Software Development Plan
Software Development Plan
Duration
Start
Finish
Predecessors
Resource Names
S
0
1
7
17
25
32
48
57
67
74
81
86
3,5 days
14 days
14,5 days
Development
21,75 days
Testing
48,75 days
Training
45,75 days
Documentation
30,5 days
Pilot
70,25 days
Deployment
5 days
Post Implementation 3 days
Review development 0 days
Software
template complete
Mon
02 Jan '00
S
M
T
09 Jan '00
S
M
T
16 Jan '00
S
M
T
23 Jan '00
S
M
T
30 Jan '00
S
M
T
Mon
Task
Summary
Inactive Milestone
Duration-only
Start-only
External Milestone
Split
Project Summary
Inactive Summary
Finish-only
Deadline
Milestone
Inactive Task
Manual Task
Manual Summary
External Tasks
Progress
Page 1
Manual Progress
06 Feb '00
S
M
T
13 Feb '00
S
M
T
20 Feb '00
S
M
T
27 Feb '00
S
M
T
05 Mar '00
S
M
T
12 Mar '00
S
M
T
19 Mar '00
S
M
T
26 Mar '00
S
M
T
02 Apr '00
S
M
T
09 Apr '00
S
M
T
16 Apr '00
S
M
T
23 Apr '00
S
M
T
30 Apr '00
S
M
T
07 May '00
S
M
T
14 May '00
S
M
T
15/05
Task
Summary
Inactive Milestone
Duration-only
Start-only
External Milestone
Split
Project Summary
Inactive Summary
Finish-only
Deadline
Milestone
Inactive Task
Manual Task
Manual Summary
External Tasks
Progress
Page 2
Manual Progress