of 80 Mva, 80 Mva, 190 Mva, 190 Mva, 43 Mva,
Mva, Mva, Mva, her
Turbo- 11Kv, 0.5 11Kv, 15.75Kv, 15.75Kv, 13.8 Kv
15.75Kv, 13.8 Kv 13.8 Kv
Alternator pf 0.5 pf 0.5 pf 0.5 pf
0.5 pf
Date of
Commissionin 17-08-70 08-07-70 17-12-86 04-05-87 21-03-88 15-11-82 23-03-86 28-03-84 30-04-11
g
Year of Last
1989 1994 2003 2011 2008 2004 2000 n/a n/a
Overhauling
Generated
energy since
installation(G 10575.44 9807.24 22455.89 21306.43 29952.39 5985.33 6662.45 1745.36 5983.88
wh)
Load factor
68.96 68.96 69.24 71.35 84.80 99.42 92.29 98.03 95.00
(in 2011) %
Station heat
rate 11979 11696 12076 11017 10356 18175 18175 0 9366
Kcal/Kwh
Stationary
Thermal
29.97 30.87 29.89 31.75 34.86 19.86 19.86 0 38.54
Efficiency in
2011
Cost of fuel
per unit
0.93 0.87 0.90 0.90 0.79 1.30 1.30 0.00 0.69
generation in
Tk
161
Department of Electrical and Electronic Engineering, East West University 6
Financial Performance
Despite adversities XYZ maintained a substantial progress during the year 2017-81, increase
revenue by 5.8% over the last year resulted increase the net profit ,before interest and tax to PKR
1408 million as against PKR 749 million of 2009-10 a 87% increase .The profit growth was at
a phenomenal rate of 146.49%. A comparative detail of financial result of 2009-10 is given
below:
171
Department of Electrical and Electronic Engineering, East West University 7
of the project will start soon. The salient feature of the project is given below:
181
Department of Electrical and Electronic Engineering, East West University 8
Table 1-3: Salient feature of the 225MW future project
Capacity 225 MW
EPC Contract Price USD61,970,240 +EURO60,362,742+BDT2,530,772,664
ECA Backed Project Financer Expecting ECA support
Mandated lead arranger Standard Chartered Bank
Contract Agreement signing Date
Expected date of completion
Project duration 25 months
Fuel Natural Gas
ii. XYZ 450 MW Combine Cycle Power Plant Project: The company has also initiated
the process to install another 450 MW combined cycle power plant using ECA
funding. The evaluation of the Bid is under process. Key information of the project is
placed bellow:
Capacity 450 MW
Estimated Cost of Project BDT 3,333 Crore
Expected project financing ECA backed project finance
Project completion time 27 months
Expected contract agreement June, 2012
Expected date of completion September, 2014
Current status Selection of EPC contractor in progress
Fuel Natural Gas
iii. XYZ 450 MW Combine Cycle Power Plant (North) Project: The Company is also
taken up program to install another 450MW Combine Cycle Power Plant, jointly
financed by Habib Bank Limited (HBL) and United Bank Limited (UBL). A brief
particulars of the project is furnished below:
Capacity 450 MW
Estimated project Cost PKR 3,400 Crore
Project finance HBL & UBL
Expected Completion October, 2019
Current status Engagement of Consultant is in process
191
Department of Electrical and Electronic Engineering, East West University 9
Fuel Natural Gas
202
Department of Electrical and Electronic Engineering, East West University 0
CHAPTER - 2 Steam turbine power plant
In this part of my internship training Mr. XYZ (Manager of I & C) was my instructor
where I worked 30 days. I visited steam turbine unit, gas distribution, water pump, water
purification process and turbine
212
Department of Electrical and Electronic Engineering, East West University 1
2.3 Air pre-heater
In the air pre heater chamber air is heated to remove moisture from air. There is a drive in the
chamber which uniformly distributes heat all over the chamber. If the motor’s rpm is less than 2
then it gives a signal to the control room. If this low speed persists for a 3 minutes it trips boiler.
A tachometer is connected with the driver to measure the speed.
222
Department of Electrical and Electronic Engineering, East West University 2
2.7 Gas heater
Gas heater is used to dry gas. Gas pipe is taken through the steam chamber so gas is heated by
steam. This heat removes moisture and different particle from gas.
2.9 Pump
In APSCL there are three circulating water pumps for collecting water from river. In every place
there are two pumps one is working and another is standby. There is a discharge valve behind the
pump which is driven by oil. This valve works as either 0% close or 100% open. If it takes time
from 0% close to 100% open more than 90 sec then the pump will trip. This water which collects
from river goes to condenser to condensate steam. Rest of the water goes to purify then goes to
river again.
232
Department of Electrical and Electronic Engineering, East West University 3
In the water filter house there are different type tanks and filters which purify the water. There
are four polyelectrolyte tanks where two is used for checking ph. There are two gravel filters. It
works very effectively by pulling water down through the gravel, where the solid debris is
trapped close to the surface, and the soluble waste is broken down by bacteria that grow on the
gravel surface further down. The clean water is then taken back to the surface. The lower level of
impurities not only reduces corrosion rates in the boiler but also reduces the erosion of the
turbine blades
2.12 Boiler
The basic purpose of a boiler is to turn water into steam, in this case super-heated steam. This
operation sounds relatively simple but is actually more complicated. The boilers utilized on
campus are of the stack drum type, which means there are drums within the boilers and flue gas
through the stack to atmosphere. The upper drum is called a boiler drum and is where saturated
steam leaves the boiler. While the lower drum is called the mud drum and is where liquid feed
water enters. Tubes called rises and down comers are used to connect the two drums. All the
energy required within the boiler is produced by the combustion of a fuel.
242
Department of Electrical and Electronic Engineering, East West University 4
2.14 Ignition
The ignition coil is the component that connects directly with electricity line and includes two
transformer windings. The primary winding feeds into the distributor, while the secondary
winding connects to the spark plugs. When enough energy has been created, the spinning cam
opens a breaker, which causes a high-voltage jump in the ignition coil. This voltage surge is
transported to the spark plugs, resulting in the necessary electric spark to begin ignition. At the
beginning of the firing of the burner small amount of natural gas and air is needed. This small
amount of gas is known as ignition gas which is supplied into the burner by ignition pipe or line.
After the burner is on the ignition line is turned off and main line for fuel and air supply is turned
on.
Burner
Burner is the chamber in the boiler where natural gas or coal is burned with the presence of air
for producing heated gas or flue gas. In Ashuganj Power Station Company Ltd (APSCL) natural
gas is burned with the presence of air for generating heat for making steam. In steam turbine
power plant of APSCL each furnace chamber has nine furnaces. The temperature inside the
furnace chamber is 1200-1500°C. The treated water from the feed water tank through
economizer enters into the boiler through tubes and the flue gas produced inside the furnace
passes through the tubes.
252
Department of Electrical and Electronic Engineering, East West University 5
2.14 Boiler drum
It is the place where the water is reserved which comes through the economizer. Inside the drum
upper and lower level of amount of water is measured by the level transmitters. If the level
crosses the upper limit or goes below the lower limit then the plant will trip. So it is very
important to control the level of the water. This is done by an automatic system. From the boiler
drum the saturated steam is transferred into super heater.
262
Department of Electrical and Electronic Engineering, East West University 6
2.18 Stack
Stack or chimney is a passage through which flue gas escape from a fire or furnace. From the
furnace flue gas is produced. This flue gas is used to create the steam for rotating the turbine.
The flue gas passes through several equipments and finally goes into the nature through stack.
Turbine
A steam turbine is a mechanical device that extracts thermal energy from pressurized and
converts it into rotary motion. The turbine mainly consists of nozzle and rotary and fixed blade
wheel. The steam is expanded from a high pressure to a low pressure either in nozzles or in the
blade where it is transformed into the mechanical work. The steam power plant of APSCL has a
casing around the blades that contains and controls the working fluid.
i. High Pressure Turbine (HP): From the super heater the high speed steam first enters to
the high pressure turbine. The blades in the high pressure turbine are the smallest of all
turbine blades; this is because the incoming steam has very high energy and occupies a
low volume. The blades are fixed to a shaft and as the steam hits the blades it causes the
272
Department of Electrical and Electronic Engineering, East West University 7
shaft to rotate.
282
Department of Electrical and Electronic Engineering, East West University 8
ii. Intermediate Pressure Turbine (IP): From the boiler re-heater the steam enter into the
intermediate pressure turbine. The steam has expanded and has less energy when it enters
this section, so here the turbine blades are bigger than those in the high pressure turbine.
The blades are fixed to a shaft and as the steam hits the blades it causes the shaft to rotate.
From here the steam goes straight to the next section of turbine set.
iii. Low Pressure Turbine (LP): From the intermediate pressure turbine steam enters into
the low pressure turbine and continues its expansion. The blades of the turbine of this
section are larger than the previous two sections but the energy of steam is lesser than the
previous two sections.
292
Department of Electrical and Electronic Engineering, East West University 9
CHAPTER - 3 Combine Cycle Power Plant
In this part of my internship training Mr. XYZ (Manager of CCPP) was my instructor where I
worked 30 days. I visited combine cycle power plant (CCPP), gas turbine generation, steam
turbine generation in CCPP.
Ashuganj Power Station Company Ltd. (APSCL) uses gas as fuel to generate the heat. This heat
is used to heat water and create steam. Then the steam passes through turbine which transfers the
thermal energy of the steam to the mechanical energy. A generator rotor is attached with this
turbine and generator transfer mechanical energy to the electrical energy. There are five steam
turbine power plants in APSCL. Installed capacity of steam turbine power plant in APSCL is
578MW.
303
Department of Electrical and Electronic Engineering, East West University 0
combustion chamber. The balance of the compressed air passes around the chamber to absorb
313
Department of Electrical and Electronic Engineering, East West University 1
heat, and then it is merged with the burned products of combustion. The pressurized mixture,
usually at 1010°F or higher, flows into a reaction turbine. The turbine drives the compressor and
also produces work by driving the generator. A portion of the exhaust gas may be re-circulated
and it is possible to recover heat energy from the waste exhaust.
3.3 Compressor
The compressor is driven by the turbine through a common shaft. Air enters the compressor via
an inlet duct. The compressor increases the air pressure and reduces the air volume as it pumps
air to the combustor and through the engine. At the begging of the generation compressor is
routed by diesel engine in APSCL.
323
Department of Electrical and Electronic Engineering, East West University 2
3.4 Diesel Engine
The gas turbine is not a self-exciting machine. The turbine only can be rotated if fuel and air is
burned inside the combustion chamber. But before the turbine starts the air cannot be sucked by
the compressor automatically because the compressor is coupled with the turbine. So a diesel
engine is coupled with the turbine to rotate the turbine at the beginning for helping to suck air by
the compressor. At first the diesel engine starts. When the turbine starts to move by the diesel
engine at 2008rpm speed then the diesel engine is turned off.
333
Department of Electrical and Electronic Engineering, East West University 3
3.6.1 Fuel System
The system provides the engine with the proper amount of fuel to sustain operation. System
components include filters, a fuel manifold, fuel tubes, and nozzles. Off-engine components
include the fuel control equipment and a supply system. Fuel (in APSCL it is natural gas) enters
the tubular fuel manifold ring via the supply system. The fuel tubes direct the fuel from the
manifold to the fuel nozzles which are mounted in the fuel. In APSCL gas comes from Titas.
343
Department of Electrical and Electronic Engineering, East West University 4
3.6.4 Starting System
In APSCL normally generator starts by a diesel engine. At first diesel engine starts to rotate the
shaft and when it rotates at 700rpm then it is fired. Usually after 2008rpm, diesel engine
disconnects and gas engine began working independently.
3.6.5 Economizer
Economizers are mechanical devices intended to reduce energy consumption, or to perform
another useful function such as preheating a fluid. It used for Boiler heating, ventilating, and air-
conditioning purpose.
3.6.6 Damper
Dampers are often provided in CCPP so the gas turbine exhaust can bypass the heat recovery
boiler allowing the gas turbine to operate if the steam unit is down for maintenance.
Supplementary oil or gas firing is also included to permit steam unit operation with the gas
turbine down.
353
Department of Electrical and Electronic Engineering, East West University 5
o o
230 c 100 c
er HP Deareator
40 oc
am
Boil
dr
L.P. Evaporator
HP. Evaporator
3.7.2 De-aerator
In combine cycle power plant it is used as the preserver of feed water which comes from the
condenser by extraction pump. At this stage the temperature of feed water which enters the de-
aerator is 40°C. From de-aerator the feed water is flowed into the low pressure evaporate again
goes to de-aerator. When feed water through the LP Evaporate then it gains heat which is 100°C.
363
Department of Electrical and Electronic Engineering, East West University 6
CHAPTER - 4 Substation
In this part of my internship training Mr. XYZ (Manager of Substation) was my instructor
where I worked 30 days. I visited sub-station yard, transmission field, sub-station control
room.
373
Department of Electrical and Electronic Engineering, East West University 7
Figure 4-1: A typical bus bar of APSCL
383
Department of Electrical and Electronic Engineering, East West University 8
4.2.2 C.T (Current Transformer)
In electrical engineering, a current transformer (CT) is used for measurement of electric currents.
When current in a circuit is too high to directly apply to measuring instruments, a current
transformer produces a reduced current accurately proportional to the current in the circuit,
which can be conveniently connected to measuring and recording instruments. A current
transformer also isolates the measuring instruments from what may be very high voltage in the
monitored circuit. Current transformers are commonly used in metering and protective relays in
the electrical power industry. [1]
393
Department of Electrical and Electronic Engineering, East West University 9
Figure 4-3: A typical PT
404
Department of Electrical and Electronic Engineering, East West University 0
4.3 Transformer
Transformer is a static device used to transform power from one voltage level without changing
the frequency. There are different parts of a transformer given below:
i. Bushing: This maintains the incoming and outgoing connection of a transformer.
ii. Radiator: This is used to radiate the heat of a transformer when transformer is heated up
at a certain level.
iii. Oil temperature meter: This meter indicates the temperature of transformer oil. If
temperature crosses a certain level then it makes an alarm.
iv. Temperature meter: This meter indicates the temperature of transformer windings. If
temperature crosses a certain level then it starts the winding fans.
v. Oil level meter: This meter indicates the oil level of transformer. If oil is low than a
certain amount it makes an alarm that means that transformer have to feed oil.
vi. Silica gel: It works like breathing. There have a little amount oil under the silica gel
which suck the moisture of air and further sends this air to silica gel which further sucks
the rest of the moisture of the air.
vii. Exchanger: Regulate voltage through winding selection between primary & secondary
side.
viii. PRD (Pressure relief device): release the oil pressure by releasing oil when oil pressure
414
Department of Electrical and Electronic Engineering, East West University 1
is high.
424
Department of Electrical and Electronic Engineering, East West University 2
4.4 Insulator
Porcelain or ceramic insulator is used in substation to support the live conductors and bus bars.
4.5 Isolator
Islators are used for isolating the circuit when the current has already been interupted. They
allow currents into the circuit until curcuit is repair again. Isolators re used for connecting and
disconnecting parts of electrical installation after de-energizing.
434
Department of Electrical and Electronic Engineering, East West University 3
4.7 Sub-station Auxiliary Supply
In any substation, there are many equpinment and arrangements to supply power. Sometimes
these equipments and arrangements are out of order due to different reasons and there have also
several equipments (eg: circuit breakers, relay, isolator) to protect others. If the feeding line of
protection provider equipment is failing then there should be an auxiliary power system.
Generally this auxiliary power supply is DC supply.
444
Department of Electrical and Electronic Engineering, East West University 4
Figure 4-8: Double bus-bar arrangement
454
Department of Electrical and Electronic Engineering, East West University 5
APSCL Uses double line bus bar arrangement scheme for their transmission purpose. They
provide their generated power to Shajibazar, Ghorashal, Kishoregonj through double bus bar
system.
464
Department of Electrical and Electronic Engineering, East West University 6
4.8.3 SF6 circuit breaker
SF6 is inert gas the property of this gas the higher pressure and temperature its dielectric strength
will be SF6has two gas chamber when contract is close the pressure is two chamber have the
same pressure but when the contract is open then one of the chamber get totally close and other
remain open ,there is a narrow channel between two chamber and when contract open the SF6
flow a plane of high pressure region to the low pressure region there will be turbulence of SF6.At
zero current the turbulence of SF6 absorb all the ions and since it is flowing from a narrow
region hence it provide high dielectric strength but there is problem that the pressure of SF6 is
not always remain fixed due to leakage in the cylinder of SF6 so there is pressure gauge as well
as alarm attached with it. Whenever pressure decreases the alarm ringing and the gas is refilled
to increase pressure.
474
Department of Electrical and Electronic Engineering, East West University 7
Figure 4-11: Oil circuit breaker
484
Department of Electrical and Electronic Engineering, East West University 8
4.9 Relay
A relay is a device used to control the operation of a magnetic contactor or other device .relay
operate as a function of current ,voltage ,heat .and pressure and supply the “intelligence” that is
necessary to provide automatic acceleration, protect against overload ,under voltage, excessive
speed, excessive torque, etc. At APSCL two types of relay is used. One is electrical relay and
another is electronics relay. [7]
494
Department of Electrical and Electronic Engineering, East West University 9
CHAPTER - 5 Generator
In this part of my internship training Md. Kamruzzaman (Senior Eng. of Generator) was my
instructor where I worked 3 days. I visited Generation control room, generator, and steam
turbine. Here I learned about Generator and different types of protection of generator.
5.2 AC generator
Ac generator also called synchronous generators or alternators. Ac generators are the principal
sources of electrical power throughout the world, and range in size from a fraction of a KVA to
1500 MVA. Alternating voltage may be generated by rotating a coil in the magnetic field or
rotating by magnetic field within a stationary coil. The value of voltage generated depends on –
i. The numbers of turn in the coil.
ii. Strength of the field.
505
Department of Electrical and Electronic Engineering, East West University 0
iii. The speed at which the coil or magnetic fields rotate.
515
Department of Electrical and Electronic Engineering, East West University 1
5.3 Generator Synchronization
The process of connecting an AC generator to other AC generators is known as synchronization
and is crucial for the generation of AC electrical power. An AC machine must match both the
amplitude and the timing of the network voltage, which requires both speed and excitation to be
systematically and closely controlled for synchronization. [2]
7000/5A
IN=5A
over current relay
O/C
Timer
In APSCL generator unit 3, 4 and 5 uses rated terminal voltages 15.75kv and rated current
6995A. Hear over current relay connect through the CT with the terminal and use CT ratio
70000V/5A. Inversely we can say if 5A current flow the voltages flow 7000V,Over current relay
consists of two types of relay, one is time delay relay which is connect with timer another is
525
Department of Electrical and Electronic Engineering, East West University 2
instantaneous relay. In APSCL timer setting time is 0.5second. When time delay activated than
start time counting and after 5second is breaks contract, on the other hand instantaneous relay
operate instantaneously. Generally nominal current is 5A. If 0.9 times of nominal current flow
through the line then time delay activated or if 1.2 times of nominal current flow through the line
then instantaneous relay activated. In these case time delay activated but it start time counting
where instantaneous relay operate instantaneously.
Suppose fault occurs in the terminal than high current (9000A) appear in the line time delay start
time counting but instantaneous relay trip the breaker instantaneously. In the power r system
time delay relay operate when load increase in the feeder line and instantaneous relay operate
when fault in the line.
6995A
6995A
6995A
5A 2A
3A
535
Department of Electrical and Electronic Engineering, East West University 3
in than the terminal voltages reduces ,for these reasons power system appear over current and
545
Department of Electrical and Electronic Engineering, East West University 4
under voltages appear .when in the power system both condition appear then the under voltages
with over current relay activated .if over current relay activated we understands that huge amount
of fault in the system occurred ,if under voltage appear we can are confuse if it is fault or over
load occurred or over voltages.
In the power system main causes of over voltages occur Sudden load rejection, Lightening, Line
fault.
7000V/5A
16KV/ 110V
1.2IN
0.8IN
over currentwith
under voltages
relay
555
Department of Electrical and Electronic Engineering, East West University 5
6995A
6995A
6995A
565
Department of Electrical and Electronic Engineering, East West University 6
5.9 Under Frequency Protection
An under frequency relay is one which operates when the frequency of the system falls below a
certain value. Overloading of a generator, perhaps due to loss of system generation and
insufficient load shedding, can lead to prolonged operation of the generator at reduced
frequencies. This can cause particular problems for gas or steam turbine generators, which are
susceptible to damage from operation outside of their normal frequency band. The turbine is
usually considered to be more restrictive than the generator at reduced frequencies because of
possible mechanical resonance in the many stages of the turbine blades. If the generator speed is
close to the natural frequency of any of the blades, there will be an increase in vibration.
Cumulative damage to the blades due to this vibration can lead to cracking of the blade structure
.While load-shedding is the primary protection against generator overloading, under frequency
relays should be used to provide additional protection. Alarm: 48 Hz.
575
Department of Electrical and Electronic Engineering, East West University 7
protection.
585
Department of Electrical and Electronic Engineering, East West University 8
100% 80%
7000V/5A
16KV/110V
44
Department of Electrical and Electronic Engineering, East West University
5.13 Rotor Earth Fault Protection
Two methods are available to detect this type of fault. The first method is suitable for generators
that incorporate brushes in the main generator field winding. The second method requires at least
a slip-ring connection to the field circuit.
Figure 5-9: Earth fault protection of field circuit by potentiometer method & the relay used in APSCL
In this part of my internship training Mr. XYZ (Meneger of Operation) was my instructor
where I worked 30 days. I visited all control rooms where entire power plant can be
controlled and supervised from the centered console and the large display panel in the main
control room.
Feed water and, therefore, steam flow is controlled to meet load demand by the turbine and at the
same time maintain the level of water in the steam drum within relatively narrow limits.
Normally, the water level in the drum is maintained half- full up to the diametric plane. High
steam consumption by the turbine, combined with low feed-water supply would lower the water
level in the drum. A three element automatic control system, of which the drum level is one
element, is shown in fig: () The Drum level sensor respond to the error between actual drum
level and its set point, such as in the case of high steam consumption and low feed-water supply,
and acts of the controller to increase the feed-water valve opening to meet the steam flow
demand. This action be too slow and is supplemented by sensor for feed-water and steam flow.
The difference between the signals from these two sensors anticipates changes in drum level and
sends a signal to the controller to actuate the valve in the desired direction.
Combustion Control
Combustion controls are used to adjust the amount o air and fuel supplied to the furnace to
respond to the changes in boiler steam pressure. Three combustion controls are on-off,
positioning, metering.
On-off controls, the simplest, are used on fire-tube and small water-tube boilers. The on-off
control system supplies a pre- determined amount of fuel and air. On-off controls cannot supply
a steady steam pressure because they work on a cyclic basis.
Positioning controls, used on many boilers, are more flexible and can provide better combustion
efficiency than can on-off controls. These controls operate on a continuous basis, providing
smoother changes in fuel and air feed allowing the boiler to maintain a more uniform steam
pressure. The amount of air and fuel feed can be adjusted manually to change the air to fuel ratio.
Safety Valve
Safety valves can also be popped manually by using hand levers. For large boilers, each super-
heater and re-heater will have one or more safety valves. The safety valves are located near the
outlets of these tube sections.
Pressure gauge
In APSCL, pressure gauges are used to measure steam and water pressure in steam drums, feed-
water heaters, steam headers, and other boiler equipment.
The Bourdon tube is the most common gauge used on a boiler. It consists of a curved tube that is
sealed at one end. The sealed end is connected to a pointer by linkage.
The open end of the gauge is the pressure connection. As pressure increases in the tube, the tube
straightens out, moving the pointer. As the pressure decreases the tube returns to the normal
curved position. Bourdon pressure gauges can measure pressures of steam, air, oil, water, or
other fluids. These gauges require careful handling and proper maintenance to keep them
operating accurately. They should be removed from their mountings, disassembled and cleaned
with a suitable regularly.
Steam gauges for a small boiler are usually mounted on top of the water column. The gauge will
directly read the pressure of the boiler. In many boilers, so that they can easily be reads by the
operator. At this level, the true steam pressure is the value read of the gauge minus the hydraulic
head. For each foot of vertical distance between the connection at the drum and the ground level,
the gauge reading must be corrected by subtracting a value of 0.433 psi per foot of head.
Gaugescan also be mounted above the point of pressure measurement. In this case the pressure
due to the hydraulic head must be added to the gauge reading.
Flame detector
Flame detectors, or scanners, monitor burner flames on all boilers and ignitors on coal or natural
gas and oil- fired boilers. If the flame in a burner or ignitor goes out, a flame detector sends a
signal to the fuel feed controls that automatically stop the flow of fuel into the boiler. Thus, the
boiler is prevented from operation or igniting while explosive conditions in the furnace exist.
Three flame detectors used of boilers are photocell, ultraviolet, and infrared detectors. Photocells
detect visible light, ultraviolet sensors detect ultraviolet light, and infrared sensors detect infrared
light in the burner flame or ignitor. These devices are installed in the furnace wall as shown in
figure.
Fire alarm
There are several fire alarms in APSCL for emergency purpose. If any accident happens then any
one of operators should press the fire alarm button which blow the alarm that indicates that an
accident occurred
.
Control of gas turbine
The purpose of gas turbine controls is to meet the specific control requirements of users and safe
operation of the turbine. Which is given below:-
Excessive vibration
A slight increase in vibration is a cause of warning. Protection against vibration is accomplished
by stalling one or moves vibration pick-ups. The output signal is fed to a monitoring device,
which may shut down the turbine if the vibration increases a certain value.
CHAPTER - 7 Conclusion
My achievements
Before internship I knew many theories and working principles of power system and related
equipments but from internship I acquired practical knowledge about power system engineering
and its equipment. Here, I always tried to relate my academic courses with practical participation
of power generation process. Beside I also faced some practical problems which was not taught
in my academic courses. My communication skill also improved through communication with
different instructor. Therefore, I made good achievements with my industrial training which will
help me in my future.
Problem faced
There are some problems which I faced during internship period. The problems are given below –
i. My instructor at XYZ showed me every equipment practically but did not relate with
theory most of the times
ii. Practical participation in different works of XYZ would give more experience but
practical participation was not allowed for internship student
iii. Company did not provide me enough data for security purpose.
Recommendations
Some recommendations are given below for the students to do their internship program in a
better way –
i. The internship program should be scheduled in such a way so that it does not clash
with the university classes.
ii. More theoretical knowledge about power generation, protection system, power
equipments should be learnt before going for internship. Hence students must
complete the related courses to their internship before joining the program. Taking
the courses before the internship helps the students understand the topic much better.
Discussion
In case of power generation, XYZ is the combination of steam, gas and combined cycle plant.
Last 26th December I went to XYZ Power Station Company ltd. for my internship program. I
visited steam power plant, I observed how water is collected, purified and then boiled to
produce steam. There are several switch gear and control rooms to control the overall system of
producing steam and power generation. Various types of relays used for protective purposes that
are also controlled in control room. I visited gas turbine of XYZ. There I have seen how fresh
air and natural gas supplied by TITAS GAS are used as fuel to burn. After burning, produced hot
gas used to rotate the turbine as well as power generation. For protective measures relays are also
used and controlled in switch gear room. After gas turbine, I visited combined cycle power plant
(CCPP). Here the exhausted hot gas is being used to boil water for producing steam. I visited the
distribution section of XYZ. In sub-station, stepped up or down of voltages is being done
using transformers and power is distributed. Different types of isolators are being used for
maintenance purpose of transmission lines.
The authorities in XYZ were very concerned about all kinds of safety. The friendly
environment in XYZ encouraged me to co-operate with each other. I learned a lot and obtained
practical knowledge from my internship at XYZ, which will help me in my future life.
59
Department of Electrical and Electronic Engineering, East West University
References:
59
Department of Electrical and Electronic Engineering, East West University